Upload
cesar-cirilo-claudio
View
182
Download
7
Embed Size (px)
Citation preview
E S T U D I O D E M E R C A D O
C A S A C O M E R C I A L FECHA DE COTIZACION 10/1/2012 10/2/2012 10/3/2012
MATERIALES UNIDAD PORCELANITE SAN JUAN GURRION COSTO MINIMOSIN IVA SIN IVA SIN IVA SIN IVA
ARENA FINA 7 m3 m3 $147.78 $135.47 160.1 $135.47
ARENA GREÑA 7 m3 m3 172.41 $172.41
GRAVA DE RIO m3 $147.78 $147.78
GRAVA DE 3/4" 7 M3 M3 $160.10 $160.10
CEMENTO GRIS SACO 50 KG (CRUZ AZUL) TON $1,982.76 $2,069 $1,982.76
CEMENTO GRIS SACO 50 KG (MOCTEZUMA)) TON $1,818.97 $1,818.97
CEMENTO BLANCO SACO 25GK $4,000.00 $3,448.28
CEMENTANTE 7 m3 m3 $163.26 $163.26
CALHIDRA SACO 25 KG TON $1,448.28 $1,380.00 $1,571.52 $1,380.00
CEMENTANTE 7 m3 M3 $73.89 $73.89
BLOCK DE SEC 15x13x40 PZA $9.05 $7.76 $7.78 $7.76
LADRILLO PZA 1.37 $1.72 $1.37
TABIQUE PZA 1637.93 1.72 $1,637.93
TABICON PZA 5.17 $5.17
ALAMBRE # GK 17.24 $17.24
ALAMBRE RECOCIDO KG $13.36 $18.97 $17.24 $13.36
ALAMBRON KG $12.50 $17.24 $16.38 $12.50
ARMEX 10x15 PZA $86.21 $94.83 112.07 $86.21
CLAVO DE 1/2" KG 13.79 51.72 $13.79
CLAVO DE 1" KG 13.79 $34.48 $51.72 $13.79
CLAVO 1 1/2" KG 13.79 $34.48 $25.86 $13.79
CLAVO 2" KG 13.79 $19.83 $20.67 $13.79
CLAVO 2 1/2" KG 13.79 $19.83 $20.67 $13.79
CLAVO DE 3" KG 13.79 $25.86 $20.67 $13.79CLAVO DE 4" KG 13.79 $25.86 $20.67 $13.79CUELLO DE CERA PZA $17.24 $17.24
GAS BUTANO 450 ML PZA $30.17 $30.17
HILO DE CAÑAMO PZA 30.17 $30.17PASTA PARA SOLDAR 150 KG PZA $25.86 $25.86REVOLVEDORA 8 HP PZA 17241.38 $17,241.38
E S T U D I O D E M E R C A D O
TUERCA UNION 1/2" PZA $32.76 $42.24
MATERIALES UNIDAD PORCELANITE SAN JUAN GURRION COSTO MINIMO
VARILLA 3/4"( TON 36 PZAS) TON 12165.52 $13,965.52 $12,931.03 $12,165.52
VARILLA DE 3/8" (TON 150 PZAS) TON $12,543.10 $14,224.14 $12,931.03 $12,543.10
VARILLA DE 3/8" (TON 150 PZAS) TON $12,543.10 $14,224.14 $12,931.03 $12,543.10VARILLA 5/8 TON $12,157.17 $11,706.90 $12,931.03 $11,706.90YESO KG
ACCESORIOS PARA BAÑO( INCLUYE: TOALLERO, JABONERO, REGADERA, CEPILLERO, DISPERSADORES DE PAPEL)
MATERIALES UNIDAD PORCELANITE SAN JUAN GURRION COSTO MINIMO
ACCE. P/BAÑO MARCA: ASPEN JUEGO 431.03 $431.03
LAVABO BLANCO PZA $166.38 217.39 $166.38
REGADERA PZA $77.59 $77.59
REGADERA HELVEMEX PZA $645.69 $645.69
REGADERA PROYECTA PZA 327.59 $327.59
REGADERA DICA PZA 80.17 $80.17
WC MARCA: CATO BLANCO PZA $1,064.66 $266.05
FREGADERO PZA 1379.31 $1,379.31
FREGADERA MARCA: EV, MOD: 1CM 49x47 PZA 419.83 $419.83
FREGADERA MARCA :EV, MOD: 1C 1EC-201 PZA 1320.69 $1,320.69
MEZCLADORA P/FEREGADERO MARCA:DICA PZA 215.52 $215.52AMARILLO LIMON KG $51.72 $51.72AMARILLO AXIDO KG 28.02 $30.17 $28.02NARANJA OTOÑAL KG $53.45 $53.45ROJO KG $66.38 $66.38ROJO OXIDO KG 31.47 $30.17 $30.17ROJO CARMIN KG 45.68 $51.72 $45.68ROJO ESCARLATA KG $52.58 $52.58ROSA FLAMINGO KG $26.72 $26.72VERDE CRISTAAL KG $44.83 $44.83VERDE OLIVO KG $65.52 $65.52VERDE PASTO KG $51.72 $51.72TIROL BLANCO KG $77.59 $77.59TIROL COLORES KG $64.66 $64.66
E S T U D I O D E M E R C A D O
JUEGOS DE BAÑO
MATERIALES UNIDAD PORCELANITE SAN JUAN GURRION COSTO MINIMO
MARCA.CATO MOD:JASMIN FUERTE JUEGO 1537.93 $1,537.93
MARCA.CATO MOD:JASMIN BLACO JUEGO 1064.66 $1,064.66
MARCA: CATO MOD:JASMIN GRIS JUEGO 1286.21 $1,286.21
MARCA: CATO MOD:REGINCI BLANCO REDONDO JUEGO 1375.86 $1,375.86
MARCA:LAMOSA, MOD: REGINCI HUESO JUEGO 1414.66 $1,414.66
JUEGO SANITARIO BLANCO CATO JUEGO 1061.66 $733.00 $733.00
DURA PISO CAJA 1.50 M2 M2DURA PISO CAJA 1.50 M2 COLOR BEIGE 20x30 M2 88.36 $88.36DURA PISO CAJA 1.50 M2 COLOR AZUL 20x30 M2 88.36 $88.36DURA PISO CAJA 1.50 M2 COLOR VERDE 20x31 M2 88.36 $88.36DURA PISO CAJA 1.50 M2 COLOR VERDE 20x32 M2 88.36 $88.36DURA PISO CAJA 1.50 M2 COLOR GRIS 20x33 M2 88.36 $88.36
DURA PISO CAJA 1.50 M2 COLOR AZUL 20x30 M2 88.36 $88.36
ITALICA CAJA 1.53 M2 COLOR BLANCO 33x33 M2 137.93 $137.93
ITALICA CAJA 1.53 M2 DIF/COLOR 33x33 PZA 124.14 $124.14
PORCELANITECAJA 1.5 M2 COLOR HUESO33x33 M2 163.79 $163.79
PORCELANITE CAJA 1.5 M2 COLOR GRIS 33x33 M2 119.83 $119.83
PORCELANITE CAJA 1.5 M2 COLOR VERDE 33x33 M2 188.79 $188.79
PORCELANITE CAJA 1.5 M2 COLOR BEIGE 33x33 M2 181.03 $181.03
MATERIALES UNIDAD BOXITO SAN JUAN GURRION COSTO
E S T U D I O D E M E R C A D O
MINIMO
APAGADOR SENCILLO PZA $16.81 $17.24 $16.81
APGADOR DE ESCALERA PZA $21.96 $21.55 $21.55
BASE PARA MEDIDOR PZA $59.50 $94.83 $59.50
CABLE #10 IUSA I M ML $7.95 $10.45 $7.95
CAJA DE REGISTRO DE 1/2" PZA $4.97 $3.45 $3.45
CAJA DE REGISTRO DE 3/4" PZA $5.35 $6.03 $5.35
CENTRO DE CARGA 240/120 V PZA $100.92 $100.92
CENTRO DE CARGA QO-1 PZA $77.59 $77.59
CENTRO DE CARGA QO-2 PZA $103.45 $103.45
CENTRO DE CARGA QO-4 PZA $198.28 $198.28
CENTRO DE CATGA QO-6 PZA $387.93 $387.93
CHALUPA GALVANIZADA PZA $3.07 $3.45 $3.07
CINTA AISLANTE PZA 9.6 $10.35 $9.60
CINTA TEFLON 6.6 MTROS PZA 3.3 $4.31 $3.30
CONECTOR PARA VARILLA PZA 4.13 $12.93 $4.13
CONTACTO POLARIZADO PZA $16.81 $20.69 $16.81
CONTACTO SENCILLO PZA $16.81 $17.24 $5.49
FUSIBLES 30 AMP PZA $5.49 $8.62 $74.48
LAMPARA CIRCULAR FLUORESCENTRE PZA 74.48 $74
LAMPARA ESPIRAL FLUORESCENTRE PZA 36.85 $36.85
MUFA GALVANIZADAS PZA $13.18 $8.62 $8.62PASTILLA P/CENTRO DE CARGA QO-120 DE 20A PZA $75.52 $94.83 $75.52
PLACA DE 1 VENTANA PZA $15.97 $17.24 $15.97
PLACA DE 2 VENTANAS PZA $15.97 $17.24 $15.97
PLACA DE 3 VENTANAS PZA $15.97 $17.24 $15.97
R. DE CABLE UNIPOLAR # 12 IUSA NEGRO DE 100M ML $4.68 $5.60 $4.68
R. DE CABLE UNIPOLAR # 14 IUSA BLANCO DE 100 ML $3.30 $4.31 $3.30
R. DE MANGUERA POLIFLEX 1/2 1OO ML ML $3.83 $4.35 $3.83
R. DE MANGUERA POLIFLEX 3/4" 50 ML ML $6.24 $3.88 $3.88
SOQUET PORCELANA 1/2" CHICO 127 V PZA 8.73 $10.35 $8.73
SOQUET PORCELANA 3/4" GRANDE127 V PZA 10.44 $12.93 $10.44
TAPA P/REGISTRO GALV CUAD 3 X3 PZA $2.21 $2.59 $2.21
TAPA P/REGISTRO DE 3/2" 4"X4" PZA 3.66 4.31 $3.66
TAQUETE PLASTICO 1/4" 1OO PZA PZA 0.12 $0.43 $0.12
TAQUETE PLOMO 3/8" PZA $0.00
TUBO CONDUIT GALV. P/ ACOMETIDA 3ML PZA 109.51 137.93 $113.04 $109.51
E S T U D I O D E M E R C A D O
VENTILADOR INDUSTRIAL P/TECHO BLANCO PZA $0.00
MATERIALES UNIDAD BOXITO SAN JUAN GURRION COSTO MINIMO
ADAPTADOR DE HULE PVC PZA 2.81 $4.31 $2.81ALIMENTADOR PARA FREGADERO 55CM PZA $34.79 $17.24 $17.24ALIMENTADOR PARA WC 35CM PZA $32.78 $19.00 $17.24 $17.24ALIMENTTADOR P/LAVABO PZA $29.64 $19.00 $17.24 $17.24CODO DE COBRE 1/2" DE 45° PZA $8.50 ### $10.00 $13.79 $8.50CODO DE COBRE 1/2" DE 90° PZA $3.83 ### $5.00 $6.06 $3.83CODO DE COBRE 3/4" DE 45° PZA $14.45 ### $10.00 $38.79 $10.00CODO DE COBRE 3/4" DE 90° PZA $46.22 ### $10.00 $17.24 $10.00CODO DE COBRE 1 1/4" PZA $51.72 $51.72CODO DE PVC 1 1/2" DE 45° PZA 1.75 1.75CODO DE PVC 1 1/2" DE 90° PZA $1.95 ### $77.59 $1.95CODO DE PVC DE 2" DE 45° PZA $1.94 ### $3.00 $2.59 $1.94CODO DE PVC DE 2" DE 90° PZA $2.08 ### $3.00 $2.60 $2.60CODO DE PVC DE 3" DE 45° PZA $5.83 ### $6.00 $6.90 $5.83CODO DE PVC DE 3" DE 90° PZA $5.84 ### $3.00 $3.00CODO DE PVC DE 4" PZA $10.34 $10.34CODO DE PVC DE 4" DE 45° PZA $7.41 ### $6.00 $6.00CODO DE PVC DE 4"DE 90° PZA $7.65 ### $9.00 $7.65CODO DE PVC DE 6" DE 45° PZA 22.66 ### $43.00 $43.10 22.66CODO DE PVC DE 6"DE 90° PZA 27.88 ### $47.00 27.88CODO PIPA PZA $18.00 $18.00CONECTOR P/INTERIOR 1/2" COBRE PZA 9.46 $13.00 $13.00 9.46CONECTOR P/INTERIOR 3/4" COBRE PZA 14.12 $17.00 $17.00 6.8CONECTOR P/INTERIOR 1/2" COBRE PZA 6.8 $9.48 12.84CONECTOR P/INTERIOR 3/4" COBRE PZA 12.84 $18.96 $6.80COPLE DE COBRE 3/4" PZA $6.80 ### $9.00 $6.90 $1.05COPLE DE COBRE 1/2" PZA $1.05 ### $5.00 $6.03 $13.42COPLE DE PVC 1 1/2" PZA $13.42 ### $17.24 $13.42COPLE DE PVC 2" PZA ### $2.59 $2.59COPLE DE PVC 3" PZA ### $6.03 $6.03
E S T U D I O D E M E R C A D O
COPLE DE PVC 4" PZA ### $7.76 $7.76COPLE DE PVC 6" PZA ### $25.86 $25.86HIDROTOMA 2" PZA $60.35 $60.35hIDROTOMA 2 1/2" PZA $77.59 $77.59
MATERIALES UNIDAD PORCELANITE SAN JUANSAN JUAN GURRION COSTO MIMINO
