29
COSTO MINA AÑO 1 AÑO 2 AÑO 3 AÑO 4 AÑO 5 AÑO 6 AÑO 7 AÑO 8 AÑO 9 AÑO 10 AÑO 11 AÑO 12 AÑO 13 AÑO 14 AÑO 15 AÑO 16 AÑO 17 COSTO DOTACIÓN (KUS$/AÑO) 3,347 5,578 7,513 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 5,578 COSTO DOTACIÓN (US$/TON) 2.45 2.07 1.64 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 2.15 COSTO PRODUCCIÓN MINA (KUS$/AÑO) 3,790 6,808 10,026 11,548 11,548 11,548 11,548 11,548 11,548 11,548 13,013 13,013 13,013 13,013 13,013 13,013 7,575 COSTO PRODUCCIÓN MINA (US$/TON) 2.77 2.52 2.18 1.83 1.83 1.83 1.83 1.83 1.83 1.83 2.07 2.07 2.07 2.07 2.07 2.07 2.92 COSTO PREPARACIÓN MINA (KUS$/AÑO) 13,138 19,512 22,409 22,602 22,625 23,926 24,088 24,636 24,339 23,634 24,773 20,261 24,875 20,597 17,479 8,426 1,017 COSTO PREPARACIÓN MINA (US$/TON) 9.60 7.23 4.88 3.59 3.59 3.80 3.82 3.91 3.86 3.75 3.93 3.22 3.95 3.27 2.77 1.34 0.39 COSTO PLANTA CHANCADO / PIQUE SKIP (KUS$/AÑO) 1,924 3,410 5,407 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 3,556 COSTO PLANTA CHANCADO / PIQUE SKIP (US$/TON) 1.41 1.26 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.37 CONTINGENCIAS (5%) (KUS$/AÑO) 1,110 1,765 2,268 2,615 2,617 2,682 2,690 2,717 2,702 2,667 2,797 2,572 2,802 2,588 2,433 1,980 886 CONTINGENCIAS (5%) (US$/TON) 0.81 0.65 0.49 0.42 0.42 0.43 0.43 0.43 0.43 0.42 0.44 0.41 0.44 0.41 0.39 0.31 0.34 COSTO TOTAL MINA (KUS$/AÑO) 23,307 37,072 47,623 54,925 54,949 56,315 56,485 57,060 56,748 56,009 58,743 54,005 58,850 54,358 51,084 41,578 18,613 COSTO TOTAL MINA (US$/TON) 17.04 13.73 10.38 8.72 8.72 8.94 8.97 9.06 9.01 8.89 9.32 8.57 9.34 8.63 8.11 6.60 7.18

Costos Operación_ Planilla R1

Embed Size (px)

DESCRIPTION

ing civil

Citation preview

Page 1: Costos Operación_ Planilla R1

COSTO MINA AÑO 1 AÑO 2 AÑO 3 AÑO 4 AÑO 5 AÑO 6 AÑO 7 AÑO 8 AÑO 9 AÑO 10 AÑO 11 AÑO 12 AÑO 13 AÑO 14 AÑO 15 AÑO 16 AÑO 17

COSTO DOTACIÓN (KUS$/AÑO) 3,347 5,578 7,513 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 10,705 5,578

COSTO DOTACIÓN (US$/TON) 2.45 2.07 1.64 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 2.15

COSTO PRODUCCIÓN MINA (KUS$/AÑO) 3,790 6,808 10,026 11,548 11,548 11,548 11,548 11,548 11,548 11,548 13,013 13,013 13,013 13,013 13,013 13,013 7,575

COSTO PRODUCCIÓN MINA (US$/TON) 2.77 2.52 2.18 1.83 1.83 1.83 1.83 1.83 1.83 1.83 2.07 2.07 2.07 2.07 2.07 2.07 2.92

COSTO PREPARACIÓN MINA (KUS$/AÑO) 13,138 19,512 22,409 22,602 22,625 23,926 24,088 24,636 24,339 23,634 24,773 20,261 24,875 20,597 17,479 8,426 1,017

COSTO PREPARACIÓN MINA (US$/TON) 9.60 7.23 4.88 3.59 3.59 3.80 3.82 3.91 3.86 3.75 3.93 3.22 3.95 3.27 2.77 1.34 0.39

COSTO PLANTA CHANCADO / PIQUE SKIP (KUS$/AÑO) 1,924 3,410 5,407 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 7,455 3,556

COSTO PLANTA CHANCADO / PIQUE SKIP (US$/TON) 1.41 1.26 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.37

