  • 1.0 ESTRUCTURA DEL CONTRATO PRINCIPAL

    TOTAL MONTO CONTRATADO 1,122,869.82

    TOTAL MONTO DEDUCTIVO 0.00

    TOTAL MONTO EJECUTADO DEL CONTRATO PRINCIPAL 1,122,869.82

    SUBTOTAL IGV TOTAL

    CONTRATO PRINCIPAL 943,588.08 179,281.74 1,122,869.82

    REAJUSTE 26,603.17 5,054.60 31,657.77

    SUB TOTAL 970,191.25 184,336.34 1,154,527.59

    TOTAL GENERAL 970,191.25 184,336.34 1,154,527.59

    SON :

    2.0 CALENDARIO PROGRAMADO (SIN IGV)

    . Del 01.07.09 al 30.07.09 349,970.59 (Valorizacin N 01)

    . Del 01.08.09 al 31.08.09 164,697.81 (Valorizacin N 02)

    . Del 01.09.09 al 30.09.09 281,109.07 (Valorizacin N 03)

    . Del 01.10.09 al 31.10.09 147,810.61 (Valorizacin N 04)

    TOTAL 943,588.09

    3.0 CALENDARIO Y VALORIZACION ( SIN IGV)

    SEGN LA OBRA PRINCIPAL

    . Del 01.07.09 al 30.07.09 349,970.60 (Valorizacin N 01)

    . Del 01.08.09 al 31.08.09 187,339.53 (Valorizacin N 02)

    . Del 01.09.09 al 30.09.09 324,143.25 (Valorizacin N 03)

    Del 01.10.09 al 31.10.09 82,134.70 (Valorizacin N 04)

    TOTAL 943,588.09

    CAPITULO IV CALENDARIO DE OBRA