HIDROTOMA 3" PZA $53.00 $103.45 $53.00LIJA PARA PLOMERO 1M PZA $9.00 $5.17 $5.17LLAVE DE NARIZ PZA $59.50 $26.00 30.17 $26.00LAVE MESCLADORA P/FREGADERO PZA 228.45 $276.00 $198.28 $198.28LLAVE MEZCLADORA P/LAVABO PZA $185.27 $103.00 $94.83 $94.83PEGAMENTO PVC 500GRS PZA 64.67 $47.40 $38.79 $38.79PIJAS PARA WC PZA $5.00 $4.31 $4.31POLIDUCTO 100M M 2.22 ### $2.59 2.22REDUCCION PVC 2" -1 1/2" PZA 2.92 $3.00 $4.31 2.92REDUCCION PVC 3"-2" PZA $5.00 $6.03 $5.00REDUCCION PVC 4"-2" PZA $9.00 $8.62 $8.62REDUCCION PVC 6"-4" PZA $17.00 $21.55 $17.00REDUCTOR BUSHIN 3/4"-1/2" PZA $13.00 $11.34 $11.34REDUCTOR CAMPANA 3/4"-1/2" PZA $12.93 $12.93TAPON 3/4 PZA $12.93 $12.93TAPON CAPA COBRE 1/2" PZA $4.00 $10.34 $4.00TAPON CAPA COBRE 3/4" PZA $10.00 $10.34 $10.00TAPON DE PVC 1 1/2" PZA $2.00 $4.31 $2.00TAPON DE PVC 3" PZA $4.00 $10.34 $4.00TAPON DE PVC 4" PZA $7.00 $18.96 $7.00TAPON DE PVC 6" PZA $22.00 $31.03 $22.00TEE DE PVC 3/4" PZA $2.00TEE DE PVC 1 1/2" PZA ### $2.00 $2.00TEE DE PVC 2" PZA ### $3.00 $3.00TEE DE PVC 3" PZA ### $4.00 $4.00TEE DE PVC 6" PZA ### $22.00 $22.00TEE DE COBRE 3/4" PZA ### $26.00 $26.00TINACO 1100 LTS TRICAPA PZA $1,328.45 $1,552.00 $1,551.72 $1,328.45TINACO DE 500 PZATINACO BICAPA NEGRO PZA 1303.45 1303.45
E S T U D I O D E M E R C A D O
TINACO TRICAPA BEIGE PZA
INSTALACIONES HIDROSANITARIASMATERIALES UNIDAD PORCELANITESAN JUANSAN JUAN GURRION COSTO MINIMO
TUBO DE COBRE 1/2" ML ### $362.07 $362.07TUBO DE COBRE 1/2" TIPO M ML ### $60.33 $362.07 $60.33TUBO DE COBRE 3/4" ML ### 493.33 $620.69 493.33TUBO DE COBRE 1" ML ### $163.83 $948.00 $163.83TUBO DE PVC 1 1/2" ML $47.00 $51.72 $47.00TUBO DE PVC 2" ML $11.16 $77.59 $11.16TUBO DE PVC 3" ML $19.33 $103.45 $19.33TUBO DE PVC 4" ML ### $27.33 $172.41 $27.33TUBO DE PVC 6" ML $56.00 $431.03 $56.00TUBO FLEXIBLE DE COBRE 1/2" PZA $19.00 $19.00VALVULA DE COMPUERTA 1/2" PZA $69.00 $51.72 $69.00VALVULA DE COMPUERTA 3/4" PZA $73.00 $77.59 $65.00VALVULA DE GLOBO 1/2" PZA $65.00 $51.72 $51.72VALVULA DE GLOBO 3/4" PZA $77.59 $77.59VALVULA DE INSERCION PZA $121.00 $137.93 $121.00VALVULA INDIVUDUAL P/LAVABO PZA $60.00 $94.83 $60.00VALVULAN P/EMPOTRAR P/REGADERA PZA $155.00 $112.07 $112.07YEE DE PVC SANITARIO 1 1/2" PZA $4.00 $4.31 $4.00YEE DE PVC SANITARIO 2" PZA $5.00 $6.03 $5.00YEE DE PVC SANITARIO 3" PZA $13.00 $11.21 $11.21YEE DE PVC SANITARIO 4 PZA $22.00 $15.52 $15.52YEE DE PVC SANITARIO 6" PZA $310.00 $310.00YEE DE PVC SANITARIO 4" CON SALIDA 2" PZA $43.00 $12.93 $12.93YEE DE PVC SANITARIO 6" CON SALIDA 4" PZA $13.00 $13.00
UNIDAD PORCELANITESAN JUANSAN JUAN GURRION COSTO MINIMO
E S T U D I O D E M E R C A D O
MATERIALESBOQUILEX DE COLOR SACO 10 KG KG $7.70 $7.70BOQUILEX GRIS PARA MURO SACO 5 KG KGBOQUILEX GRISPARA PISO SACO 10 KG KGPEGAZULEJOS SACO 10 KG KG $73.28 ### 77.59 $73.28PEGA BUN GRIS SACO 20 KG KG 47.58 $3.00 47.58PEGA BUS GRIS SOBRE PISO SACO 20 KG PZA 99.14 99.14PORCELANITRA BLANCO SACO 20 KG PZATIRA TRIN ML 30.6 30.6
E S T U D I O D E M E R C A D O
CONCEPTO MEDIDAS MADERERIASCOSTO MINIMO
LARGO*ANCHO*GROSOR (MM)GURRION SIN IVA EL CIPRÉS SIN IVA
TRIPLAY 6 m2 $190 $163.79 $163.79
TRIPLAY 9 m2 $330 $284.48 $284.48
TRIPLAY 12 m2 $385 $331.90 $331.90
CIMBRA PLAY 1.22M *2.44M*16MM $450.00 $387.93 $400.00 $344.83 $344.83
TABLA 2.50M*30CM*2.5CM $100.00 $86.21 $83.00 $71.55 $71.55
POLIN 4-4-8 10CM*2.50M*10CM $110.00 $94.83 $118.00 $101.72 $94.83
BARROTE 2-4-8 2.50M*10CM*2.5CM $55.00 $47.41 $50.00 $43.10 $43.10
DUELA 1-4-8 2.50M*10CM*2.5CM $55.00 $47.41 $28.00 $24.14 $24.14
CHAFLAN 2.50M $10.00 $8.62 $7.00 $6.03 $6.03
TABLONES 2.50M*30CM*4CM $166.00 $143.10 $165.00 $142.24 $142.24
MOLDES P/COLMNA. DE 20 CM DIAMTRS $166.00 $143.10 $120.00 $103.45 $143.10DE 25 CM D. $170.00 $146.55 $146.55
PUERTA ESTANDAR 90 X 2.30 $400.00 $344.83 $344.83
PUERTA TRIPLAY 90 X 2.30 $400.00 $344.83 $344.83
MAQUINARIA MENOR COSTO SIN IVAREVOLVEDORA E CONCRETO ULTRA-10 CIPSA $14,310.34VIBRADORA DE GASOLINA DE 55 HP $818.97BAILARINA balle R-66 MOTOR DE 4 TIEMPO $9,913.78RETROEXCAVADORA super L580 $318,965.52GASOLINA MAGNA $9.16GASOLINA PREMIUM $9.65DIESEL $9.47
INVESTIGACION DE MERCADO
DESCRIPCION UNIDAD COSTO SIN I.V.A COSTOS CON I.V.ARevolvedora de 1 saco son motor a gasolina de 12 HP Pza 13300 15428Gasolina Magna Ltro. $7.69 $8.92Diesel Ltro. $8.00 $9.28Aceite Ltro. $9.50 $11.02Cemento Gris Ton $1,758.62 $2,040.00Cemento Blanco Ton $3,448.28 $4,000.00Calhidra Ton $1,379.31 $1,600.00Arena M3 $129.31 $150.00Grava 3/4" M3 $172.41 $200.00Varilla #3 Ton $11,637.93 $13,500.00Varilla #4 Ton $13,034.48 $15,120.00Agua en Pipa M3 $2.50 $2.90Duela de 10cm X 1" X 2.50mts Pza $23.28 $27.00Duela de 15cm X 1" X 2.50mts Pza $35.34 $40.99Duela de 20cm X 1" X 2.50mts Pza $46.55 $54.00Duela de 30cm X 1" X 2.50mts Pza $69.83 $81.00Polin 2" x 2" x 2,50m Pza $23.28 $27.00Polin 2" x 4" x 2,50m Pza $42.24 $49.00Polin 4" x 4" x 2,50m Pza $101.72 $118.00Estacas de Madera Pza $8.62 $10.00Clavo 1" Kg $34.48 $40.00Clavo 2 1/2" Kg $19.83 $23.00Alambron 1/4" Kg $17.24 $20.00Alambre Recocido Kg $18.97 $22.01Hilo de Nylon Pza $15.50 $17.98Block Solido 13 x 15 x 40 cm Pza $7.76 $9.00Tabique Rojo Recocido de la Region 7 x 14 x 28 cm Pza $1.72 $2.00Pegazulejo Cruz Azul Kg $0.00
DESCRIPCION UNIDAD COSTO SIN I.V.A COSTOS CON I.V.ALozeta Porcelanite color Beige de 30 x 30 cm. M2 $0.00Pintura Comex Vinimex Ltro. $79.31 $92.00Impermeabilizante Comex Top 2000 Ltro. $43.75 $50.75Rodillo Pza. $35.34 $40.99Extension para Rodillo de 3m. Pza. $117.24 $136.00Brocha de 6" Pza. $58.62 $68.00Cepillo de Plastico Pza. $2.59 $3.00Detergente en polvo Kg $8.62 $10.00Puerta de madera de Pino de 2.10 x 0.90 mts Pza. $0.00Puerta para Baño de 2.10 x 0.70 mts Pza. $0.00Ventana de Perfiles Tubulares de 0.80 x 1.20 mts Pza. $0.00Registro Galvanizado con tapa Pza. $4.31 $5.00Lampara Incandecente de 20 watss Pza. $0.00Poliducto Electrico Naranja de 3/4" Mtro. $4.31 $5.00Cable #12 Mtro. $0.00Base para Lampara Pza. $0.00Cinta Aislante Pza. $12.93 $15.00Caja para Contacto-Apagador Pza. $4.31 $5.00Contacto Polarizado Pza. $15.52 $18.00Conector T.P.D 19 mm Pza. $0.00Cople Conduit Galvanizado 19 mm Pza. $0.00Chalupa Galvanizada Pza. $4.31 $5.00Apagador Sencillo Pza. $0.00Varilla para sistema de tierra fisica Pza. $0.00Conector para Varilla de Tierra Pza. $0.00Tubo Vertical para Mufa Pza. $103.45 $120.00Mufa Galvanizada Pza. $12.93 $15.00Base para Medidor Pza. $0.00Interruptor General de Cuchillas Pza. $0.00Centro de Carga para 1 pastilla Pza. $51.72 $60.00
Pastilla termomagnetica de 30 Ampers Pza. $60.34 $69.99
DESCRIPCION UNIDAD COSTO SIN I.V.A COSTOS CON I.V.ATubo de Cobre de 1/2" Mtro. $51.72 $60.00Cople de Cobre de 1/2" Pza. $4.31 $5.00Pasta para soldar 100 grs. Pza. $8.62 $10.00Lija para Plomero Mtro. $6.90 $8.00Soldadura Estaño 50 x 50 Mtro. $0.00Codo de Cobre de 1/2" a 90 Pza. $6.90 $8.00Valvula de paso Cobre 1/2" soldada Pza. $30.17 $35.00Llave de Nariz Pza. $30.17 $35.00Tee de Cobre de 1/2" Pza. $6.90 $8.00Valvula de Compresión Soldada de 1/2" Pza. $30.17 $35.00Regadera Pza. $59.48 $69.00Valvula para Regadera Pza. $0.00Tubo de PVC de 2" Mtro. $14.37 $16.67Tubo de PVC de 4" Mtro. $33.04 $38.33Coladera con Tapa Pza. $30.17 $35.00Codo de PVC de 2" a 90 Pza. $4.31 $5.00Codo de PVC de 4" a 90 Pza. $12.93 $15.00Tee de PVC de 2" Pza. $8.62 $10.00Tee de PVC de 4" Pza. $21.55 $25.00Pegamento PVC Lt. $0.00Tee de PVC de 4" x 2" Pza. $25.86 $30.00Codo de PVC de 4" x 2" Pza. $21.55 $25.00Tubo de PVC de 6" Mtro. $70.41 $81.68Cople de PVC de 6" Pza. $21.55 $25.00Taza W.C Pza. $0.00Tanque W.C Pza. $0.00Cuello de Cera Pza. $12.93 $15.00Taquete de plomo 1" x 3/8" Pza. $0.00Tornillo de fijacion para W.C Pza. $4.31 $5.00
Manguera de Extencion para W.c Pza. $21.55 $25.00Cemento Blanco Kg $86.21 $100.00
DESCRIPCION UNIDAD COSTO SIN I.V.A COSTOS CON I.V.AAdaptador de hule Pza $4.31 $5.00Cespol Cromado para Lavabo Pza $68.97 $80.01Contra Rejilla Pza $0.00Escoba con cerdas de Plastico Pza $0.00Flotador para Tinaco Pza $25.86 $30.00Juego de accesorio de baño Jgo. $0.00Lavabo Lerma Pza $0.00Lavadero de Concreto Pza $0.00Llave de aleta Pza $0.00Manguera de Extensión Pza $17.24 $20.00Pijas de 1" 1/4" Pza $0.22 $0.26Tinaco Rotoplas de 750 litros de capacidad Pza $0.00
I N S T I T U TO T E C N O L O G I C O D E L I S T M O.
CATALOGO DE CONSEPTO
PARTIDA CONCEPTO UNIDAD
I TRABAJOS PRELIMINARES Columna1
I.1 TRAMITE DE PERMISO DE USO DEL SUELO. M²
I.2 TRAMITE DE LICENCIA DE CONSTRUCCIÓN.
II OBRAS PRELIMINARES
II.1 DESMONTE DE ARBOLES Y MATERIALES DE REGULAR TAMAÑO CON EQUIPO MANUAL, INCLUYENDO M²
LIMPIEZA Y QUEMA DE MATERIALES QUE OBSTRUYAN EL AREA DE CONSTRUCCION
II.2 DESPALME DE LA CAPA ORGANICA DEL SUELO CON MAQUINA. A UNOS 20 CMS DE ESPESOR M²
II.3 M²
III CIMENTACIÓN.