CONTINGENCIAS (5%) (KUS$/AÑO) 1,110 1,765 2,268 2,615 2,617 2,682 2,690 2,717 2,702 2,667 2,797 2,572 2,802 2,588 2,433 1,980 886

CONTINGENCIAS (5%) (US$/TON) 0.81 0.65 0.49 0.42 0.42 0.43 0.43 0.43 0.43 0.42 0.44 0.41 0.44 0.41 0.39 0.31 0.34

COSTO TOTAL MINA (KUS$/AÑO) 23,307 37,072 47,623 54,925 54,949 56,315 56,485 57,060 56,748 56,009 58,743 54,005 58,850 54,358 51,084 41,578 18,613

COSTO TOTAL MINA (US$/TON) 17.04 13.73 10.38 8.72 8.72 8.94 8.97 9.06 9.01 8.89 9.32 8.57 9.34 8.63 8.11 6.60 7.18

Page 2: Costos Operación_ Planilla R1

Turnos/Día 3

Turnos/Totales 4

Dotación MinaDotación Tarifas Tarifas

Dotación/Turno Dotación Total KUS$/Mes KUS$/Año1.- Gerencia Mina 2 2Gerente Mina 1 1 8.5 102.0Secretaria 1 1 1.5 18.0Sub-Total (1) 2 22.- Superintendencia Ingeniería, Geología y Geomecánica 18 19Superintendente Mina 1 1 7.0 84.0Ingenieros Planificación 3 3 5.0 60.0Geólogos 2 2 5.0 60.0Geomecánicos 1 1 5.0 60.0Ayudantes Geologo 2 2 3.0 36.0Proyectistas/Dibujantes 3 3 2.5 30.0Topografos 2 2 2.5 30.0Alarifes 2 2 1.5 18.0Laboratoristas 1 1 2.5 30.0Ayudante Laboratorio (Muestrero) 1 2 1.5 18.0Sub-Total (2) 18 193.- Superintendencia Producción Mina 27 91Superintendente Producción 1 1 7.0 84.0Supervisor Producción 1 4 5.5 66.0Supervisor Chancado y Skip 1 4 5.5 66.0Supervisor Perforación y Tronadura Producción 1 4 5.5 66.0Operadores Cargadores Frontales Sala Control 2 8 3.0 36.0Operadores Camiones Sala Control 2 8 3.0 36.0Operadores Perforadoras Radiales Sala Control 1 4 3.0 36.0Operadores Chancador y Skip Sala Control 1 4 3.0 36.0Operadores Perforadoras Radiales Terreno 3 12 3.0 36.0Operador Equipo Tronadura 2 8 2.5 30.0Operadores Equipos Apoyo 6 12 2.5 30.0Operadores Ayudante Producción 3 12 2.0 24.0Ayudantes Tronadura Producción 2 8 2.0 24.0Control Producción 1 2 3.5 42.0Sub-Total (3) 27 914.- Superintendencia Construcción y Preparación 18 67Superintendente Construcción y Preparación 1 1 7.0 84.0Supervisor Preparación 1 4 5.5 66.0Operador Jumbo Avance 3 12 2.5 30.0Operador LHD Preparación 3 12 2.5 30.0Capataz Tronadura Avance 1 4 3.5 42.0Mineros Tronadura 1 4 2.0 24.0Operador Shotcretera 1 4 2.5 30.0Operador Empernador 1 4 2.5 30.0Mineros Fortificación 1 4 2.0 24.0Operador Equipo Servicio 1 4 2.5 30.0Mineros Servicios 1 4 2.0 24.0Inspector Construcción ITO 1 4 3.0 36.0Ayudante Inspector Construcción ITO 1 4 2.5 30.0Geomecánicos Terreno 1 2 4.0 48.0Sub-Total (4) 18 675.- Superintendencia Mantención Mina 19 73Superintendencia Mantención 1 1 7.0 84.0Supervisor Mecánico 1 4 5.5 66.0Supervisor Eléctrico e Instrumentación 1 4 5.5 66.0Mantenedores Mecánicos 6 24 2.5 30.0Mantenedores Eléctricos 3 12 2.5 30.0Mantenedores Instrumentación 2 8 2.5 30.0Mantenedores Planta Chancado 2 8 2.5 30.0Mantenedores Pique Skip y Correas 2 8 2.5 30.0Pañolero 1 4 2.5 30.0Sub-Total (5) 19 736.-Subgerencia Seguridad y Medio Ambiente 4 4Subgerente Seguridad y Medio Ambiente 1 1 4.0 48.0Prevencionista 2 2 3.5 42.0Medio Ambientalista 1 1 3.5 42.0Sub-Total (6) 4 47.- Unidad de Soporte y Mantención 5 11Jefe Unidad 1 1 4.0 48.0Ingeniero de Soporte 1 4 3.0 36.0Ingeniero Mantención 2 2 3.0 36.0Ingeniero Desarrollo 1 4 2.5 30.0Sub-Total (7) 5 11

