01_cronograma de Ejecución de Obra

Embed Size (px)

Citation preview

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    1/8

    Id Nombre de tarea Duracin Comienzo Fin

    1 CONTRUCCIN DE 02 AULAS + DIRECCIN 46 das lun 03/08/15 lun 05/10/15

    2 ESTRUCTURAS 44.5 das lun 03/08/15 vie 02/10/15

    3 OBRAS PROVISIONALES 1.5 das lun 03/08/15 mar 04/08/15

    4 CART EL DE IDENT IF ICACIO N DE LA OBRA DE 3.60 1 da l un 03/08/15 lun 03/08/15

    5 CASETA ADIC IONAL P/GUARDIANIA Y/O DEPOSIT 1.5 d as lun 03 /08/15 mar 04/08 /15

    6 OBRAS PRELIMINARES 2 das mar 04/08/15 jue 06/08/15

    7 PERFILADO E = 0.15 M 1 da mar 04/08/15 mi 05/08/15

    8 LIMPIEZA DE TERRENO MANUAL 1 da mi 05/08/15 jue 06/08/159 TRAZO Y REPLANTEO 1 da mi 05/08/15 jue 06/08/15

    10 MOVIMIENTO DE TIERRAS 41 das jue 06/08/15 vie 02/10/15

    11 EXCAVACION DE ZANJAS PARA CIMIENTOS 2 das jue 06/08/15 lun 10/08/15

    12 CO RT E DE TERRENO PARA AF IRMADO E = 5 CM. 2 das vi e 07/08/15 m ar 11/08/15

    13 RELLENO CON MATERIAL PROPIO 2 das vie 11/09/15 mar 15/09/15

    14 RELLENO CON MATERIAL DE PRESTAMO MANUA 2 das mar 15/09/15 jue 17/09/15

    15 NIVELACION INTERIOR APISONADO MANUAL PRE 2 das jue 17 /09/15 lun 21 /09/15

    16 ELIMINACIO N DE MAT ERIAL EXCEDENT E CO N CA 4 das jue 17/09/15 mi 23/09/15

    17 RELLENO CON MATERIAL DE PRESTAMO (AFIRM 2 d as mi 30 /09/15 vie 02/10 /15

    18 OBRAS DE CONCRETO SIMPLE 38.5 das lun 03/08/15 jue 24/09/15

    19 SOLADO PARA ZAPAT AS DE 4" F C = 100 KG/CM2 1 da m ar 11/08/15 m i 12/08/ 15

    20 FALSO PISO DE 4" DE CONCRETO 1:10 1 da mi 23/09/15 jue 24/09/1521 CO NCRET O CICLOPEO FC=140KG/CM2 + 30 % P 2 das l un 17/08/15 m i 19/08/ 15

    22 CONCRET O PARA VEREDAS F'C=140 KG/CM2 2 das mi 05/08/15 jue 06/08/15

    23 ENCO FRADO Y DESENCO FRADO DE VEREDAS 2 das l un 03/08/15 m ar 04/08/15

    24 JUNTAS ASFALTICAS 1 da vie 07/08/15 vie 07/08/15

    25 OBRAS DE CONCRETO ARMADO 37.5 das lun 10/08/15 mi 30/09/15

    26 ZAPATAS 3 das mi 12/08/15 lun 17/08/15

    27 CONCRETO PARA ZAPAT AS F'C=210 KG/CM2 1 da vie 14/08/15 lun 17/08/15

    28 ACERO ESTRUCTURAL TRABAJADO PARA ZA 1 da mi 12/08/15 jue 13/08/15

    29 VIGAS DE CONEXIN 5 das lun 17/08/15 lun 24/08/15

    30 CONCRETO PARA VIGAS DE CONEXIN F 'C=2 2 d as jue 20 /08/15 lun 24/08/15

    31 ENCOFRADO Y DESENCOFRADO DE VIGAS D 2 das mar 18/08/15 jue 20/08/15

    32 ACERO ESTRUCTURAL TRABAJADO PARA VIG 2 das lun 17/08/15 mi 19/08/1533 SOBRECIMIENTO REFORZADO 5 das lun 24/08/15 lun 31/08/15