III.1 TRAZO Y NIVELACION DEL TERRENO CON EQUIPO TOPOGRAFICO ESTABLECIENDO EJES Y REFERENCIAS M²
INCLUYENDO CRUCETAS, ESTACAS, HILOS, MARCAS Y TRAZOS CON CALHIDRA
III.2 EXCAVACIÓN CON MAQUINARIA EN ZANJA PARA ALOJAR LA ZAPATA CORRIDA M³
III.3 AFINE CON HERRAMIENTA DEL FONDO Y PAREDES DE LA EXCAVACION. m2
III.4 CONSOLIDACION DEL FONDO DE LA EXCAVACION CON HERRAMIENTO MANUAL m2
III.5.- COLOCACIÓN DE LA PLANTILLA DE CONCRETO POBRE DE F´c= 100Kg/cm2 DE 5 CM DE ESPESOR
III.6.- SUMINISTRO,HABILITADO, ARMADOY COLOCACION DE ACERO DE REFUERZO EN CIMENTACION
F´y=4200KG/CM2.
A).- ZAPATA CORRIDA KG O TON
B).- CONTRATRABES Y TRABES DE LIGA KG O TONC).-DALA DE CIMENTACION KG O TON
III.7.- SUMINISTRO, HABITADO, CIMBRADO Y DESCIMBRADO, ACABADO COMUN EN CIMENTACION.
A).- ZAPATA CORRIDA m2
B).- CONTRATRABES Y TRABES DE LIGA (T.L.) m2
C).-DALA DE CIMENTACION m2III.8.- SUMINISTRO, TRANSPORTES Y COLOCACION DE CONCRETO DE F´c=200KG/CM2
A).- ZAPATA CORRIDA m3
B).- CONTRATRABES Y TRABES DE LIGA m3
C).-DALA DE CIMENTACION m3
III.9.- MURETE DE BLOCK DE 13x39x20cm( 4 HILADA) SOLIDO, ACENTADO CON MORTERO CEMENTO-
ARENA 1:3, DESPLANTADA SOBRE ZAPATA CORRIDA, HASTA EL NIVEL DEL TERRENO (N.T.N) m2
III.10 RELLENO Y COMPACTADO CON HERRAMIENTA MANUAL EN ZAPATAS, CON MATERIALES-
PRODUCTOS DE LA EXCAVACION. m3
III.11 CARGA Y ACARREO DEL MATERIAL SOBRANTE PRODUCTO DE EXCAVACION EN CARRETILLAS
FUERA DE LA OBRA m3
IV ESTRUCTURA
IV.1 CASTILLO DE CONCRETO ARMADO F´c =200KG/CM2, CON ACERO DE F´y=4200kg/cm2 DE
4 VARS DE #3 (3/8") DE DIAMETRO Y ESTRIBU DE 20 CMS DE SEPARACION (TIPO K-1) ml
IV.2 CASTILLO DE CONCRETO ARMADO (TIPO K-2) F´c =200KG/CM2, CON ACERO DE REFUERZO
DE F´y= 4200KG/CM2 CON 4 VARS DE 1/2" DE DIAMETRO Y 2 VARS DE 3/8" CON ESTRIBU DE
ALAMBRON DE 20 CM DE SEPARACION ml
IV.3.- COLUMNA DE CONCRETO ARMADO DE F´c=200kg/cm CON ACERO DE REFUERZO F´y=4200kg/cm2
ARMADO CON 6 VARS #3 (3/8") @ 25CM DE SEPARACION, AGREGADO MAXIMO DE 3/8"
O B R A: C O N S T R U C C I Ó N D E U N A C A S A - H A B I T A C I Ó N.
ALUMNO: JOSE JOSE LAMBEERTO
CARGA Y ACARREO DEL MATERIAL EN CAMION PRODUCTO DEL DESPALME. EL MATERIAL DEBERÁ SER DEPOSITADO FUERA DE LA OBRA.
M²
DE 30 x 30 CM m3
IV.4 CADENA O DALA DE CONCRETO ARMADO DE F´c=200KG/CM2, ACERO DE REFUERZO F´ y=4200KG/CM2
ESTRIBU DE ALAMBRON A CADA 20 CM
A).-CADENA DE DESPLANTE (CD), CON 6 VARS DE 3/8" ML
B).-CADENA INTERMEDIA (CI), CON 4 VARS DE 3/8" ML
C).-CADENA DE CERRAMIENTO (CC), CON 6 VARS DE 3/8" ML
IV.5.- TRABES DE CONCRETO ARMADO F´c=200KG/CM2´ACERO DE REFUERZO DE F´y=4200kg/cm2
(ALTA RESISTENCIA) SECCION Y ARMADO SEGÚN PROYECTO M3
V ALBAÑILERIAV.1 MUROS DE CARGA DE MAMPOSTERIA DE BLOCK, RECORRIDO, ASENTADO EN LA CADENA DE DESPLAN-
TE Y JUNTADO CON EL MORTERO CEM- ARENA 1:3, DE 13 CM DE ESPESOR. M²
V.2.- MURO DE CARGA DE MAMPOSTERIA DE TABIQUE DE 26x26x5 CM. ASENTADO Y JUNTADO CON MORTE-
RO PREFABRICADO PROPORCION CEM-ARENA 1:5. M²
V.3 FIRMES DE CONCRETO SIMPLE F´c=150 KG/CM2 DE 5 CM DE ESPESOR M²
V.4 CONSTRUCCION DE REGISTRO PARA ALBANAL DE BLOCK SOLIDO,APLANADO INFERIOR FINO CON
MORTERO CEM-ARENA 1:3 Y PISO PULIDO DE DE CONCRETO SIMPLE PIEZA
V.5 SUMINISTRO Y Y COLOCACION DE LAVADEROS DE CONCRETO ARMADO PREFABRICADO PIEZA
V.6 COLOCACION DE VENTANAS DE HERRERIA, CON CEM-ARENA 1:3,INCLUYE RANULADO DE
1.50 x 1.30 mts PIEZA
2.00x1.30 PIEZA
V.7 COLOCACION DE PUERTAS DE HERRERIA CON MORTERO CEM-ARENA 1:3INCLUYENDO RANURA PIEZA
V.8.- BASE PARA TINACO A PLOMO Y A NIVEL, A UNA ALTURA DE 0.48M ( INCLUYE TODO LO NECESARIO
PARA SU CORRECTA EJECUCION M2
VI INSTALACIÓN HIDRO-SANITARIA.
VI.1 SALIDA DE PVC SANITARIO CON DIÁMETRO SEGÚN EL MUEBLE QUE INDIQUE EL PROYECTO SAL.
(REGADERA, WC, LAVABO, CESPOL ,FREGADERO) INCLUYE LIMPIEZA, CARGA Y ACARREO DENTRO
Y FUERA DE LA OBRA DE MATERIALES, MANO DE OBRA RANURADO Y RESANES DE ALBAÑILERIA,
, PRUEBA SANITARIA Y TODO LO NECESARIO PARA SU CORRECTA FUNCIONAMIENTO DE
DESCARGA.
VI.2 MANO DE OBRA EN PLOMERÍA PARA BAÑO Y COCINA SAL.
VI.3 SUMINISTRO Y COLOCACIÓN DE WC LÍNEA ECONÓMICA COLOR BLANCO, INCLUYE HERRAJES DE PIEZA
CONEXIÓN Y FUNCIONAMIENTO, JUNTAS DE SILICÓN, ASIENTO, PRUEBA, LIMPIEZA, CARGA Y
ACARREO DENTRO Y FUERA DE LA OBRA Y TODO LO DE TODO LO NECESARIO PARA SU
CORRECTA FUNCIONAMIENTO.
VI.4 SUMINISTRO Y COLOCACIÓN DE LAVABO LÍNEA ECONOMICA COLOR BLANCO, LLVE PIEZA
MEZCLADORA ,METALICA CROMADA, CESPOL DE PLASTICO RÍGIDO, CONTRAREJILLA
Y SOPORTES.
VI.5 SUMINISTRO Y COLOCACIÓN DE REGADERA, LLAVES MANERALES Y CHAPETONES LINEA PIEZA
ECONÓMICA METALICOS CROMADOS, INCLUYE, LIMPIEZA, CARGA Y ACARREO DE MATERIALES
DENTRO Y FUERA DE LA OBRA.
VI.6 SUMINISTRO Y COLOCACIÓN DE LAVADERO PREFABRICADO, COLOCACIÓN EN PATIO DE CERVICIO PIEZA
VI.7 SUMINISTRO Y COLOCACION DE BOTE DE CESPOL CON COLADERA CROMADA PARA REGADERA DELBAÑO. PIEZA
NECESARIO PARA SU CORRECTA FUNCIONAMIENTO PIEZA
VI.8 SALIDA HIDRAULICA SEGÚN PROYECTO POR MUEBLE (REGADERA, WC, LAVADERO, LAVABO,
TARJA, LAVADERO, TINACO) LINEA DE TUBERIA DE COBRE, COLOCACION DE JARRA DE AIRE, SAL.
INCLUYE LA LIMPIEZA, CARGA Y ACARREO DENTRO Y FUERA DE LA OBRA DE MATERIALES, MANO
DE OBRA, RANURADO, RESANES DE ALBAÑILERIA, PRUEBA HIDROSTATICA, Y TODO LO NECERSARIO
PARA SU BUEN FUNCIONAMIENTO
VII INSTALACION ELECTRICAVII.1 SALIDA PARA ACOMETIDA ELECTRICA ADOSADA EN EJE EXTERIOR DEL MURO EDIFICIO CON
COLOCACION DE INTERRUPOR TERMO MAGNETICO DE 15 AMP, Y/O MURETE ACOMETIDA A BASE DE
CONCRETO ARMADO CON ZAPATA F´C=200KG/CM2, AGREGADO MAXIMO 19 MM HECHO EN OBRA SAL.
CENTRO DE CARGA Q0-2, SISTEMA DE TIERRA FISICA, BASE PARA MEDIDOR, ALCANCES MEDIDAS
Y ALTURAS SEGÚN LO QUE REQUIERA LA COMPANIA ELECTRICA DE LA LOCALIDAD, INCLUYE
MATERIALES, ACARREOS, MANO DE OBRAS, LIMPIEZA, Y TODOS LOS ACCESORIOS Y MATERIALES,
NECESARIOS PARA SU INSTALACIÓN Y COLOCACIÓN.
VII.2 SUMINISTRO E INSTALACIÓN DE SALIDA DE CENTRO Y/O ARBOTANTE DONDE INDIQUE SAL
EL PROYECTO, INCLUYE POLIDUCTO, CAJA GALV. O PVC, CABLE DEL N° 14 SOQUET DE PORCELANA
RANURADO, RESANE DE ALBAÑILERIA, LIMPIEZA, MANO DE OBRA Y TODO LO NECESARIO EN SU
CORRECTA INSTALACIÓN Y FUNCIONAMIENTO.
VII.3 SUMINISTRO E INSTALACIÓN DE SALIDA DE APAGADOR, DONDE INDIQUE EL PROYECTO SAL
INCLUYE POLIDUCTO, CAJA PVC, CABLE N° 14 PLACA DE PLASTICO´QUINZIÑO, RANURADO,
RESANE DE ALBAÑILERIA, LIMPIEZA, MANO DE OBRA Y TODO LO NECESARIO PARA SU
CORRECTA INSTALACIÓN Y FUNCIONAMIENTO.
VII.4 SUMINISTRO E INSTALACIÓN DE SALIDA DE CONTACTO COMO INDICA EL PROYECTO, INCLUYE SAL
POLIDUCTO, CAJA PVC, CABLE DEL N° 12, PLACA DE PLASTICO QUINZIÑO O SIMILAR, RANURADO,
RESANE DE ALBAÑILERIA, LIMPIEZA, MANO DE OBRA, Y TODO LO NECESARIO PARA INSTALACION
Y FUNCIONAMIENTO.
VIII ACABADOS.VIII.1 APLANADO DE CEMENTO Y ARENA A PLOMO, ACABADO EN ESPONJEADO EN M²
INTERIORES.
VIII.2 APLANADO DE CEMENTO Y ARENA A PLOMO EN EXTERIORES. M²
VIII.3 SUMINISTRO Y COLOCACIÓN DE LAMBRIN DE AZULEJO DE COLOR BLANCO DE 20x20CM, M²
EN REGADERA PEGADO A BASE DE PEGAZULEJO Y EMBOQUILLADO DE CEMENTO PLANCO
VII.4 ACABADO APARENTE APLANADO DE CEMENTO Y ARENA A PLOMO, ACABADO EN M²
ESPONJEADO EN PLAFON
VIII.5 ACABADO Y PULIDO INTEGRAL EN PISOS DE CONCRETO DE RECAMARAS, M²
ESTANCIA Y COCINA.
VIII.6 AZULEJO COLOR BLANCO DE 20*20 CM ANTIDERRAPANTE, EN REGADERA PEGADO M²
A BASE DE PEGAZULEJO Y EMBOQUILLADO DE CEMENTO BLANCO.
IX PINTURAIX.1 PINTURA VINILICA EN MUROS M²
IX.2 PINTURA VINÍLICA EN PLAFONES. M²
IX.3 PINTURA ESMALTE EN HERRERÍA. PIEZA
X CANCELERÍAX.1 SUMINISTRO Y COLOCACIÓN DE PUERTA DE MULTIPANEL CLÁSICA CON TROQUE- PIEZA
LADOS 5 PANELES EN INTERIOR LISA Y CHAPA DE CAJA CON JALADERA.
X.2 SUMINISTRO Y COLOCACIÓN DE PUERTAS DE FIBRA, IMPRESA CON CHAPA DE PIEZA
PERILLA EUCAPLAC EN RECAMARAS Y BAÑO.