TOTAL DOTACIÓN MINA 93 267

Page 3: Costos Operación_ Planilla R1

Dotación Mina AÑO 1 AÑO 2 AÑO 3 AÑO 4 AÑO 5 AÑO 6 AÑO 7 AÑO 8 AÑO 9 AÑO 10 AÑO 11 AÑO 12 AÑO 13 AÑO 14 AÑO 15 AÑO 16 AÑO 17

1.- Gerencia MinaGerente Mina 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Secretaria 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Sub-Total (1) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 22.- Superintendencia Ingeniería, Geología y Geomecánica 19

Superintendente Mina 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 7

Ingenieros Planificación 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 15

Geólogos 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 10

Geomecánicos 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5

Ayudantes Geologo 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 1 6

Proyectistas/Dibujantes 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 7.5

Topografos 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 5

Alarifes 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 3

Laboratoristas 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2.5

Ayudante Laboratorio (Muestrero) 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 3

Sub-Total (2) 10 13 18 19 19 19 19 19 19 19 19 19 19 19 19 19 133.- Superintendencia Producción Mina 91

Superintendente Producción 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Supervisor Producción 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Supervisor Chancado y Skip 1 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Supervisor Perforación y Tronadura Producción 1 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 1

Operadores Cargadores Frontales Sala Control 2 4 6 8 8 8 8 8 8 8 8 8 8 8 8 8 4

Operadores Camiones Sala Control 2 4 6 8 8 8 8 8 8 8 8 8 8 8 8 8 4

Operadores Perforadoras Radiales Sala Control 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Operadores Chancador y Skip Sala Control 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Operadores Perforadoras Radiales Terreno 4 6 8 12 12 12 12 12 12 12 12 12 12 12 12 12 6

Operador Equipo Tronadura 2 3 4 8 8 8 8 8 8 8 8 8 8 8 8 8 3

Operadores Equipos Apoyo 1 6 8 12 12 12 12 12 12 12 12 12 12 12 12 12 6

Operadores Ayudante Producción 1 6 8 12 12 12 12 12 12 12 12 12 12 12 12 12 6

Ayudantes Tronadura Producción 2 3 4 8 8 8 8 8 8 8 8 8 8 8 8 8 3

Control Producción 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1

Sub-Total (3) 21 43 59 91 91 91 91 91 91 91 91 91 91 91 91 91 434.- Superintendencia Construcción y PreparaciónSuperintendente Construcción y Preparación 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Supervisor Preparación 1 1 3 4 4 4 4 4 4 4 4 4 4 4 4 4 1

Operador Jumbo Avance 3 6 9 12 12 12 12 12 12 12 12 12 12 12 12 12 6

Operador LHD Preparación 3 6 9 12 12 12 12 12 12 12 12 12 12 12 12 12 6

Capataz Tronadura Avance 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Mineros Tronadura 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Operador Shotcretera 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Operador Empernador 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Mineros Fortificación 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Operador Equipo Servicio 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Mineros Servicios 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Inspector Construcción ITO 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Ayudante Inspector Construcción ITO 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Geomecánicos Terreno 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1

Sub-Total (4) 18 33 51 67 67 67 67 67 67 67 67 67 67 67 67 67 335.- Superintendencia Mantención MinaSuperintendencia Mantención 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Supervisor Mecánico 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Supervisor Eléctrico e Instrumentación 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Mantenedores Mecánicos 4 8 10 24 24 24 24 24 24 24 24 24 24 24 24 24 8

Mantenedores Eléctricos 4 8 10 12 12 12 12 12 12 12 12 12 12 12 12 12 8

Mantenedores Instrumentación 2 4 4 8 8 8 8 8 8 8 8 8 8 8 8 8 4

Mantenedores Planta Chancado 2 4 4 8 8 8 8 8 8 8 8 8 8 8 8 8 4

Mantenedores Pique Skip y Correas 2 4 4 8 8 8 8 8 8 8 8 8 8 8 8 8 4

Pañolero 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Sub-Total (5) 18 35 42 73 73 73 73 73 73 73 73 73 73 73 73 73 356.-Subgerencia Seguridad y Medio AmbienteSubgerente Seguridad y Medio Ambiente 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Prevencionista 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 1

Medio Ambientalista 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Sub-Total (6) 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 37.- Unidad de Soporte y MantenciónJefe Unidad 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Ingeniero de Soporte 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Ingeniero Mantención 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1

