ANALISIS DE PRECIOS UNITARIOS
SIN IVA
PROYECTO:
PARTIDA No.: 1
ITEM No.: MORTERO 1:1
A- MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO SUBTOTAL
CEMENTO BOLSAS 28 $7.85 $219.80
ARENA M3 0.8 $16.00 $12.80
AGUA BARRIL 2 $2.00 $4.00
SUBTOTAL: $236.60
B- MANO DE OBRA
DESCRIPCION JORNAL PRESTACION JORN-TOTAL RENDIMIENTO SUBTOTAL
6 AUXILIARES $42.00 $12.00 $54.00 0.53 $28.77
SUBTOTAL $28.77
C-EQUIPO Y HERRAMIENTAS
DESCRIPCION TIPO CAPACIDAD RENDIMIENTO COSTO/HORA SUBTOTAL
HERRAMIENTAS CONV 4% $10.61
CONCRETERA 3.73 $5.71 $21.33
COMBUSTIBLE 3.73 $1.00 $3.73
SUBTOTAL: $35.68
D-SUBCONTRATOS
DESCRIPCION UNIDAD CANTIDAD PRECIO SUBTOTAL
SUBTOTAL:
COSTO DIRECTO $301.05
COSTO INDIRECTO 20% $60.21
UNIDAD:M3
PRECIO UNITARIO $361.26
ANALISIS DE PRECIOS UNITARIOS
SIN IVA
PROYECTO:
PARTIDA No.: 1
ITEM No.: MORTERO 1:2
A- MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO SUBTOTAL
CEMENTO BOLSAS 19 $7.85 $149.15
ARENA M3 1.07 $16.00 $17.12
AGUA BARRIL 1 $2.00 $2.00
SUBTOTAL: $168.27
B- MANO DE OBRA
DESCRIPCION JORNAL PRESTACION JORN-TOTAL RENDIMIENTO SUBTOTAL
6 AUXILIARES $42.00 $12.00 $54.00 0.36 $19.44
SUBTOTAL $19.44
C-EQUIPO Y HERRAMIENTAS
DESCRIPCION TIPO CAPACIDAD RENDIMIENTO COSTO/HORA SUBTOTAL
HERRAMIENTAS CONV 4% $7.51
CONCRETERA 2.54 $5.71 $14.51
COMBUSTIBLE 2.54 $1.00 $2.54
SUBTOTAL: $24.56
D-SUBCONTRATOS
DESCRIPCION UNIDAD CANTIDAD PRECIO SUBTOTAL
SUBTOTAL:
COSTO DIRECTO $212.27
COSTO INDIRECTO 20% $42.45
UNIDAD:M3
PRECIO UNITARIO $254.73
ANALISIS DE PRECIOS UNITARIOS
SIN IVA
PROYECTO:
PARTIDA No.: 1
ITEM No.: MORTERO 1:3
A- MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO SUBTOTAL
CEMENTO BOLSAS 15 $7.85 $117.75
ARENA M3 1.21 $16.00 $19.36
AGUA BARRIL 2 $2.00 $4.00
SUBTOTAL: $141.11
B- MANO DE OBRA
DESCRIPCION JORNAL PRESTACION JORN-TOTAL RENDIMIENTO SUBTOTAL
6 AUXILIARES $42.00 $12.00 $54.00 0.27 $14.36
SUBTOTAL $14.36
C-EQUIPO Y HERRAMIENTAS
DESCRIPCION TIPO CAPACIDAD RENDIMIENTO COSTO/HORA SUBTOTAL
HERRAMIENTAS CONV 4% $6.22
CONCRETERA 1.87 $5.71 $10.69
COMBUSTIBLE 1.87 $1.00 $1.87
SUBTOTAL: $18.77
D-SUBCONTRATOS
DESCRIPCION UNIDAD CANTIDAD PRECIO SUBTOTAL
SUBTOTAL:
COSTO DIRECTO $174.25
COSTO INDIRECTO 20% $34.85
UNIDAD:M3
PRECIO UNITARIO $209.10