X.3 SUMINISTRO Y COLOCACIÓN DE CANCEL DE ALUMINIO ACABADO NATURAL DE PIEZA
ACUERDO AL PLANO.XI VIDRERÍA
XI.1 SUMINISTRO Y COLOCACIÓN DE VIDRÍO SENCILLO DE 3 MM. PIEZA
XII LIMPIEZAXII.1 LIMPIEZA FINAL, INCLUYE CARGA Y ACARREO, DENTRO Y FUERA DEL TERRENO. M²
CLAVE CONCEPTOLOCALIZACIÓN
LARGO ANCHO ALTO UNIDAD CANTIDAD TOTALEJE TRAMO
TP TRABAJOS PRELIMINARES
TP1.-A 1---3 4.7
M2 14.57 14.571 A----C 3.10
TP2.-A 1---3 4.7
M2 14.57 14.571 A----C 3.10
CLAVE CONCEPTOLOCALIZACIÓN
LARGO ANCHO ALTO UNIDAD CANTIDAD TOTALEJE TRAMO
CM CIMENTACIONES
CM1.-
A 1'---3' 3.20 0.80 0.80
M3
2.05
11.91
B 0---2' 2.3 0.80 0.80 1.47C 0---3' 4.7 0.80 0.80 3.011 A'---C' 2.3 0.80 0.80 1.472 a----C' 3.1 0.80 0.80 1.983 a----C' 3.1 0.80 0.80 1.98
CM2.-
A 1'---3' 3.20 0.80
M2
2.56
14.96
B 0---2' 2.3 0.80 1.84C 0---3' 4.7 0.80 3.761 A'---C' 2.3 0.80 1.842 a----C' 3.1 0.80 2.483 a----C' 3.1 0.80 2.48
CLAVE CONCEPTOLOCALIZACIÓN
LARGO ANCHO ALTO UNIDAD CANTIDAD TOTALEJE TRAMO
CM3.- ml de la zapata corrida=18.70 x 0.80x0.05=0.748 M3 0.748 0.748
CM4.-
A 1'---3' 3.20 0.80
Ml
3.20
18.70
Limpieza de terreno tipo zacatal, con herramienta menor, considerando retiro y quema de material producto de
limpieza . Altura maxima de arbustos 2.00 mts
Trazo y nivelacion del terreno plano por medios manuales establesieondo ejes y referecia incluye ejes estacas hilos y
trazos de calidra.
Excavación manual en material tipo b, en cepas para cimentación, con pico y pala. Incluye afine de taludes y acarreo en carretilla del material producto de excavacion. Profundidad
máxima de excavación de 0.00 a 0.80
Consolidación de fondo de excavacion en cepas para cimentación, con pizon de mano.
Plantilla de concreto simple f'c= 100 kg/cm2, con proporcion C-A-G, prop. 1:3:4, con 5 cm de espesor.
Zapata corrida de Cimentación de 80 x 15 cm, armada con 4 varillas longitudinales de 3/8" de Ø @ 20 cms y varillas transversales de 3/8" de Ø @ 20 cms. Concreto f'c=200 kg/cm2, agregado máx. de 3/4" revenimiento 8-10 cm,
proporcion C-A-G, 1:2:2.5 Incluye suministro, habilitado, armado, elaboracion y colocación de concreto. Habilitado,
cimbrado y descimbrado.
CM4.-
B 0---2' 2.3 0.80
Ml
2.3
18.70C 0---3' 4.7 0.80 4.71 A'---C' 2.3 0.80 2.32 a----C' 3.1 0.80 3.13 a----C' 3.1 0.80 3.1
CM5.-
A 2---3 1.98 0.60
M2
1.19
6.93
B 1---2 1.10 0.60 0.66C 1---3 3.28 0.60 1.971 B---C 1.24 0.60 0.742 A --C 1.91 0.60 1.153 A --C 2.04 0.60 1.22
CM6.-
A 2---3 2.18
M
2.18
12.54
B 1---2 1.30 1.30C 1---3 3.48 3.481 B---C 1.37 1.372 A --C 2.04 2.043 A --C 2.17 2.17
CM7.-
Vol. De exc. 11.91
M3 8.02 8.02
Vol. Cim. 18.70x0.80x0.20=2.99
Vol. De murete. 11.55x0.60x0.13=0.90
11.91- 3.89= 8.02
CLAVE CONCEPTOLOCALIZACIÓN
LARGO ANCHO ALTO UNIDAD CANTIDAD TOTALEJE TRAMO
EC ESTRUCTURAS DE CONCRETO
EC1.- M 21 21(7 piezas)(3.00) = 21.00 mts
Zapata corrida de Cimentación de 80 x 15 cm, armada con 4 varillas longitudinales de 3/8" de Ø @ 20 cms y varillas transversales de 3/8" de Ø @ 20 cms. Concreto f'c=200 kg/cm2, agregado máx. de 3/4" revenimiento 8-10 cm,
proporcion C-A-G, 1:2:2.5 Incluye suministro, habilitado, armado, elaboracion y colocación de concreto. Habilitado,
cimbrado y descimbrado.
Murete de block de 13x15x40 junteado con mezcla de cemento-arena proporcion 1:4 con 1cm de espesor
Cadena de Desplante de 15 x 20 cm, armada con 4 varillas de 3/8" Ø, estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado, y colocacion de acero de refuerzo.
Concreto f'c=150 kg/cm2 prop. C-A-G 1:2:3.5 Habilitado, cimbrado y descimbrado.
Relleno y compactación de material producto de excavación en cepas de cimentación con pala y pizon de mano en cepas de 20
cms. Incluye acarreo dentro de la obra.vol. total = vol de cim. + vol. De mur. =2.99 + 0.90 =3.89
Castillo de 13 x 20 cm, armado con 4 varillas de 3/8"Ø y estribos de 1/4" de Ø @ 20cms. Incluye suministro, habilitado,
armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2 prop: C-A-G 1:2:3.5. Habilitado, cimbrado y
descimbrado.
EC2.-
A 2---3 2.18
M
2.18
12.54
B 1---2 1.30 1.30C 1---3 3.48 3.481 B---C 1.37 1.372 A --C 2.04 2.043 A --C 2.17 2.17
EC3.-
A 2---3 1.98
M
1.98
8.54C 1---3 3.28 3.282 B --C 1.24 1.243 A --C 2.04 2.04
EC4.- Tablero (1)=1x2.10=2.10 mas Tablero= (2)3.48x2.90=10.09=12.19 M2 12.19 12.19
CLAVE CONCEPTOLOCALIZACIÓN
LARGO ANCHO ALTO UNIDAD CANTIDAD TOTALEJE TRAMO
AA ALBAÑILERIA Y ACABADOS
AA1.-
área total contando cadenas y castillos
M2 27.22
1 B-C 1.37 3.00 4.112 A-C 2.04 3.00 6.123 A-C 2.17 3.00 6.51A 2--3 2.18 3.00 6.54B 1---2 1.30 3.00 3.90C 1---3 3.48 3.00 10.44
Restando área de cadenasCadena de Remate= 12.54 ml x 0.20 m= 2.51 m2 2.51
Cadena de cerramiento= 12.54 ml x 0.20 m= 2.51 m2 2.51área de puertas y ventanas
2 puertas de .90 x 2.10 = 3.78 m2 3.78
Cadena de remate de 13 x 20 cms, armada con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20cms. Incluye suministro,
habilitado, armado y colocacion de acero de refuerzo, concreto f'c=150 kg/cm2 prop: C-A-G 1:2:3.5 Habilitado, cimbrado y
descimbrado.
Cadena de cerramiento de 13 x 20 cms, armada con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20cms. Incluye suministro,
habilitado, armado y colocacion de acero de refuerzo, concreto f'c=150 kg/cm2 prop: C-A-G 1:2:3.5 Habilitado, cimbrado y
descimbrado.
Losa plana de concreto armado de 10 cm de espesor, armada con varillas de 3/8" Ø @ 20 cms, en ambos sentidos. Concreto
f'c=200 kg/cm2, agregado máximo 3/4", revenimiento 8-10 cm. Incluye materiales, desperdicios, traslapes, ganchos, y
bastones. Elaboración, colocación, curado de concreto. Habilitado, cimbrado y descimbrado.
Muro de Block de 13x15x40 cm, junteado con mezcla de cem-arena proporción 1:4 con 1.5 cm de espesor promedio.
AA1.-
2 ventanas de .80 x 0.90= 1.44 m2
M2
1.44
27.22
1 ventana para baño de 0.40 x 0.40 m2 = 0.16 m2 0.16
Muro de Block de 13x15x40 cm, junteado con mezcla de cem-arena proporción 1:4 con 1.5 cm de espesor promedio.
AA2.-
A 1---2 1.37
M22.74
7.621 B---C 1.37A 2---3 2.25
4.882 A---C 2.17
AA3.- área de firmes M2 7.62 7.62
CLAVE CONCEPTOLOCALIZACIÓN
LARGO ANCHO ALTO UNIDAD CANTIDAD TOTALEJE TRAMO
AA4.-
área total contando castillos, cadenas, y emboquillado1 B---C 2.87 3.00
M2
8.61
40.18
2 A---C 2.67 3.00 8.013 A---C 4.45 3.00 13.35A 2---3 2.83 3.00 8.49B 1---2 2.87 3.00 8.61
RESTANDO AREA DE VENTANAS2 ventanas de .80 x 0.90= 1.44 m2 1.44
1 ventana para baño de 0.70 x 0.50 m2 = 0.35 m2 0.35Por los dos lados de cada muro=1.79 x 2 = 3.58 m2 3.58
AGREGANDO EMBOQUILLADOPta 2.10+2.10+.9=5.1 X .15 =0.77 0.77
Ventanas 0.80+0.8+0.9+0.9=3.4 X .15 = 0.51 0.51Ventana baño = 0.4 X 4 lados = 1.6 x .15= 0.24 0.24
AA5.-
Tablero (1)= eje1 tramos B-C (1.35)XejeA tramos 1-2 (1.35)=1.82
M2 10.51 10.51
Tablero (2)= eje2 tramos A-C (2.23)XejeA tramos 2-3 (2.15)=4.79Bolado(1)= eje1 tramos a-B (0.53)Xeje a tramos 1-1' (1)=0.53
Bolado(2)= eje2 tramos a-B (1.33)Xeje a tramos 1'-2 (0.43)=0.57Bolado(3)= eje2 tramos a-A (0.53)XejeA tramos 2-3' (2.98)=1.58Bolado(4)= eje3' tramos a-C (2.30)Xeje a tramos 3-3' (0.53)=1.22
área de losas= 10.51
AA6.-área de muros= 40.18
M240.18
50.69área de losas= 10.57 10.51
AA7.-área de losa
M212.19 12.19
Firmes de concreto f'c=200 kg/cm, proporción C-A-G 1:2:3.5 espesor de 8 cm, acabado rustico con regla.
Suministro y colocación de piso de lozeta de 60 x 60 cms. Asentado con pegazulejo y juntas de cemento blanco, incluye
cortes rectos, rebabas, remates y desperdicios.
Aplanado en muros con mortero cemento-arena proporción 1:5 a plomo y regla dejando 1.5 cm de espesor. Incluye mano
de obra y desperdicios.
Aplanado fino en Losa con mortero cemento-arena prop: 1:5 a plomo y regla dejando 2 cm de espesor. Incluye mano de obra
y desperdicios.
Pintura vinilica en muros y losa, trabajo terminado. Incluye preparacion de superficie y mano de obra.
Impermeabilizante en azotea, trabajo terminado. Incluye preparación de superficie y mano de obra.
AA7.-área de losa
M212.19 12.19
AA8.- Registro sanitario de tabique recocido, de 40 x 60 x60 int. indicado en plano PZA 1 1HER HERRERÍA
HER1.-A 2---3
PZA1.00
2.002 B --C 1.00
Impermeabilizante en azotea, trabajo terminado. Incluye preparación de superficie y mano de obra.
Suministro y colocación de puerta de Pailería de 0.90 x 2.10 m.
CLAVE CONCEPTOLOCALIZACIÓN
LARGO ANCHO ALTO UNIDAD CANTIDAD TOTALEJE TRAMO
HER1.-A 2---3
PZA 1.00 1.003 B --C 1.00
HER1.- B 1---2 PZA 1.00 1.00
IEC INSTALACIÓN ELECTRICA
IEC1.- Instalación eléctrica en muros (ranurado y manguereado). La instalación eléctrica en muros se realizará en una lotificación
LOTE 1.00 1.00
IEC2.- La instalación eléctrica en muro se realizará en una lotificación LOTE 1.00 1.00
IEC3.- La inst. del cableado y las chalupas se hará por lotificación LOTE 1.00 1.00
IEC4.- Suministro e instalación de centros incandescentes. El num total de salidas será de 3 salidas marcado en plano. SDA 3.00 3.00
IEC5.- Indicado en plano SDA 1.00 1.00
LF1.-Limpieza total de obra terminada,con escobas, agua, jabon, etc. M2 27.72 27.72
HS INSTALACIÓN HIDRO-SANITARIA
HS1.-La instalación sanitaria se analizará en una lotificación
LOTE 1.00 1.00
HS2.- La instalación hidraílica se analizará por lotificación LOTE 1.00 1.00
HS3.- Conforme a proyecto PZA 1.00 1.00
HS4.- De acuerdo a proyecto. PZA 1.00 1.00
HS5.- Indicado en plano PZA 1.00 1.00
LF LIMPIEZA DE OBRA
LF1.-Limpieza total de obra terminada,con escobas, agua, jabon, etc. Área de construcción = 14.57 M2 14.57 14.57
Suministro y colocación de ventana de perfiles tubulares, medidas de 0.80 x 0.90. Inlcluye primera pintura, bagueta y
vidrio de 6 mm de espesor y perfiles necesarios.Suministro y colocación de ventana de perfiles tubulares para baño, medidas 0.40x0.40 m. Incluye primera pintura de
esmalte, bagueta dorada, vidrio de 6mm de espesor y perfiles necesarios.
Instalación eléctrica en losa de entrepiso (manguereado). Incluye: materiales, mano de obra y herramienta necesaria.
Instalación eléctrica en muros y losa (cableado e instalación de chalupas).
Suministro y colocación de contacto. Incluye: materiales, mano de obra y herramienta necesaria.
Suministro e instalación sanitaria en la cimentación y en muros (ramaleo) Incluye: materiales, mano de obra, herramienta
necesaria.
Suministro e instalación hidráulica en la cimentación y en muros (ramaleo).
Suministro y colocación del tinaco de 750 lt. Incluye: materiales, mano de obra y herramienta necesaria.
Suministro e instalación del W.C., Incluye: materiales, accesorios, mano de obra y herramienta necesaria.
Suministro e instalación del lavabo. Incluye: materiales, accesorios, mano de obra y herramienta necesaria..