Ingeniero Desarrollo 1 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 2

Sub-Total (7) 4 6 9 11 11 11 11 11 11 11 11 11 11 11 11 11 6

TOTAL DOTACIÓN MINA 76 135 184 267 267 267 267 267 267 267 267 267 267 267 267 267 135

Page 4: Costos Operación_ Planilla R1

AÑO 1 AÑO 2 AÑO 3 AÑO 4 AÑO 5 AÑO 6 AÑO 7 AÑO 8 AÑO 9 AÑO 10 AÑO 11 AÑO 12 AÑO 13 AÑO 14 AÑO 15 AÑO 16 AÑO 17

Extracción Mina

Material (Tpd) 3,800 7,500 12,750 17,500 17,500 17,500 17,500 17,500 17,500 17,500 17,500 17,500 17,500 17,500 17,500 17,500 7,200

Equipos Producción

Camión Bajo Pefil (50 Toneladas) 1 2 3 4 4 4 4 4 4 4 6 6 6 6 6 6 2

Cargador LHD (12 Toneladas) 1 3 5 6 6 6 6 6 6 6 6 6 6 6 6 6 3

Perforadora Radial (3") 1 2 4 6 6 6 6 6 6 6 6 6 6 6 6 6 2

Camión Cargador de Explosivos 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2

Martillo Móvil 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Camión Aljibe 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Camión Petrolero 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Camión Utilitario 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Total Equipos Producción 8 17 23 27 27 27 27 27 27 27 29 29 29 29 29 29 17

Equipos Preparaciones

Cargador Bajo Pefil (LHD) 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Perforadora Avance 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

Shotcretera 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Equipos Empernador 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Acuñador 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Total Equipos Preparación 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14

Page 5: Costos Operación_ Planilla R1

PERFORACIÓN RADIAL 3" TRONADURA RADIAL 3"

Perforación Requerida/Año 528,517 mb/año Perforación Requerida/Año 528,517 mb/añoDiámetro Perforación (3") 7.62 cm

EQUIPOS CANTIDAD COSTO COSTO EQUIPOS Rend. COSTO COSTOmb/hr US$/hr US$/mb mb/hr US$/hr US$/mb

JUMBO RADIAL 3" 21.70 50.32 2.32 CARGADOR EXPLOSIVO 50.00 34.17 0.68TOTAL EQUIPOS 2.32 TOTAL EQUIPOS 0.68

MATERIALES VIDA ÚTIL VALOR COSTO EXPLOSIVOS CONSUMO VALOR COSTOmb US$/un US$/mb un/mb US$/un US$/mb

BARRAS 6' 800 150 2.63 ANFO (kg) 1.8 1.00 1.80BITS 3" 450 700 1.56 TRONEX (un) 0.4 0.75 0.30CULATIN 1,100 200 0.18 FULMINANTE (un) 0.6 1.00 0.60COPLAS 200 150 9.75 NONEL (m) 0.4 0.50 0.20

TOTAL MATERIALES 14.11 CORDON DETONANTE (m) 2.0 0.35 0.70TOTAL MATERIALES 3.60

COSTO DIRECTO (US$/mb) 16.43COSTO DIRECTO (US$/mb) 4.28

Page 6: Costos Operación_ Planilla R1

CAMIÓN 50 TONITEM CANTIDAD UNIDAD

COMBUSTIBLECONSUMO 40 lt/hr

PRECIO 1.2 US$/ltCOSTO 48.00 US$/hr

LUBRICANTESCONSUMO (30% COMBUSTIBLE) 12 lt/hr

PRECIO 1.20 US$/ltCOSTO 14.40 US$/hr

NEUMATICOSVIDA UTIL 5,500 hr/setPRECIO 30,000 US$/setCOSTO 5.45 US$/hr

TOLVAVIDA UTIL 2,500 hr/unPRECIO 9,000 US$/unCOSTO 3.60 US$/hr

OTROS COSTOS(20% ANTERIORES) 14.29 US$/hr

COSTOS OPERACIÓN EQUIPO 85.75 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 26.97 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 21.58 US$/hr