    34 CONCRETO EN SOBRECIMIENTO REFORZADO 2 das jue 27/08/15 lun 31/08/15

    S D L M X J V S D L M X J V S D L M X J

    02 ago '15 09 ago '15 16 ago '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 1

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    2/8

    Id Nombre de tarea Duracin Comienzo Fin

    35 ENCOFRADO Y DESENCOFRADO DE SOBRECI 2 d as mar 25 /08/15 jue 27/08/15

    36 ACERO ESTRUCTURAL TRABAJADO PARA SO 2 das lun 24/08/15 mi 26/08/15

    37 COLUMNAS 22 das mi 12/08/15 vie 11/09/15

    38 CONCRET O PARA CO LUMNAS F'C=210 KG /CM 2 das m i 09/09/15 vie 11/09/15

    39 ENCO FRADO Y DESENCOF RADO DE CO LUMN 2 das l un 07/09/15 m i 09/09/ 15

    40 ACERO ESTRUCTURAL TRABAJADO PARA CO 2 das mi 12/08/15 vie 14/08/15

    41 VIGAS 4 das jue 24/09/15 mi 30/09/15

    42 CONCRETO PARA VIGAS F'C=210 KG/CM2 2 das lun 28/09/15 m i 30/09/1543 ENCOFRADO Y DESENCOFRADO NORMAL EN 2 das jue 24/09/15 lun 28/09/15

    44 ACERO ESTRUCTURAL TRABAJADO PARA VIG 2 das jue 24/09/15 lun 28/09/15

    45 CANALETA PARA DRENAJE 6 das lun 10/08/15 lun 17/08/15

    46 CONCRET O PARA CANALET A F'C=140 KG/CM2 2 das vi e 14/08/15 lun 17/08/15

    47 ENCO FRADO Y DESENCOF RADO DE CANALE 2 das l un 10/08/15 m ar 11/08/15

    48 ACERO ESTRUCTURAL TRABAJADO PARA CA 2 das mi 12/08/15 jue 13/08/15

    49 ARQUITECTURA 45.5 das lun 03/08/15 lun 05/10/15

    50 MURO Y TABIQUES DE ALBAILERIA 5 das lun 31/08/15 lun 07/09/15

    51 MURO DE SOG A LADRILLO KING -KO NG CO N CEM 5 das l un 31/08/15 lun 07/09/15

    52 MURO DE CABEZA LADRILLO KING-KONG CON CE 2 d as jue 03 /09/15 lun 07/09/15

    53 ACERO EN MUROS 5 das lun 31/08/15 lun 07/09/15

    54 REVOQUES ENLUCIDOS Y MOLDURAS 5 das mar 11/08/15 lun 17/08/1555 T ARRAJ EO INT ERIOR C/MO RT ERO 1:4 X1.5 CM 4 das m ar 11/08/15 vie 14/08/15

    56 TARRAJEO EN EXTERIOR C /MORTERO 1 :4 X 1 .5C 4 d as mi 12 /08/15 lun 17/08/15

    57 TARRAJEO DE SUPERF. COLUMNAS, MURO COR 4 d as mi 12 /08/15 lun 17/08/15

    58 CIELORRASOS 4 das lun 17/08/15 jue 20/08/15

    59 CIELO RASO CON PLANCHA FIBROCEMENTO E = 4 das lun 17/08/15 jue 20/08/15

    60 FRISO DE MADERA DE 1"X20" 4 das lun 17/08/15 jue 20/08/15

    61 PISOS Y PAVIMENTOS 26.5 das mi 26/08/15 jue 01/10/15

    62 CONTRAPISO DE 48 MM. 1 da mi 30/09/15 jue 01/10/15

    63 PISO S DE CEMENT O PULIDO COLO READO E = 2" 2 das m i 26/08/15 jue 27/08/15

    64 CONTRAZOCALOS 3 das vie 14/08/15 mar 18/08/15

    65 CONTRAZOCALO DE CEMENTO PULIDO C /MORT 3 d as vie 14 /08/15 mar 18/08 /15

    66 REVESTIMIENTOS 2 das jue 03/09/15 lun 07/09/1567 BRUAS DE 1c m. 2 das j ue 03/09/15 lun 07/09/15

    68 CUBIERTAS 6 das lun 03/08/15 lun 10/08/15

    S D L M X J V S D L M X J V S D L M X J

    02 ago '15 09 ago '15 16 ago '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 2