CLAVE CONCEPTO UNIDAD CANTIDADTRABAJOS PRELIMINARES (TP)
TP1.- M2 14.57
TP2.- M2 14.57
CIMENTACIONES (CM)
CM1.- M3 11.91
CM2.- Consolidación de fondo de excavación en cepas para cimentación con pizon de mano. M3 14.96
CM3.- Plantilla de concreto simple f'c=100 kg/cm2, con proporción C-A-G 1:3:4 con 5cm de espesor. Incluye cimbrado M2 0.75
CM4.- M2 18.7
CM5.- Murete de Block de 13x15x40 junteado con mezcla cemento arena, proporcion 1:4 con 1 cm de espesor. M2 6.93
Limpieza del terreno tipo zacatal, con herramienta menor considerando retiro y quema del material producto de limpieza. Altura máxima de arbustos 2.00 mts.
Trazo de la obra, considerando posicionamiento de punto de apoyo, distancia entre ejes y encalado de ancho de cepas.
Excavación manual en material tipo B, en cepas para cimentación, con pico y pala. Incluye afine de taludes, y acarreo en carretilla del material producto de excavación, profundidad máxima de excavación de 0.00 a 0.80
Zapata Corrida de Cimentación de 80 x 15 cm, armada con 4 varillas longitudinales de 3/8" de Ø @ 20 cms, varillas transversales de 3/8" de Ø @ 20 cms. Concreto f'c=200 kg/cm2, agregado máximo de 3/4" revenimiento 8-10 cm, prop; C-A-G
1:2:2.5. Incluye suministro, habilitado, armado, colado, traslapes, y desperdicios de acero, elaboración y colocación de concreto. Habilitado cimbrado y descimbrado.
CLAVE CONCEPTO UNIDAD CANTIDAD
CM6.- M2 12.54
CM7.- M2 8.02
ESTRUCTURAS DE CONCRETO (EC)
EC1.- M 21.00
EC2.- M 12.54
EC3.- M 8.54
EC4.- M2 12.19
Cadena de Desplante de 15 x 20 cm, armada con 4 varillas de 3/8" de Ø, estribos de 1/4"@ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2 prop; C-A-G 1:2:3.5, habilitado, cimbrado y
descimbrado.
Relleno y compactación de material producto de excavación en cepas de cimentación con pala y pizon de mano en cepas de 20 cm. Incluye acarreo dentro de la obra.
Castillo de 13 x 20 cm, armado con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo. Concretos f'c=150 kg/cm2, prop; C-A-G 1:2:3.5. Habilitado, cimbrado y descimbrado.
Cadena de Cerramiento de 13 x 20 cms, armada con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2, proporción C-A-G 1:2:3.5. Habilitado,
cimbrado y descimbrado
Cadena de Remate de 13 x 20 cms, armada con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2, proporción C-A-G 1:2:3.5. Habilitado,
cimbrado y descimbrad
Losa Plana de concreto armado de 10 cms de espesor, armada con 4 varillas de 3/8" Ø @20cms en ambos sentidos. Concreto f'c= 200 kg/cm2, agregado máximo de 3/4" revenimiento 8-10 cm. Incluye materiales, desperdicios, traslapes, ganchos y
bastones. Elaboración, colocacion, curado de concreto. Habilitado, cimbrado y descimbrado.
EC4.- M2 12.19
CLAVE CONCEPTO UNIDAD CANTIDADALBAÑILERÍA Y ACABADOS (AA)
AA1.- Muro de Block de 13 x 15 x 40 cm, junteado con mezcla de cem-arena, prop 1:4 con 1.5 cm de espesor promedio M2 27.22
AA2.- Firmes de concreto f'c=200 kg/cm2 proporción C-A-G 1:2:3.5, espesor de 8 cm acabado rustico con regla. M2 7.62
AA3.- M2 7.62
AA4.- M2 40.18
AA5.- M2 10.51
AA6.- Pintura vinilica en muros y losa. Trabajo terminado, incluye preparación de superficie y mano de obra. M2 50.69
AA7.- Impermeabilizante en azotea, trabajo terminado, incluye preparación de superficie y mano de obra. M2 12.69
AA8.- Registro sanitario de tabique recocido, de 40 x 60 x60 int. PZA 1.00
Losa Plana de concreto armado de 10 cms de espesor, armada con 4 varillas de 3/8" Ø @20cms en ambos sentidos. Concreto f'c= 200 kg/cm2, agregado máximo de 3/4" revenimiento 8-10 cm. Incluye materiales, desperdicios, traslapes, ganchos y
bastones. Elaboración, colocacion, curado de concreto. Habilitado, cimbrado y descimbrado.
Suministro y colocación de piso de lozeta de 30 x 30 cm, asentado con pegazulejo y juntas de cemento blanco. Incluye cortes rectos, rebabas, remates y desperdicios.
Aplanado acabado fino en marcos de 1.5 cm de espesor con mortero cemento- arena, proporcion 1:5 a plomo y regla. Incluye mano de obra y desperdicios.
Aplanadofino en losa con mortero cemento-arena prop; 1:5 a plomo y regla dejando 2 cm de espesor. Incluye mano de obra y desperdicios.
AA8.- Registro sanitario de tabique recocido, de 40 x 60 x60 int. PZA 1.00
CLAVE CONCEPTO UNIDAD CANTIDADHERRERÍA (HER)
HER1.- Suministro y colocación de puerta de cancelería, medidas de 0.90 x 2.10. Inlcluye materiales y mano de obra. PZA 2.00
HER2.- PZA 1.00
HER3.- PZA 1
INSTALACIÓN ELECTRICA (IEC)
IEC1.- Instalación eléctrica en muros (ranurado y manguereado). Incluye: materiales, mano de obra y herramienta necesaria. LOTE 1.00
IEC2.- Instalación eléctrica en losa de entrepiso (manguereado). Incluye: materiales, mano de obra y herramienta necesaria. LOTE 1.00
IEC3.- LOTE 1.00
IEC4.- Suministro e instalación de centros incandescentes. Incluye: materiales, mano de obra y herramienta necesaria. SDA 3.00
IEC5.- Suministro y colocación de contactos. Incluye: materiales, mano de obra y herramienta necesaria. SDA 1.00
IEC 6.- Suministro, conexión y colocación de tubo y mufa vertical de 1 1/4" Ø. Incluye herramienta, material y mano de obra. PZA 1.00
Suministro y colocación de ventana de cancelería, medidas de 0.80 x 0.90. Inlcluye primera pintura, bagueta y vidrio de 6 mm de espesor y perfiles necesarios.
Suministro y colocación de ventana de cancelería para baño, medidas 0.40x0.40 m. Incluye primera pintura de esmalte, bagueta dorada, vidrio de 6mm de espesor y perfiles necesarios.
Instalación eléctrica en muros y losa (cableado e instalación de chalupas). Incluye: materiales, mano de obra y herramienta necesaria. .
IEC 6.- Suministro, conexión y colocación de tubo y mufa vertical de 1 1/4" Ø. Incluye herramienta, material y mano de obra. PZA 1.00
CLAVE CONCEPTO UNIDAD CANTIDAD
IEC 7.- Suministro y colocación de base para medidor. Incluye conexión, herramienta y mano de obra. PZA 1.00
IEC 8.- PZA 1.00
INSTALACIÓN HIDRO-SANITARIA (HS)
HS1.- LOTE 1.00
HS2.- LOTE 1.00
HS3.- Suministro y colocación del tinaco de 750 lt. Incluye: materiales, mano de obra y herramienta necesar PZA 1
HS4.- Suministro e instalación del W.C., Incluye: materiales, accesorios, mano de obra y herramienta necesaria. PZA 1.00
HS5.- Suministro e instalación del lavabo. Incluye: materiales, accesorios, mano de obra y herramienta necesaria. PZA 1.00
LF LIMPIEZA DE OBRA
LF1.- Limpieza total de obra terminada,con escobas, agua, jabon, etc. M2 14.57
Suministro, colocación y prueba de centro de carga para 1 pastilla termomagnética de 30 Amp. Incluye elementos de fijación, materiales y mano de obra.
Suministro e instalación sanitaria en la cimentación y en muros (ramaleo) Incluye: materiales, mano de obra, herramienta necesaria.
Suministro e instalación hidráulica en la cimentación y en muros (ramaleo) Incluye: materiales, mano de obra, herramienta necesaria.
TABULADOR DE SALARIOS
CATEGORÍA SALARIO SALARIO BASE
CABO $300.00 260
OFICIAL ALBAÑIL $270.00 230
OFICIAL FIERRERO $300.00 260
OFICIAL CARPINTERO $250.00 220
OFICIAL AZULEJERO $260.00230
OFICIAL PLOMERO $260.00230
OFICIAL ELECTRICO $300.00260
OFICIAL PINTOR $250.00220
PEÓN $150.00 130
OPERADOR DE EQUIPO MENOR $170.00 150
AYUDANTE $180.00 160
OFICIAL ALUMINIERO $220.00 190
SOLDADOR $300.00260
CHOFER DE CAMION $250.00 220
ANALISIS DEL FACTOR DE SALARIO REAL
DICAL DIAS CALENDARIO 365.00DIAGUI DIAS DE AGUINALDO 15.00
PIVAC DIAS POR PRIMA VACACIONAL 1.50
Horas extras gravables en el SBCHoras extras no gravables en el SBC
Tp TOTAL DE DIAS REALMENTE PAGADOS AL AÑO 381.50
DIDOM DIAS DOMINGO 52.00
DIFES DIAS FESTIVOS POR LEY 8.00
DIPCO DIAS POR COSTUMBRE 5.00DIAS POR VACACIONES 6.00
DIPEC DIAS PERDIDOS POR CONDICONES DEL CLIMA 2.00
DIPEE DIAS PERDIDOS POR ENFERMEDAD (ACCIDENTES)2.00
DINLA DIAS NO LABORADOS AL AÑO 74.00TI TOTAL DE DIAS REALMENTE LABORADOS AL AÑO (DICAL-DINLA) 291.00
Tp / Tl DIAS PAGADOS ENTRE DIAS LABORADOS 1.3189(Tp-Te) / Tl (DIAS PAGADOS - TIEMPO EXTRA NO GRAVABLE) / TOTAL DE DIAS REALMENTE LABORADOS AL AÑO 1.3189
FSBC FACTOR DE SALARIO BASE DE COTIZACION (Tp-Te) / DICAL para calculo del IMSS 1.3100OC Otros Cargos
SALARIO MINIMO D.F. $62.333 VECES SALARIO MINIMO D.F. $186.99 25 VECES SALARIO MINIMO D.F. $ 1558.25 25 VECES SALARIO MINIMO D.F. $ 1558.25
CATEGORIA SALARIO I. RIESGO II. ENFERMEDAD Y MATERNIDAD III IV V TOTAL PS
CLAVE DESCRIPCION INFONAVIT
A B C D E F G H I J K L M N O P Q R S T(Tp-Te) / DICAL DxE GxF HxSMDF F-3SMDF JxI KxF LxF MxF NxF OxF PxF QxF RxF SUMA (G-R) , sin I S/F
Tp / Tl Sn FSBC SBC 7.5888% 20.4000% 1.1000% 0.7000% 1.0500% 1.7500% 2.00% 3.1500% 1.00% 5.00% 2.00% SP SP/SBC
TRAB01 CABO 1.3189 $260.00 1.045205479 271.75 20.62 12.72 84.76 0.93 1.90 2.85 4.76 5.44 8.56 2.72 13.59 5.44 79.52 0.2926TRAB02 OF. ALBAÑIL 1.3189 $230.00 1.045205479 240.40 18.24 12.72 53.41 0.59 1.68 2.52 4.21 4.81 7.57 2.40 12.02 4.81 71.57 0.2977TRAB03 OF. FIERRERO 1.3189 $260.00 1.045205479 271.75 20.62 12.72 84.76 0.93 1.90 2.85 4.76 5.44 8.56 2.72 13.59 5.44 79.52 0.2926TRAB04 OF. CARPINTERO 1.3189 $220.00 1.045205479 229.95 17.45 12.72 42.96 0.47 1.61 2.41 4.02 4.60 7.24 2.30 11.50 4.60 68.92 0.2997TRAB05 OF. AZULEJERO 1.3189 $230.00 1.045205479 240.40 18.24 12.72 53.41 0.59 1.68 2.52 4.21 4.81 7.57 2.40 12.02 4.81 71.57 0.2977
TRAB06 OF. PLOM/FONT 1.3189 $230.00 1.045205479 240.40 18.24 12.72 53.41 0.59 1.68 2.52 4.21 4.81 7.57 2.40 12.02 4.81 71.57 0.2977
TRAB07 OF. ELECTRICO 1.3189 $260.00 1.045205479 271.75 20.62 12.72 84.76 0.93 1.90 2.85 4.76 5.44 8.56 2.72 13.59 5.44 79.52 0.2926
TRAB08 OF. PINTOR 1.3189 $220.00 1.045205479 229.95 17.45 12.72 42.96 0.47 1.61 2.41 4.02 4.60 7.24 2.30 11.50 4.60 68.92 0.2997
TRAB09 OF. PEON 1.3189 $130.00 1.045205479 135.88 10.31 12.72 -51.11 -0.56 0.95 1.43 2.38 2.72 4.28 1.36 6.79 2.72 45.09 0.3318
TRAB10 OP. EQ. MENOR 1.3189 $150.00 1.045205479 156.78 11.90 12.72 -30.21 -0.33 1.10 1.65 2.74 3.14 4.94 1.57 7.84 3.14 50.38 0.3214
TRAB11 OF. AYUDANTE 1.3189 $160.00 1.045205479 167.23 12.69 12.72 -19.76 -0.22 1.17 1.76 2.93 3.34 5.27 1.67 8.36 3.34 53.03 0.3171
TRAB12 OF. ALUNINIERO 1.3189 $190.00 1.045205479 198.59 15.07 12.72 11.60 0.13 1.39 2.09 3.48 3.97 6.26 1.99 9.93 3.97 60.98 0.3071TRAB13 SOLDADOR 1.3189 $260.00 1.045205479 271.75 20.62 12.72 84.76 0.93 1.90 2.85 4.76 5.44 8.56 2.72 13.59 5.44 79.52 0.2926TRAB14 CHOF DE CAMION 1.3189 $220.00 1.045205479 229.95 17.45 12.72 42.96 0.47 1.61 2.41 4.02 4.60 7.24 2.30 11.50 4.60 68.92 0.2997
DIAS PAGADOS / DIAS
LABORADOS
SALARIO NOMINAL $
FACTOR SALARIO BASE DE
COTIZACION
SALARIO BASE DE
COTIZACION
DE TRABAJO
CUOTA FIJA
EXCEDENTE DE TRES
SALARIOS MINIMOS
APLICACIÓN IMSS AL
EXCEDENTE
PRESTACIONES EN DINERO
GASTOS MEDICOS
PENSIONADOS
INVALIDEZ Y VIDA
RETIRO (SAR)
CESANTIA EN EDAD
AVANZADA Y VEJEZ
GUARDERIAS Y PRESTACIONES
SOCIALES
IMPUESTO SOBRE
NOMINA
SUMA PRESTACIONE
S
OBLIGACION OBRERO-
PATRONAL
ANALISIS DEL FACTOR DE SALARIO REAL
CATEGORIA PS F.S.R
CLAVE DESCRIPCION
Tp / Tl SP/SBC FSR=PSx(TP/TL)+(TP/TL)
TRAB01 CABO 1.3189 0.2926 1.70482195638132
TRAB02 OF. ALBAÑIL 1.3189 0.2977 1.71156915505714
TRAB03 OF. FIERRERO 1.3189 0.2926 1.70482195638132
TRAB04 OF. CARPINT 1.3189 0.2997 1.71422714241429
TRAB05 OF. AZULEJER 1.3189 0.2977 1.71156915505714
TRAB06 OF. PLOM/FO 1.3189 0.2977 1.71156915505714
TRAB07 OF. ELECTRIC 1.3189 0.2926 1.70482195638132
TRAB08 OF. PINTOR 1.3189 0.2997 1.71422714241429
TRAB09 OF. PEON 1.3189 0.3318 1.75655047956264
TRAB10 OP. EQ. MEN 1.3189 0.3214 1.74275620671429
TRAB11 OF. AYUDANT 1.3189 0.3171 1.73715228336964
TRAB12 OF. ALUNINIE 1.3189 0.3071 1.72387983334286
TRAB13 SOLDADOR 1.3189 0.2926 1.70482195638132
TRAB14 CHOF DE CAM 1.3189 0.2997 1.71422714241429
DIAS PAGADOS / DIAS
LABORADOS
OBLIGACION
OBRERO-PATRONAL
FACTOR DE SALARIO REAL
ANALISIS DE SALARIO INTEGRADO
CATEGORIA SALARIO F.S.R S.I
CLAVE DESCRIPCION FACTOR DE SALARIO REAL
Sn FSR=PSx(TP/TL)+(TP/TL) S.I = FSR XSn
TRAB01 CABO $260.00 1.70482195638132 443.25
TRAB02 OF. ALBAÑIL $230.00 1.71156915505714 393.66
TRAB03 OF. FIERRE $260.001.70482195638132 443.25
TRAB04 OF. CARPIN $220.001.71422714241429 377.13
TRAB05 OF. AZULEJ $230.001.71156915505714 393.66
TRAB06 OF. PLOM/F $230.00 1.71156915505714 393.66
TRAB07 OF. ELECTRI $260.001.70482195638132 443.25