RESUMENCOSTO OPERACIÓN 85.75 US$/hrCOSTO MANTENCION/REPARACION 26.97 US$/hrCOSTO OVERHAUL 21.58 US$/hr

TOTAL COSTO OPERACIÓN 134.29 US$/hr

Page 7: Costos Operación_ Planilla R1

LHD 12 TonITEM CANTIDAD UNIDAD

COMBUSTIBLECONSUMO 30 lt/hr

PRECIO 1.2 US$/ltCOSTO 36.00 US$/hr

LUBRICANTESCONSUMO (30% COMBUSTIBLE) 9 lt/hr

PRECIO 1.2 US$/ltCOSTO 10.80 US$/hr

NEUMATICOSCONSUMO 1,250 hr/set

PRECIO 7,000 US$/setCOSTO 5.6 US$/hr

BALDEVIDA UTIL 1,750 hr/unPRECIO 3,200 US$/unCOSTO 1.8 US$/hr

OTROS COSTOS(20% ANTERIORES) 10.85 US$/hr

COSTOS OPERACIÓN EQUIPO 65.07 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 27.33 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 21.86 US$/hr

RESUMENCOSTO OPERACIÓN 65.07 US$/hrCOSTO MANTENCION/REPARACION 27.33 US$/hrCOSTO OVERHAUL 21.86 US$/hr

TOTAL COSTO OPERACIÓN 114.26 US$/hr

Page 8: Costos Operación_ Planilla R1

JUMBO RADIAL 3"ITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 80 kwh

PRECIO 0.092 US$/kwhCOSTO 7.36 US$/hr

COMBUSTIBLECONSUMO 1 lt/hr

PRECIO 1.20 US$/ltCOSTO 1.20 US$/hr

LUBRICANTESCONSUMO (8% COMBUSTIBLE) 0.08 lt/hr

PRECIO 1.20 US$/ltCOSTO 0.10 US$/hr

NEUMATICOSCONSUMO 4,000 hr/set

PRECIO 4,000 US$/setCOSTO 1.0 US$/hr

AGUA INDUSTRIALCONSUMO 0.05 m3/hr

PRECIO 1.0 US$/m3COSTO 0.05 US$/hr

OTROS COSTOS(20% ANTERIORES) 1.94 US$/hr

COSTOS OPERACIÓN EQUIPO 11.64 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 21.49 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 17.19 US$/hr

RESUMENCOSTO OPERACIÓN 11.64 US$/hrCOSTO MANTENCION/REPARACION 21.49 US$/hrCOSTO OVERHAUL 17.19 US$/hr

TOTAL COSTO OPERACIÓN 50.32 US$/hr

Page 9: Costos Operación_ Planilla R1

MARTILLO MÓVILITEM CANTIDAD UNIDAD

COMBUSTIBLECONSUMO 10 lt/hr

PRECIO 1.2 US$/ltCOSTO 12.00 US$/hr

LUBRICANTESCONSUMO (30% COMBUSTIBLE) 3 lt/hr

PRECIO 1.20 US$/ltCOSTO 3.60 US$/hr

NEUMATICOSVIDA UTIL 3,000 hr/setPRECIO 5,000 US$/setCOSTO 1.7 US$/hr

CABEZALVIDA UTIL 5,000 hr/unPRECIO 8,000 US$/unCOSTO 1.6 US$/hr

OTROS COSTOS(15% ANTERIORES) 2.83 US$/hr

COSTOS OPERACIÓN EQUIPO 21.70 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 6.25 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 5.00 US$/hr

RESUMENCOSTO OPERACIÓN 21.70 US$/hrCOSTO MANTENCION/REPARACION 6.25 US$/hrCOSTO OVERHAUL 5.00 US$/hr

TOTAL COSTO OPERACIÓN 32.95 US$/hr

Page 10: Costos Operación_ Planilla R1

CAMIÓN EXPLOSIVOSITEM CANTIDAD UNIDAD

COMBUSTIBLECONSUMO 14 lt/hr

PRECIO 1.2 US$/ltCOSTO 16.80 US$/hr

LUBRICANTESCONSUMO (30% COMBUSTIBLE) 4 lt/hr

PRECIO 1.20 US$/ltCOSTO 5.04 US$/hr

NEUMATICOSVIDA UTIL 100,000 hr/setPRECIO 5,000 US$/setCOSTO 0.05 US$/hr

OTROS COSTOS(15% ANTERIORES) 3.28 US$/hr

COSTOS OPERACIÓN EQUIPO 25.17 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 5.00 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 4.00 US$/hr

RESUMENCOSTO OPERACIÓN 25.17 US$/hrCOSTO MANTENCION/REPARACION 5.00 US$/hrCOSTO OVERHAUL 4.00 US$/hr

TOTAL COSTO OPERACIÓN 34.17 US$/hr

Page 11: Costos Operación_ Planilla R1

CAMIÓN PETROLEROITEM CANTIDAD UNIDAD

COMBUSTIBLECONSUMO 12 lt/hr

PRECIO 1.2 US$/ltCOSTO 14.40 US$/hr

LUBRICANTESCONSUMO (30% COMBUSTIBLE) 4 lt/hr

PRECIO 1.20 US$/ltCOSTO 4.32 US$/hr

NEUMATICOSVIDA UTIL 100,000 hr/setPRECIO 5,000 US$/setCOSTO 0.05 US$/hr

OTROS COSTOS(15% ANTERIORES) 2.82 US$/hr

COSTOS OPERACIÓN EQUIPO 21.59 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 2.40 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 1.92 US$/hr