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    3/8

    Id Nombre de tarea Duracin Comienzo Fin

    69 COBERTURA DE TEJA ANDINA 4 das mi 05/08/15 lun 10/08/15

    70 CUMBRERA DE TEJA ANDINA 2 das lun 03/08/15 mar 04/08/15

    71 CARPINTERIA DE MADERA 1 da mi 26/08/15 mi 26/08/15

    72 PUERTA DE MADERA TIPO 1 1 da mi 26/08/15 mi 26/08/15

    73 VENTANAS DE MADERA 2 das mi 26/08/15 jue 27/08/15

    74 VENTANA DE MADERA TIPO 1 1 da mi 26/08/15 mi 26/08/15

    75 VENTANA DE MADERA TIPO 2 1 da mi 26/08/15 mi 26/08/15

    76 VENTANA DE MADERA TIPO 3 1 da jue 27/08/15 jue 27/08/1577 VENTANA DE MADERA TIPO 4 1 da jue 27/08/15 jue 27/08/15

    78 VENTANA DE MADERA TIPO 5 1 da jue 27/08/15 jue 27/08/15

    79 TICERO DE MADERA 1 da jue 20/08/15 jue 20/08/15

    80 TICERO DE MADERA CEDRO CEPILLADO BARNIZ 1 da jue 20/08/15 jue 20/08/15

    81 MARCO DE MADERA 2 das vie 21/08/15 lun 24/08/15

    82 MARCO DE MADERA CEDRO CEPILLADO BARNIZ 1 da vie 21/08/15 vie 21/08/15

    83 PIZARRA ACRILICA 1 da lun 24/08/15 lun 24/08/15

    84 ESTRUCTURA TIJERAL DE MADERA 2 das jue 01/10/15 lun 05/10/15

    85 TIJERAL DE MADERA PARA CUBIERTA 1 da jue 01/10/15 vie 02/10/15

    86 ANCLAJE TIJERAL DE MADERA 1 da jue 01/10/15 vie 02/10/15

    87 CORREA DE MADERA 3"X3" 1 da vie 02/10/15 lun 05/10/15

    88 CARPINTERIA METALICA 7 das mar 18/08/15 mi 26/08/1589 REJILLA METALICA PARA DRENAJE 1 da mar 18/08/15 mar 18/08/15

    90 VARILLA LISA DE FIERRO 1/2" P/VENT ANAS 2 das m ar 25/08/15 m i 26/08/ 15

    91 CERRAJERIA 2 das mar 25/08/15 mi 26/08/15

    92 BISAGRA CAPUCHINA DE 4" X 4" 1 da mi 26/08/15 mi 26/08/15

    93 CERRADURA PARA PUERT A PRINCIPAL PESADA 1 da m i 26/08/15 m i 26/08/ 15

    94 BISAGRA CAPUCHINA PARA VENTANAS 1 da mi 26/08/15 mi 26/08/15

    95 MANIJA DE BRONCE PARA VENTANAS 1 da mar 25/08/15 mar 25/08/15

    96 VIDRIOS, CRISTALES Y SIMILARES 2 das jue 27/08/15 vie 28/08/15

    97 VIDRIOS SEMIDOBLES INCOLORO CRUDO 2 das jue 27/08/15 vie 28/08/15

    98 PINTURA 5 das vie 21/08/15 jue 27/08/15

    99 PINT URA VINILICA EN CIELO RASO 2 MANOS 2 das vie 21/08/15 lun 24/08/15

    100 PINTURA VIN IL ICA EN MUROS INTERIORES 2 MAN 2 d as vie 21 /08/15 lun 24/08/15101 PINTURA VIN IL ICA EN MUROS EXTERIORES 2 MA 2 d as lun 24 /08/15 mar 25/08 /15