TRAB08 OF. PINTOR $220.00 1.71422714241429 377.13
TRAB09 OF. PEON $130.001.75655047956264 228.35
TRAB10 OP. EQ. ME $150.001.74275620671429 261.41
TRAB11 OF. AYUDAN $160.00 1.73715228336964 277.94
TRAB12 OF. ALUNIN $190.00 1.72387983334286 327.54
TRAB13 SOLDADOR $260.001.70482195638132 443.25
TRAB14 CHOF DE CA $220.00 1.71422714241429 377.13
SALARIO NOMINAL $
SALARIO INTEGRADO
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.260 3% Tón 0.2678 $1,982.76 $530.98
Arena 0.500 8% M3 0.54 $135.47 $73.15Grava 3/4" 0.680 5% M3 0.714 $160.10 $114.31
Agua 0.195 20% M3 0.234 $50.00 $11.70Costo M3 $730.15
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.254 3% Tón 0.26162 $1,982.76 $518.73
Arena 0.470 10% M3 0.517 $135.47 $70.04Grava 3/4" 0.700 5% M3 0.735 $160.10 $117.67
Agua 0.190 20% M3 0.228 $50.00 $11.40Costo M3 $717.84
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.268 3% Tón 0.27604 $1,982.76 $547.32
Arena 0.500 8% M3 0.54 $135.47 $73.15Grava 3/4" 0.680 5% M3 0.714 $160.10 $114.31
Agua 0.215 20% M3 0.258 $50.00 $12.90Costo M3 $747.69
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.280 3% Tón 0.2884 $1,982.76 $571.83
Arena 0.470 8% M3 0.5076 $135.47 $68.76Grava 3/4" 0.700 5% M3 0.735 $160.10 $117.67
Agua 0.210 20% M3 0.252 $50.00 $12.60Costo M3 $770.87
Analisis de costo basico de concreto f'c=100 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=100 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=100 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 12-15 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=100 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 12-15 incluye materiales y desperdicios
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.323 3% Tón 0.33269 $1,982.76 $659.64
Arena 0.480 8% M3 0.5184 $135.47 $70.23Grava 3/4" 0.670 5% M3 0.7035 $160.10 $112.63
Agua 0.210 20% M3 0.252 $50.00 $12.60Costo M3 $855.10
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.308 3% Tón 0.31724 $1,982.76 $629.01
Arena 0.450 8% M3 0.486 $135.47 $65.84Grava 3/4" 0.700 5% M3 0.735 $160.10 $117.67
Agua 0.200 20% M3 0.24 $50.00 $12.00Costo M3 $824.52
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.354 3% Tón 0.36462 $1,982.76 $722.95
Arena 0.480 8% M3 0.5184 $135.47 $70.23Grava 3/4" 0.670 5% M3 0.7035 $160.10 $112.63
Agua 0.130 20% M3 0.156 $50.00 $7.80Costo M3 $913.61
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.338 3% Tón 0.34814 $1,982.76 $690.28
Arena 0.450 8% M3 0.486 $135.47 $65.84Grava 3/4" 0.670 5% M3 0.7035 $160.10 $112.63
Agua 0.130 20% M3 0.156 $50.00 $7.80Costo M3 $876.55
analisis de costo basico de concreto f'c=150 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=150 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=150 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 12-15 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=150 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 12-15 incluye materiales y desperdicios
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.355 3% Tón 0.36565 $1,982.76 $725.00
Arena 0.470 8% M3 0.5076 $135.47 $68.76Grava 3/4" 0.650 5% M3 0.6825 $160.10 $109.27
Agua 0.195 20% M3 0.234 $50.00 $11.70Costo M3 $914.73
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.337 3% Tón 0.34711 $1,982.76 $688.24
Arena 0.440 10% M3 0.484 $135.47 $65.57Grava 3/4" 0.680 5% M3 0.714 $160.10 $114.31
Agua 0.185 20% M3 0.222 $50.00 $11.10Costo M3 $879.21
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.390 3% Tón 0.401803 $1,982.76 $796.68
Arena 0.470 8% M3 0.5076 $135.47 $68.76Grava 3/4" 0.650 5% M3 0.6825 $160.10 $109.27
Agua 0.215 20% M3 0.258 $50.00 $12.90Costo M3 $987.61
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.373 3% Tón 0.38419 $1,982.76 $761.76
Arena 0.440 8% M3 0.4752 $135.47 $64.38
analisis de costo basico de concreto f'c=200 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=200 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=200 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 12-15 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=100 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 12-15 incluye materiales y desperdicios
Grava 3/4" 0.680 5% M3 0.714 $160.10 $114.31Agua 0.205 20% M3 0.246 $50.00 $12.30
Costo M3 $952.74
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.423 3% Tón 0.43569 $1,982.76 $863.87
Arena 0.465 8% M3 0.5022 $135.47 $68.03Grava 3/4" 0.640 5% M3 0.672 $160.10 $107.59
Agua 0.190 20% M3 0.228 $50.00 $11.40Costo M3 $1,050.89
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.400 3% Tón 0.412 $1,982.76 $816.90
Arena 0.435 10% M3 0.4785 $135.47 $64.82Grava 3/4" 0.670 5% M3 0.7035 $160.10 $112.63
Agua 0.180 20% M3 0.216 $50.00 $10.80Costo M3 $1,005.15
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.467 3% Tón 0.48101 $1,982.76 $953.73
Arena 0.465 8% M3 0.5022 $135.47 $68.03Grava 3/4" 0.640 5% M3 0.672 $160.10 $107.59
Agua 0.210 20% M3 0.252 $50.00 $12.60Costo M3 $1,141.95
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
analisis de costo basico de concreto f'c=250 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=250 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 8-10 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=250 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 3/4", revenimiento 12-15 incluye materiales y desperdicios
analisis de costo basico de concreto f'c=250 kg/cm2, proporción C-A-G 1:3.4, agregado máximo 1 1/2", revenimiento 12-15 incluye materiales y desperdicios
Cemento 0.467 3% Tón 0.48101 $1,982.76 $953.73Arena 0.465 8% M3 0.5022 $135.47 $68.03
Grava 3/4" 0.640 5% M3 0.672 $160.10 $107.59Agua 0.210 20% M3 0.252 $50.00 $12.60
Costo M3 $1,141.95
lechado de cemento banco
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 1.300 3% Tón 1.339 $3,836.00 $5,136.40
Agua 0.900 20% M3 1.08 $50.00 $54.00Costo M3 $5,190.40
lechado de cemento gris
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 1.300 3% Tón 1.339 $1,982.76 $2,654.92
Agua 0.900 20% M3 1.08 $50.00 $54.00Costo M3 $2,708.92
PASTA de cemento blanco
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 1.500 3% Tón 1.545 $3,826.00 $5,911.17
Agua 0.700 20% M3 0.84 $50.00 $42.00Costo M3 $5,953.17
PASTA de cemento gris
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 1.500 3% Tón 1.545 $1,982.76 $3,063.36
Agua 0.700 20% M3 0.84 $50.00 $42.00
Costo M3 $3,105.36
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.600 3% Tón 0.618 $1,982.76 $1,225.35
Arena 1.000 8% M3 1.08 $135.47 $146.31Agua 0.275 20% M3 0.33 $50.00 $16.50
Costo M3 $1,388.15
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.510 3% Tón 0.5253 $1,982.76 $1,041.54
Arena 1.100 8% M3 1.188 $135.47 $160.94Agua 0.272 20% M3 0.3264 $50.00 $16.32
Costo M3 $1,218.80
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.430 3% Tón 0.4429 $1,982.76 $878.16
Arena 1.120 8% M3 1.2096 $135.47 $163.86Agua 0.266 20% M3 0.3192 $50.00 $15.96
Costo M3 $1,057.99
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.300 3% Tón 0.309 $1,982.76 $612.67
calidra 0.150 15% M3 0.1725 $1,380.00 $238.05Arena 1.000 8% M3 1.08 $135.47 $146.31Agua 0.280 20% M3 0.336 $50.00 $16.80
Costo M3 $1,013.83
Analisis del costo basico de la mezcla (mortero) cemento - arena proporcion 1:1:2
Analisis del costo basico de la mezcla (mortero) cemento - arena proporcion 1:1:3
Analisis del costo basico de la mezcla (mortero) cemento - arena proporcion 1:1:4
Analisis del costo basico de la mezcla (mortero) cemento- calidra - arena proporcion 1:1:4
MATERIAL desp. (%) UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECemento 0.255 3% Tón 0.26265 $1,982.76 $520.77
calidra 0.125 15% M3 0.14375 $1,380.00 $198.37Arena 1.050 8% M3 1.134 $135.47 $153.62Agua 0.279 20% M3 0.3348 $50.00 $16.74
Costo M3 $889.51
Analisis del costo basico de la mezcla (mortero) cemento- calidra - arena proporcion 1:1:6
A
FECHA: 04/OCT.2012
ANALISIS DE FACTOR DE SOBRECOSTO (FSC)
dias pagados al año: dias no laborados al año:a)Dias Calendario 365.00 a)Domingos 52.00b)Aguinaldo según Ley 15.00 b)Dias Festivos 7.00c)Prima Vacacional 1.50 c)Enfermedad 1.00
381.50 d)Mal tiempo 2.00e)Fiestas Regionales 5.00f) Vacaciones 7.00
dias laborados al año (DLA): 74.00DLA= dias calendario - dias no laborados
DLA= (365.00) - (80.00)= 291.00factor de sobrecosto (FSC):
FSC= dias pagados/ dias laboradosdatos para IMSS: FSC= (381.50) / (285.00) = 1.3109966
Guarderias y Prestaciones 1.00%Enfermedad y Especie 20.40%
Maternidad 1.10% factor del salario real (FSR):Invalidez y Vida 1.75% Cuotas= 36.15%
S.A.R 2.00% FSC= 34.00%Cesantia y Vejez 3.15% 70.15%
Infonavit 5.00%Pensionados 1.05%
Dinero 0.70%FACTOR DE SALARIO REAL= 1,7015
36.15%
INTEGRACIÓN DE CUADRILLAS
CLAVE CATEGORIA UNIDAD CANTIDAD SALARIO REAL IMPORTE
C1.-CABO JOR. 0.10 $ 443.25 $ 44.33 PEON JOR. 1.00 $ 228.35 $ 228.35
TOTAL: $ 272.68
C2.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL ALBAÑIL JOR. 1.00 $ 393.66 $ 393.66 PEON JOR. 1.00 $ 228.35 $ 228.35
TOTAL: $ 666.34
C3.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL CARPINTERO JOR. 1.00 $ 377.13 $ 377.13 PEON JOR. 1.00 $ 228.35 $ 228.35
TOTAL: $ 649.81
C4.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL FIERRERO JOR. 1.00 $ 443.25 $ 443.25 AYUDANTE JOR. 1.00 $ 277.94 $ 277.94
TOTAL: $ 765.52
C5.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL AZULEJERO JOR. 1.00 $ 443.25 $ 443.25 PEÓN JOR. 1.00 $ 228.35 $ 228.35
TOTAL: $ 715.93
C6.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL PLOMERO JOR. 1.00 $ 393.66 $ 393.66 AYUDANTE JOR. 1.00 $ 277.94 $ 277.94
TOTAL: $ 715.93
CLAVE CATEGORIA UNIDAD CANTIDAD SALARIO REAL IMPORTE
C7.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL ELÉCTRICO JOR. 1.00 $ 443.25 $ 443.25 AYUDANTE JOR. 1.00 $ 277.94 $ 277.94
TOTAL: $ 765.52
C8.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL PINTOR JOR. 1.00 $ 347.43 $ 347.43 AYUDANTE JOR. 1.00 $ 277.94 $ 277.94
TOTAL: $ 669.70
C9.-
CABO JOR. 0.50 $ 443.25 $ 221.63 OFICIAL ALBAÑIL JOR. 1.00 $ 393.66 $ 393.66 PEON JOR. 6.00 $ 228.35 $ 1,370.11
TOTAL: $ 1,985.40
C10.-
CABO JOR. 1.00 $ 443.25 $ 443.25 OFICIAL ALBAÑIL JOR. 1.00 $ 393.66 $ 393.66 PEON JOR. 15.00 $ 228.35 $ 3,425.27
TOTAL: $ 4,262.19
C11.-
CABO JOR. 0.10 $ 443.25 $ 44.33 OFICIAL ALUMINIERO JOR. 1.00 $ 327.54 $ 327.54 PEON JOR. 1.00 $ 228.35 $ 228.35
TOTAL: $ 600.21
ANALISIS DE PRECIOS UNITARIOS
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Gasolina Lts 0.125 $8.19 $1.02Cerillos Pza 3.000 $0.05 $0.15
Subtotal= $1.17
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C1.- (100 m2/jor) Jor 0.01 $293.88 $2.94Subtotal= $2.94
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor %C1 0.05 $2.94 $0.15Subtotal= $0.15
COSTO DIRECTO $4.26COSTO INDIRECTO 22% $0.94PRECIO UNITARIO $5.20
CLAVE: T.P.1. UNIDAD: M2
LIMPIEZA DEL TERRENO TIPO ZACATAL, CON HERRAMIENTA MENOR, CONSIDERANDO RETIRO Y QUEMA DEL MATERIAL PRODUCTO DE LIMPIEZA. ALTURA MÁXIMA DE ARBUSTOS 2.OO MTS.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Calhidra ton 0.00025 $1,380.00 $0.35Estacas de 2" x 2" x 2.5" Pza 0.5 $8.62 $4.31
Hilo de nylon Pza 0.0167 $38.79 $0.65Clavo de 2 1/2" Kg 0.026 $17.00 $0.44
Subtotal= $5.74
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C2.- (240 m2/jor) Jor 0.004 $693.19 $2.77Subtotal= $2.77
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor %C2 0.05 $2.77 $0.14Subtotal= $0.14
COSTO DIRECTO $8.66COSTO INDIRECTO 22% $1.90PRECIO UNITARIO 10.56
CLAVE: T.P.2. UNIDAD: M2
TRAZO Y NIVELACIÓN DE LA OBRA POR MEDIOS MANUALES CONSIDERANDO POSICIONAMIENTO DE PUNTO DE APOYO, DISTANCIA ENTRE EJES Y ENCALADO DE ANCHO DE CEPA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C1.- (3.5 m3/jor) Jor 0.286 $293.88 $84.05Subtotal= $84.05
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor %C1 0.05 $84.05 $4.20Subtotal= $4.20
COSTO DIRECTO $88.25COSTO INDIRECTO 22% $19.42PRECIO UNITARIO $107.67
CLAVE: C.M.1. UNIDAD: M3
EXCAVACION MANUAL EN MATERIAL TIPO B, EN CEPAS PARA CIMENTACIÓN, CON PICO Y PALA. INCLUYE AFINE DE TALUDES Y ACARREO EN CARRETILLA DEL MATERIAL PRODUCTO DE EXCAVACIÓN. PROFUNDIDAD MAXIMA DE EXCAVACION DE 0.00 A 0.80 MTS.