RESUMENCOSTO OPERACIÓN 21.59 US$/hrCOSTO MANTENCION/REPARACION 2.40 US$/hrCOSTO OVERHAUL 1.92 US$/hr

TOTAL COSTO OPERACIÓN 25.91 US$/hr

Page 12: Costos Operación_ Planilla R1

CAMIÓN ALJIBEITEM CANTIDAD UNIDAD

COMBUSTIBLECONSUMO 12 lt/hr

PRECIO 1.2 US$/ltCOSTO 14.40 US$/hr

LUBRICANTESCONSUMO (30% COMBUSTIBLE) 4 lt/hr

PRECIO 1.20 US$/ltCOSTO 4.32 US$/hr

NEUMATICOSVIDA UTIL 100,000 hr/setPRECIO 5,000 US$/setCOSTO 0.05 US$/hr

OTROS COSTOS(15% ANTERIORES) 2.82 US$/hr

COSTOS OPERACIÓN EQUIPO 21.59 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 3.00 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 2.40 US$/hr

RESUMENCOSTO OPERACIÓN 21.59 US$/hrCOSTO MANTENCION/REPARACION 3.00 US$/hrCOSTO OVERHAUL 2.40 US$/hr

TOTAL COSTO OPERACIÓN 26.99 US$/hr

Page 13: Costos Operación_ Planilla R1

CAMIÓN UTILITARIOITEM CANTIDAD UNIDAD

COMBUSTIBLECONSUMO 8 lt/hr

PRECIO 1.2 US$/ltCOSTO 9.60 US$/hr

LUBRICANTESCONSUMO (30% COMBUSTIBLE) 2 lt/hr

PRECIO 1.20 US$/ltCOSTO 2.88 US$/hr

NEUMATICOSVIDA UTIL 50,000 hr/setPRECIO 3,000 US$/setCOSTO 0.1 US$/hr

OTROS COSTOS(15% ANTERIORES) 1.88 US$/hr

COSTOS OPERACIÓN EQUIPO 14.42 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 1.00 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 0.80 US$/hr

RESUMENCOSTO OPERACIÓN 14.42 US$/hrCOSTO MANTENCION/REPARACION 1.00 US$/hrCOSTO OVERHAUL 0.80 US$/hr

TOTAL COSTO OPERACIÓN 16.22 US$/hr

Page 14: Costos Operación_ Planilla R1

VENTILADOR 450 KCFMITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 470 kwh

PRECIO 0.092 US$/kwCOSTO 43.3 US$/hr

LUBRICANTESCOSTO (30% EE) 12.98 US$/hr

OTROS COSTOS(20% ANTERIORES) 11.2 US$/hr

COSTOS OPERACIÓN EQUIPO 67.49 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS ADQUISICION) 11.13 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 5.24 US$/hr

RESUMENCOSTO OPERACIÓN 67.49 US$/hrCOSTO MANTENCION/REPARACION 11.13 US$/hrCOSTO OVERHAUL 5.24 US$/hr

TOTAL COSTO OPERACIÓN 83.85 US$/hr

Page 15: Costos Operación_ Planilla R1

VENTILADOR 370 KCFMITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 455 kwh

PRECIO 0.092 US$/kwCOSTO 41.9 US$/hr

LUBRICANTESCOSTO (30% EE) 12.56 US$/hr

OTROS COSTOS(20% ANTERIORES) 10.9 US$/hr

COSTOS OPERACIÓN EQUIPO 65.34 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS ADQUISICION) 10.94 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 5.15 US$/hr

RESUMENCOSTO OPERACIÓN 65.34 US$/hrCOSTO MANTENCION/REPARACION 10.94 US$/hrCOSTO OVERHAUL 5.15 US$/hr

TOTAL COSTO OPERACIÓN 81.42 US$/hr

Page 16: Costos Operación_ Planilla R1

VENTILADOR 200 KCFMITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 101 kwh

PRECIO 0.092 US$/kwCOSTO 9.3 US$/hr

LUBRICANTESCOSTO (30% EE) 2.79 US$/hr

OTROS COSTOS(20% ANTERIORES) 2.4 US$/hr

COSTOS OPERACIÓN EQUIPO 14.53 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS ADQUISICION) 1.43 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 0.67 US$/hr