    102 PINTURA EN PUERTAS C/BARNIZ 2 MANOS 1 da mi 26/08/15 mi 26/08/15

    S D L M X J V S D L M X J V S D L M X J 02 ago '15 09 ago '15 16 ago '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 3

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    4/8

    Id Nombre de tarea Duracin Comienzo Fin

    103 PINT URA DE VENT ANAS CON BARNIZ MARINO 1 da mar 25/08/15 m ar 25/08/15

    104 PINT URA DE VENT ANAS DE FIERRO CON ESMALT 1 da j ue 27/08/15 jue 27/08/15

    105 JUNTAS 9.5 das mi 26/08/15 mar 08/09/15

    106 JUNTAS 1" TPICO CON ESPUMA PLASTICA 5 das mar 01/09/15 mar 08/09/15

    107 JUNT AS 1 CM DE SILICONA DE COLO R MARR N 2 das m i 26/08/15 jue 27/08/15

    108 INSTALACIONES SANITARIAS 3 das mar 11/08/15 jue 13/08/15

    109 SISTEMA DE AGUA DE LLUVIA 3 das mar 11/08/15 jue 13/08/15

    110 CANALETA SEMICIRCULAR P/AGUA PLUVIALES PL 2 das mar 11/08/15 mi 12/08/15111 MONTAJE P/DRENAJE PLUVIAL CON TUBERIA DE 2 das mi 12/08/15 jue 13/08/15

    112 DADO DE CONCRETO PARA PROTECCIN TUBER 2 das mi 12/08/15 jue 13/08/15

    113 INSTALACIONES ELECTRICAS 13.5 das jue 20/08/15 mar 08/09/15

    114 SALIDA PARA CENTROS DE LUZ EN TECHO 1 da jue 20/08/15 jue 20/08/15

    115 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CO 1 da lun 07/09/15 mar 08/09/15

    116 CAJA DE PASE 200 X 200 X 100 MM 1 da jue 20/08/15 jue 20/08/15

    117 RED DE DISTRIBUCIN ELECTRICA 1 da jue 20/08/15 jue 20/08/15

    118 TABLERO ELECTRICO GAB.METALICO P/DISTRIBUCI 1 da vie 21/08/15 vie 21/08/15

    119 FLUORESCENTE RECTO ISPE 2 X 40 W INCLUYENDO 1 da mi 26/08/15 mi 26/08/15

    120 POZO DE PUESTA A TIERRA 1 da jue 20/08/15 jue 20/08/15

    121 VARIOS 33 das lun 17/08/15 jue 01/10/15

    122 LIMPIEZA FINAL DE OBRA 1 da lun 31/08/15 lun 31/08/15123 CONTROL DE CALIDAD 4 das lun 17/08/15 jue 01/10/15

    124 FLETE 46 das lun 03/08/15 lun 05/10/15

    125 FLETE TERRESTRE 3 das lun 03/08/15 lun 05/10/15

    S D L M X J V S D L M X J V S D L M X J

    02 ago '15 09 ago '15 16 ago '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 4

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    5/8

    V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M23 ago '15 30 ago '15 06 sep '15 13 sep '15 20 sep '15 27 sep '15 04 oct '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 5

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    6/8

    V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M23 ago '15 30 ago '15 06 sep '15 13 sep '15 20 sep '15 27 sep '15 04 oct '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 6

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    7/8

    V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M23 ago '15 30 ago '15 06 sep '15 13 sep '15 20 sep '15 27 sep '15 04 oct '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 7

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16

  • 7/25/2019 01_cronograma de Ejecucin de Obra

    8/8

    V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M23 ago '15 30 ago '15 06 sep '15 13 sep '15 20 sep '15 27 sep '15 04 oct '15

    Tarea

    Divisin

    Hito

    Resumen

    Resumen del proyecto

    Tareas externas

    Hito externo

    Tarea inactiva

    Hito inactivo

    Hito inactivo

    Resumen inactivo

    Tarea manual

    solo duracin

    Informe de resumen manual

    Resumen manual

    solo el comienzo

    solo fin

    Tareas externas

    Hito externo

    Progreso

    Fecha lmite

    Pgina 8

    Proyecto: CRONOGRAMA DE JEFecha: mar 19/01/16