CONSOLIDACIÓN DE FONDO DE EXCAVACIÓN EN CEPAS PARA CIMENTACIÓN, CON PIZON DE MANO
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Agua M3 0.0002 $71.42 $0.01Subtotal= $0.01
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C1.- (50 m2/jor) Jor 0.02 $293.88 $5.88Subtotal= $5.88
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor %C1 0.05 $5.88 $0.30Subtotal= $0.30
COSTO DIRECTO $6.19
COSTO INDIRECTO 22% $1.36
CLAVE: C.M.2. UNIDAD: M2
PRECIO UNITARIO 7.55
PLANTILLA DE CONCRETO SIMPLE F'C=100 KG/CM2, CON PROPORCIÓN C-A-G; 1:3:4 CON 5 CM DE ESPESOR.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto f'c=100 kg/cm2 m3 0.0525 $683.15 $35.87Subtotal= $35.87
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C.2 (20 m2/jor) jor 0.0500 $693.19 $34.66Subtotal= $34.66
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor %C.2 0.05 $34.66 $1.73Subtotal= $1.73
COSTO DIRECTO $72.26
COSTO INDIRECTO 22% $15.90
CLAVE: C.M.3. UNIDAD: M2
PRECIO UNITARIO 88.15
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto f´c=200 kg/cm2 m3 0.126 $841.57 $106.04Varilla #3 ton 0.0057 $11,379.31 $64.86
Alambrón 1/4" kg 0.5 $15.51 $7.76Alambre Recocido kg 0.42 $15.97 $6.71
Tablas de 15 cm x 2.50 mts pza 0.147 $41.25 $6.06Estacas pza 3 $8.62 $25.86
Clavos de 2 1/2" kg 0.0018 $17.00 $0.03Subtotal= $217.32
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C.3. (15 m2/jor) jor 0.11 $645.60 $71.02Cuadrilla C.4. (0.2 ton/jor) jor 0.031 $645.60 $20.01Cuadrilla C.9. ( 5 m3/jor) jor 0.025 $2,114.55 $52.86
Subtotal= $143.89EQUIPO
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTERevolvedora C.H. 0.19 $88.72 $16.86
Vibrador dre gasolina hr 0.014 $60.05 $0.84
CLAVE: C.M.4. UNIDAD: M2
ZAPATA CORRIDA DE CIMENTACIÓN DE 0.80 X 0.15 MTS, ARMADA CON 4 VARILLAS LONGITUDINALES DE 3/8" DE DIAM. @ 20 CMS, VARILLAS TRANSVERSALES DE 3/8" DE DIAM. @ 20 CMS. CONCRETO F'C=200 KG/CM2, AGREGADO MÁXIMO 3/4" REVENIMIENTO 8-10 CM, PROP C-A-G 1:2:2.5.
INCLUYE SUMINISTRO, HABILITADO, ARMADO, COLADO, TRASLAPES Y DESPERDICIOS DE ACERO, ELABORACION Y COLOCACIÓN DE CONCRETO, HABILITADO, CIMBRADO Y DESCIMBRADO.
Subtotal= $17.70
COSTO DIRECTO $378.91
COSTO INDIRECTO 22% $83.36
PRECIO UNITARIO 462.27
MURETE DE BLOCK DE 13 X 15 X 40, JUNTEADO CON MEZCLA CEMENTO- ARENA, PROPORCION 1:4 CON 1 CM DE ESPESOR
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Mezcla de Cemento-Arena 1:4 m3 0.01672 $985.15 $16.47Block de 13 x 15 x 40 pza 16.3 $6.47 $105.46
Agua m3 0.059 $71.42 $4.21
Subtotal= $126.14
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C.2.- (14 m2/jor) jor 0.0710 $693.19 $49.22Subtotal= $49.22
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor %C.2 0.05 $49.22 $2.46Subtotal= $2.46
CLAVE: C.M.5. UNIDAD: M2
COSTO DIRECTO $177.82
COSTO INDIRECTO 22% $39.12
PRECIO UNITARIO $216.94
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto f'c=150 kg/cm2 m3 0.0315 $847.89 $26.71Varillas #3 ton 0.0024 $11,379.31 $27.31
Alambron 1/4 kg 0.788 $15.51 $12.22Alambre Recocido kg 0.319 $15.97 $5.09
Tablas de 20 cm x 2.50 pza 0.147 $71.00 $10.44Clavos 2 1/2" kg 0.07 $17.00 $1.19Polín de 2 x 2" pza 0.048 $32.33 $1.55
Agua m3 0.006 $71.42 $0.43Subtotal= $84.94
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C.4 (15 m2/jor) jor 0.027 $645.60 $17.43Cuadrilla C.3 (0.20 ton/jor) jor 0.018 $645.60 $11.62Cuadrilla C.9 (5.0 m3/ jor) jor 0.0062 $693.19 $4.30
Subtotal= $33.35
HERRAMIENTA Y EQUIPO
CLAVE: C.M.6. UNIDAD: ML
CADENA DE DESPLANTE DE 15 X 20 CM, ARMADA CON 4 VARILLAS DE 3/8" DE Ø, ESTRIBOS DE 1/4" @ 20 CMS. INCLUYE SUMINISTRO, HABILITADO, ARMADO Y COLOCACION DE ACERO DE REFUERZO. CONCRETO F'C=150 KG/CM2 PROPORCION C-A-G 1:2:3.5. HABILITADO CIMBRADO Y
DESCIMBRADO.
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTEHerramienta menor % Mano de obra 0.05 $33.35 $1.67
Subtotal= $1.67
COSTO DIRECTO $119.96COSTO INDIRECTO 22% $26.39PRECIO UNITARIO $146.35
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Agua M3 0.3276 $71.42 $23.40Subtotal= $23.40
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C1.(2.75 m3/Jor)- Jor 0.364 $293.88 $106.97Subtotal= $106.97
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
CLAVE: C.M.7. UNIDAD: M3
RELLENO Y COMPACTACIÓN DE MATERIAL PRODUCTO DE LA EXCAVACION, EN CEPAS DE CIMENTACIÓN CON PALA Y PIZON DE MANO, EN CEPAS NO MAYORES A 20 CM. INCLUYE ACARREO DENTRO DE LA OBRA.