RESUMENCOSTO OPERACIÓN 14.53 US$/hrCOSTO MANTENCION/REPARACION 1.43 US$/hrCOSTO OVERHAUL 0.67 US$/hr

TOTAL COSTO OPERACIÓN 16.63 US$/hr

Page 17: Costos Operación_ Planilla R1

VENTILADOR 75 KCFMITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 47 kwh

PRECIO 0.092 US$/kwCOSTO 4.3 US$/hr

LUBRICANTESCOSTO (30% EE) 1.29 US$/hr

OTROS COSTOS(20% ANTERIORES) 1.1 US$/hr

COSTOS OPERACIÓN EQUIPO 6.72 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS ADQUISICION) 1.04 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 0.49 US$/hr

RESUMENCOSTO OPERACIÓN 6.72 US$/hrCOSTO MANTENCION/REPARACION 1.04 US$/hrCOSTO OVERHAUL 0.49 US$/hr

TOTAL COSTO OPERACIÓN 8.24 US$/hr

Page 18: Costos Operación_ Planilla R1

VENTILADOR 25 KCFMITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 21 kwh

PRECIO 0.092 US$/kwCOSTO 1.9 US$/hr

LUBRICANTESCOSTO (30% EE) 0.58 US$/hr

OTROS COSTOS(20% ANTERIORES) 0.5 US$/hr

COSTOS OPERACIÓN EQUIPO 3.01 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS ADQUISICION) 0.24 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 0.11 US$/hr

RESUMENCOSTO OPERACIÓN 3.01 US$/hrCOSTO MANTENCION/REPARACION 0.24 US$/hrCOSTO OVERHAUL 0.11 US$/hr

TOTAL COSTO OPERACIÓN 3.37 US$/hr

Page 19: Costos Operación_ Planilla R1

Tipo Cantidad US$/hr US$/hrVENTILADOR 450 KCFM 2 83.85 167.70278VENTILADOR 370 KCFM 2 81.42 162.84163VENTILADOR 200 KCFM 1 16.63 16.634178VENTILADOR 75 KCFM 1 8.24 8.2389582Total Costos ventilación principal 355.41754

Page 20: Costos Operación_ Planilla R1

MARTILLO FIJOITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 30 kwh

PRECIO 0.092 US$/kwhCOSTO 2.76 US$/hr

LUBRICANTESCOSTO (30% EE) 0.83 US$/hr

CABEZALVIDA UTIL 5,000 hr/un

PRECIO 8,000 US$/unCOSTO 1.6 US$/hr

OTROS COSTOS(20% ANTERIORES) 1.04 US$/hr

COSTOS OPERACIÓN EQUIPO 6.23 US$/hr

COSTO MANTENCION/REPARACION(50% COSTOS ADQUISICION) 5.00 US$/hr

COSTO OVERHAUL(40% COSTOS ADQUISICION) 4.00 US$/hr

RESUMENCOSTO OPERACIÓN 6.23 US$/hrCOSTO MANTENCION/REPARACION 5.00 US$/hrCOSTO OVERHAUL 4.00 US$/hr

TOTAL COSTO OPERACIÓN 15.23 US$/hr

Page 21: Costos Operación_ Planilla R1

APRON/GRIZZLYITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 78 kwh

PRECIO 0.092 US$/kwCOSTO 7.2 US$/hr

LUBRICANTESCOSTO (30% EE) 2.15 US$/hr

OTROS COSTOS(20% ANTERIORES) 1.9 US$/hr

COSTOS OPERACIÓN EQUIPO 11.19 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 9.52 US$/hr

RESUMENCOSTO OPERACIÓN 11.19 US$/hrCOSTO MANTENCION/REPARACION 9.52 US$/hr

TOTAL COSTO OPERACIÓN 20.71 US$/hr

Page 22: Costos Operación_ Planilla R1

CHANCADORITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 216 kwh

PRECIO 0.092 US$/kwCOSTO 19.9 US$/hr

LUBRICANTESCOSTO (30% EE) 5.97 US$/hr

OTROS COSTOS(20% ANTERIORES) 5.2 US$/hr

COSTOS OPERACIÓN EQUIPO 31.04 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 26.39 US$/hr

RESUMENCOSTO OPERACIÓN 31.04 US$/hrCOSTO MANTENCION/REPARACION 26.39 US$/hr

TOTAL COSTO OPERACIÓN 57.43 US$/hr

Page 23: Costos Operación_ Planilla R1

CORREA TRANSPORTADORA 48"ITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 93 kwh

PRECIO 0.092 US$/kwCOSTO 8.6 US$/hr

LUBRICANTESCOSTO (30% EE) 2.57 US$/hr

OTROS COSTOS(20% ANTERIORES) 2.2 US$/hr

COSTOS OPERACIÓN EQUIPO 13.36 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 11.36 US$/hr

RESUMENCOSTO OPERACIÓN 13.36 US$/hrCOSTO MANTENCION/REPARACION 11.36 US$/hr

TOTAL COSTO OPERACIÓN 24.72 US$/hr

Page 24: Costos Operación_ Planilla R1

SISTEMA SKIPITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 2,310 kwh

PRECIO 0.092 US$/kwCOSTO 212.6 US$/hr

LUBRICANTESCOSTO (30% EE) 63.77 US$/hr

OTROS COSTOS(20% ANTERIORES) 55.3 US$/hr

COSTOS OPERACIÓN EQUIPO 331.59 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 281.85 US$/hr

RESUMENCOSTO OPERACIÓN 331.59 US$/hrCOSTO MANTENCION/REPARACION 281.85 US$/hr

TOTAL COSTO OPERACIÓN 613.43 US$/hr

Page 25: Costos Operación_ Planilla R1

HUINCHE TAMBORITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 638 kwh

PRECIO 0.092 US$/kwCOSTO 58.7 US$/hr

LUBRICANTESCOSTO (30% EE) 17.60 US$/hr

OTROS COSTOS(20% ANTERIORES) 15.2 US$/hr

COSTOS OPERACIÓN EQUIPO 91.49 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 77.77 US$/hr

RESUMENCOSTO OPERACIÓN 91.49 US$/hrCOSTO MANTENCION/REPARACION 77.77 US$/hr

TOTAL COSTO OPERACIÓN 169.26 US$/hr

Page 26: Costos Operación_ Planilla R1

ALIMENTADORITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 33 kwh

PRECIO 0.092 US$/kwCOSTO 3.0 US$/hr

LUBRICANTESCOSTO (30% EE) 0.91 US$/hr

OTROS COSTOS(20% ANTERIORES) 0.8 US$/hr

COSTOS OPERACIÓN EQUIPO 4.74 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 4.03 US$/hr

RESUMENCOSTO OPERACIÓN 4.74 US$/hrCOSTO MANTENCION/REPARACION 4.03 US$/hr

TOTAL COSTO OPERACIÓN 8.76 US$/hr

Page 27: Costos Operación_ Planilla R1

CORREA TRANSPORTADORA 48" SUPERFICIEITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 111 kwh

PRECIO 0.092 US$/kwCOSTO 10.2 US$/hr

LUBRICANTESCOSTO (30% EE) 3.06 US$/hr

OTROS COSTOS(20% ANTERIORES) 2.7 US$/hr

COSTOS OPERACIÓN EQUIPO 15.93 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 13.54 US$/hr

RESUMENCOSTO OPERACIÓN 15.93 US$/hrCOSTO MANTENCION/REPARACION 13.54 US$/hr

TOTAL COSTO OPERACIÓN 29.47 US$/hr

Page 28: Costos Operación_ Planilla R1

EQUIPOS AUXILIARESITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 126 kwh

PRECIO 0.092 US$/kwCOSTO 11.6 US$/hr

LUBRICANTESCOSTO (30% EE) 3.47 US$/hr

OTROS COSTOS(20% ANTERIORES) 3.0 US$/hr

COSTOS OPERACIÓN EQUIPO 18.04 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 15.33 US$/hr

RESUMENCOSTO OPERACIÓN 18.04 US$/hrCOSTO MANTENCION/REPARACION 15.33 US$/hr

TOTAL COSTO OPERACIÓN 33.37 US$/hr

Page 29: Costos Operación_ Planilla R1

BOMBASITEM CANTIDAD UNIDAD

ENERGÍA ELÉCTRICACONSUMO 336 kwh

PRECIO 0.092 US$/kwCOSTO 30.9 US$/hr

LUBRICANTESCOSTO (30% EE) 9.27 US$/hr

OTROS COSTOS(20% ANTERIORES) 8.0 US$/hr

COSTOS OPERACIÓN EQUIPO 48.22 US$/hr

COSTO MANTENCION/REPARACION(85% COSTOS OPERACIÓN) 40.99 US$/hr

RESUMENCOSTO OPERACIÓN 48.22 US$/hrCOSTO MANTENCION/REPARACION 40.99 US$/hr

TOTAL COSTO OPERACIÓN 89.21 US$/hr