Herramienta menor % Mano de obra 0.05 $106.97 $5.35Subtotal= $5.35
COSTO DIRECTO $135.72COSTO INDIRECTO 22% $29.86PRECIO UNITARIO $165.58
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto F´C=150 kg/cm2 m3 0.0273 $847.89 $23.15Varillas N°3 ton 0.0024 $11,379.31 $27.31
Alambrón de 1/4" kg 0.6526 $15.51 $10.12Alambre Recocido kg 0.306 $15.97 $4.89andamio metálico renta/dia 0.005 $238.56 $1.19Duela de 25 cms pza 0.147 $71.00 $10.44
Polin 2" x 4" x 2,50m pza 0.0960 $42.24 $4.06Clavos de 2 1/2" kg 0.022 $17.00 $0.37
Subtotal= $81.53MANO DE OBRA
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECuadrilla C2.-(9,5ml/J ) Jor 0.105 693.88 $72.86
Subtotal= $72.86
CLAVE: E.C.2 UNIDAD: M
CASTILLO DE 13 X 20 CMS, ARMADO CON 4 VARILLAS DE 3/8" DE Ø Y ESTRIBOS DE 1/4" DE Ø @20 CMS. INCLUYE SUMINISTRO, HABILITADO, ARMADO Y COLOCACIÓN DE ACERO DE REFUERZO, CONCRETO F´C=150 KG/CM2 EN PROPORCION C-A-G 1:2:3.5. HABILITADO, CIMBRADO DESCIMBRADO
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor M.O. 0.05 72.86 3.64Revolvedora hr 0.0500 $88.72 $4.44
Vibrador para concreto hr 0.05 $60.05 $3.00Subtotal= $8.08
COSTO DIRECTO $162.46COSTO INDIRECTO 22% $35.74PRECIO UNITARIO $198.20
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto F´C=150 kg/cm2 m3 0.0273 $841.57 $22.97Varillas N°3 ton 0.0024 $11,379.31 $27.31
Alambrón de 1/4" kg 0.788 $15.51 $12.22Alambre Recocido kg 0.319 $15.97 $5.09
Duela de 25 cms pza 0.147 $71.00 $10.44Clavos de 2 1/2" kg 0.087 $17.00 $1.48
andamio metálico renta/dia 0.005 $238.56 $1.19Polin 4" x 4" x 2,50m pza 0.1920 $64.66 $12.41
Agua m3 0.0050 $71.42 $0.60Subtotal= $93.73
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C.4 (0.20 Ton/Jor) Jor 0.018 $645.60 $11.62Cuadrilla C.3 (13m2/Jor) Jor 0.031 $645.60 $20.01Cuadrilla C.2 ( 0.85 m3/Jor) Jor 0.032 $693.19 $22.18
CLAVE: E.C.3 UNIDAD: M
CADENA DE REMATE DE 13 X 20 CMS, ARMADO CON 4 VARILLAS DE 3/8" DE Ø Y ESTRIBOS DE 1/4" DE Ø @ 20 CMS. INCLUYE SUMINISTRO, HABILITADO, ARMADO Y COLOCACIÓN DE ACERO DE REFUERZO, CONCRETO F'C= 150 KG/CM2 EN PROPORCIÓN C-A-G 1:2:3.5. HABILITADO,
CIMBRADO Y DESCIMBRADO
Subtotal= $53.82HERRAMIENTA Y EQUIPO
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTEHerramienta menor % 0.05 $53.82 $2.69
Revolvedora hr 0.0700 $88.72 $6.21Vibrador para concreto hr 0.07 $60.05 $4.20
Subtotal= $13.10COSTO DIRECTO $160.65COSTO INDIRECTO 22% $35.34PRECIO UNITARIO $195.99
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto F´C=150 kg/cm2 m3 0.0273 $841.57 $22.97Varillas N°3 ton 0.0024 $11,379.31 $27.31
Alambrón de 1/4" kg 0.788 $15.51 $12.22Alambre Recocido kg 0.319 $15.97 $5.09
Duela de 25 cms pza 0.147 $71.00 $10.44Clavos de 2 1/2" kg 0.087 $17.00 $1.48
andamio metálico renta/dia 0.005 $238.56 $1.19Polin 4" x 4" x 2,50m pza 0.1920 $64.66 $12.41
Agua m3 0.0050 $71.42 $0.60Subtotal= $93.73
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C.4 (0.20 Ton/Jor) Jor 0.018 $645.60 $11.62Cuadrilla C.3 (13m2/Jor) Jor 0.031 $645.60 $20.01
CLAVE: E.C.2 UNIDAD: M
CADENA DE CERRAMIENTO DE 13 X 20 CMS, ARMADO CON 4 VARILLAS DE 3/8" DE Ø Y ESTRIBOS DE 1/4" DE Ø @ 20 CMS. INCLUYE SUMINISTRO, HABILITADO, ARMADO Y COLOCACIÓN DE ACERO DE REFUERZO, CONCRETO F'C= 150 KG/CM2 EN PROPORCIÓN C-A-G 1:2:3.5. HABILITADO,
CIMBRADO Y DESCIMBRADO
Cuadrilla C.2 ( 0.85 m3/Jor) Jor 0.032 $693.19 $22.18Subtotal= $53.82
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % 0.05 $53.82 $2.69Revolvedora hr 0.0700 $88.72 $6.21
Vibrador para concreto hr 0.07 $60.05 $4.20Subtotal= $13.10
COSTO DIRECTO $160.65COSTO INDIRECTO 22% $35.34PRECIO UNITARIO $195.99
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto F´c= 200 kg/cm2 m3 0.105 $841.57 $88.36Varillas del N°3 ton 0.0181 $11,379.31 $205.97
Alambre Recocido kg 1.81 $15.97 $28.91Clavos de 2 1/2" kg 0.305 $17.00 $5.19Cimbrado de losa m2 1 $23.00 $23.00
Agua m3 0.005 $71.42 $0.36Andamio metálico pza 0.09 $35.34 $3.18
Subtotal= $354.96
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
CLAVE: E.C.4 UNIDAD: M2
LOSA PLANA DE CONCRETO ARMADO DE 10 CM DE ESPESOR, ARMADA CON VARILLAS DE 3/8" Ø @ 20 CMS EN AMBOS SENTIDOS. CONCRETO F´C= 200 KG/CM2, AGREGADO MÁXIMO DE 3/4, REVENIMIENTO 8-10 CM. ELABORACION, COLOCACION, CURADO DE CONCRETO, HABILITADO Y ARMADO DE
ACERO DE REFUERZO. HABILITADO, CIMBRADO Y DESCIMBRADO
Cuadrilla C3.- (12 m2/jor) jor 0.083 $645.60 $53.58Cuadrilla C4.- (0,18 ton/jor) jor 0.133 $645.60 $85.86Cuadrilla C10.- (20 m3/jor) jor 0.005 $4,567.36 $22.84
Subtotal= $162.29HERRAMIENTA Y EQUIPO
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTEHerramienta menor % 0.05 $162.29 $8.11
Revolvedora hr 0.04 $88.72 $3.55Vibrador para concreto hr 0.04 $60.05 $2.40
Subtotal= $14.07
COSTO DIRECTO $531.31COSTO INDIRECTO 22% $116.89PRECIO UNITARIO $648.20
MURO DE BLOCK DE 13 X 15 X 40 CM, JUNTEADO CON MEZCLA DE CEMENTO ARENA EN PROPORCION 1:4 CON 1.5 CMS DE ESPESOR PROMEDIO.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Block solido de 13x 15 x 40 pza 18.28 $6.47 $118.27Cemento-Arena prop:1:4 m3 0.01672 $985.15 $16.47
Agua m3 0.045 $71.42 $3.21Subtotal= $137.96
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C2.- (12 m2/jor) Jor 0.0833333333333333 $693.19 $57.77Subtotal= $57.77
CLAVE: A.A.1 UNIDAD: M2
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $57.77 $2.89Andamio Metalico renta/dia 0.08125 $16.00 $1.30
Subtotal= $4.19
COSTO DIRECTO $199.91COSTO INDIRECTO 22% $43.98PRECIO UNITARIO $243.89
FIRMES DE CONCRETO F'C=200 KG/CM2 PROPORCIÓN C-A-G 1:2:3.5, ESPESOR DE 8 CM ACABADO RÚSTICO CON REGLA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto f´c= 200 kg /cm2 m3 0.084 $841.57 $70.69Agua m3 0.008 $71.42 $0.57
Subtotal= $71.26
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C2.- (1 m3/jor) Jor 0.084 $693.19 $58.23
CLAVE: A.A.2 UNIDAD: M2
Subtotal= $58.23
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $58.23 $2.91Subtotal= $2.91
COSTO DIRECTO $132.40COSTO INDIRECTO 22% $29.13PRECIO UNITARIO $161.53
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Loseta 30x30 cm m2 1.05 $185.34 $194.61Adhesivo para pegapiso saco 0.33 $43.27 $14.28
Lechada de cemento blanco m3 0.0013 $4,189.33 $5.45Subtotal= $214.33
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C5.- (07 m2/jor) Jor 0.142857142857143 $707.32 $101.05
CLAVE: A.A.3 UNIDAD: M2
SUMINISTRO Y COLOCACIÓN DE PISO DE LOSETA DE 30 X 30 CM, ASENTADO CON PEGAZULEJO Y JUNTAS DE CEMENTO BLANCO. INCLUYE CORTES RECTOS, REBABAS, REMATES Y DESPERDICIOS.
Subtotal= $101.05
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $101.05 $5.05Subtotal= $5.05
COSTO DIRECTO $320.43COSTO INDIRECTO 22% $70.49PRECIO UNITARIO $390.92
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Mezcla cemento arena 1:5 m3 0.018 $865.56 $15.58Agua m3 0.003 $71.42 $0.21
Subtotal= $15.79
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
CLAVE: A.A.4 UNIDAD: M2
APLANADO ACABADO FINO EN MUROS DE 1.5 CM DE ESPESOR CON MORTERO CEMENTO- ARENA, PROPORCION 1:5 A PLOMO Y REGLA. INCLUYE MANO DE OBRA Y DESPERDICIOS.
Cuadrilla C2.- (14 m2/jor) Jor 0.0714 $693.19 $49.51Subtotal= $49.51
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $49.51 $2.48Andamio Metalico renta/dia 0.07143 $16.00 $1.14
Subtotal= $2.48
COSTO DIRECTO $67.78COSTO INDIRECTO 22% $14.91PRECIO UNITARIO $82.69
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Mezcla cemento arena 1:5 m3 0.025 $865.56 $21.64Agua m3 0.004 $71.42 $0.29
Subtotal= $21.93
MANO DE OBRA
CLAVE: A.A.5 UNIDAD: M2
APLANADOFINO EN LOSA CON MORTERO CEMENTO-ARENA PROP; 1:5 A PLOMO Y REGLA DEJANDO 2 CM DE ESPESOR. INCLUYE MANO DE OBRA Y DESPERDICIOS.
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECuadrilla C2.- (11 m2/jor) Jor 0.0910 $693.19 $63.08
Subtotal= $63.08
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $63.08 $3.15Andamio Metalico renta/dia 0.07143 $16.00 $1.14
Subtotal= $3.15
COSTO DIRECTO $88.16COSTO INDIRECTO 22% $19.40PRECIO UNITARIO $107.56
PINTURA VINÍLICA EN MUROS Y LOSA. TRABAJO TERMINADO, INCLUYE PREPARACIÓN DE SUPERFICIE Y MANO DE OBRA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Pintura comex vinimex 19 lt 0.0126 $1,193.10 $15.03Sellador 5 X 1 comex 19 lt 0.0026 $512.17 $1.33Rodillo para pintura pieza 0.01 $35.34 $0.35
Brocha de 4" pieza 0.01 $44.83 $0.45
CLAVE: A.A.6 UNIDAD: M2
Agua m3 0.005 $71.42 $0.36Subtotal= $17.52
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C8.- (26 m2/jor) Jor 0.0380 $700.92 $26.63Subtotal= $26.63
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $26.63 $1.33Andamio Metalico renta/dia 0.0315 $16.00 $0.50
Subtotal= $1.84
COSTO DIRECTO $45.99COSTO INDIRECTO 22% $10.12PRECIO UNITARIO $56.11
IMPERMEABILIZANTE EN AZOTEA, TRABAJO TERMINADO, INCLUYE PREPARACIÓN DE SUPERFICIE Y MANO DE OBRA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Primacreto a cubeta 4 lts pza 0.1375 $107.00 $14.71Fibracreto presentación a 4 lts cb 0.125 $127.00 $15.88
Flexocreto 100, 110 m2 roll 0.02 $35.34 $0.71
CLAVE: A.A.7 UNIDAD: M2
Agua m3 0.0137 $71.42 $0.98Gravilla cubeta de 20 kg cb 0.01048 $495.00 $5.19
Subtotal= $37.46
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C2.- (16 m2/jor) Jor 0.0625 $693.19 $43.32Subtotal= $43.32
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $43.32 $2.17Subtotal= $2.17
COSTO DIRECTO $82.95COSTO INDIRECTO 22% $18.25PRECIO UNITARIO $101.20
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Concreto F´c= 150 kg/cm2 m3 0.099 $847.89 $83.94
CLAVE: A.A.8 UNIDAD: PZA
REGISTRO DE 40 X 6O CM HASTA 1M DE PROF CON MUROS DE TABIQUE DE 6X13X26 DE ESPESOR CON JUNTAS DE 1.5 CM APLANADO Y PULIDO INT. JUNTEADO CON MORTERO CEM-ARENA 1:4 CON PLANTILLA DE CONCRETO DE 150 KG/CM2 , AGR MAX 3/4" INCL. MATERIALES, RELLENO, MANO DE
OBRA, DESP., HERR. Y EQ.
Tabique rojo de 6 x 13 x 26 cm pieza 172 $1.81 $311.32Mezcla cem-arena 1:4 m3 0.182 $985.15 $179.30
lechada de cemento gris m3 0.033 $2,310.43 $76.24Agua m3 0.03 $71.42 $2.14
Subtotal= $652.95
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C2.- (2 pzas/jor) jor 0.5 $693.19 $346.60Subtotal= $346.60
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % 0.05 $346.60 $17.33Subtotal= $17.33
COSTO DIRECTO $1,016.87COSTO INDIRECTO 22% $223.71PRECIO UNITARIO $1,240.58
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTEConcreto F´c= 150 kg/cm2 m3 0.024 $847.89 $20.35
CLAVE: A.A.8 UNIDAD: PZA
TAPA DE REGISTRO DE 0.40 X 0.60 M CON MARCO Y CONTRAMARCO METÁLICO TIPO LIGERO DE CONCRETO F´C= 150 KG/CM2.INCLUYE MATERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIA.
Mezcla cem-arena 1:4 m3 0.0038 $985.15 $3.74Alambrón del No 2 kg 0.63 $15.51 $9.77Alambre recocido kg 0.063 $15.97 $1.01
Clavo de 21/2" kg 0.035 $17.00 $0.60Duela de 2" pza 0.096 $23.28 $2.23
Subtotal= $37.70
MANO DE OBRA
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTECuadrilla C2.- (10 pzas/jor) jor 0.1 $693.19 $69.32
Subtotal= $69.32
HERRAMIENTA Y EQUIPO
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTEHerramienta menor % 0.05 $346.60 $17.33
Subtotal= $17.33
COSTO DIRECTO $124.35COSTO INDIRECTO 22% $27.36PRECIO UNITARIO $151.71
SUMINISTRO Y COLOCACIÓN DE PUERTA DE CANCELERÍA DE 0.90 X 2.10 MTS. INCLUYE MATERIALES Y MANO DE OBRA.
MATERIALES
CLAVE: HER1 UNIDAD: Pieza
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTEPuerta de cancelería de 0.90 x 2.10 pieza 1 $1,150.00 $1,150.00
Subtotal= $1,150.00
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C 11 (3 pzas/jor) Jor 0.3300 $639.19 $210.93Subtotal= $210.93
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $210.93 $10.55Subtotal= $10.55
COSTO DIRECTO $1,371.48COSTO INDIRECTO 22% $301.73PRECIO UNITARIO $1,673.20
CLAVE: HER2 UNIDAD: Pieza SUMINISTRO Y COLOCACIÓN DE VENTANA DE CANCELERÍA DE 0.80 X 0.90 MTS. INCLUYE MATERIALES Y MANO DE OBRA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Ventana de cancelería de 0.80 x 0.90 pieza 1 $474.14 $474.14Subtotal= $474.14
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C 11 (3 pzas/jor) Jor 0.3300 $639.19 $210.93Subtotal= $210.93
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $210.93 $10.55Subtotal= $10.55
COSTO DIRECTO $695.62COSTO INDIRECTO 22% $153.04PRECIO UNITARIO $848.66
SUMINISTRO Y COLOCACIÓN DE VENTANA DE CANCELERÍA PARA BAÑO DE 0.40 X 0.40 MTS. INCLUYE MATERIALES Y MANO DE OBRA.
CLAVE: HER3 UNIDAD: Pieza
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Ventana de cancelería de 0.40 x 0.40 pieza 1 $258.62 $258.62Subtotal= $258.62
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C 11 (5 pzas/jor) Jor 0.2000 $639.19 $127.84Subtotal= $127.84
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $127.84 $6.39Subtotal= $6.39
COSTO DIRECTO $392.85COSTO INDIRECTO 22% $86.43PRECIO UNITARIO $479.28
INSTALACIÓN ELÉCTRICA EN MUROS (RAMALEO Y MANGUEREADO)
CLAVE: IEC.1 UNIDAD: LOTE___
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
m 10.8 $2.15 $23.22Segueta de diente grueso pieza 1 $10.34 $10.34
Subtotal= $33.56
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 ( 8 lotes/jor9.- Jor 0.1250 $705.21 $88.15Subtotal= $88.15
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $88.15 $4.41Subtotal= $4.41
COSTO DIRECTO $126.12COSTO INDIRECTO 22% $27.75PRECIO UNITARIO $153.86
Tubería poliflex naranja de 1/2" para uso eléctrico
CLAVE: IEC2 UNIDAD: LOTE____
INSTALACIÓN ELÉCTRICA EN LOSA (MANGUEREADO). INCLUYE MATERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIA)
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
m 15 $2.15 $32.25Segueta de diente grueso pieza 1 $10.34 $10.34
Subtotal= $42.59
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 ( 4 lotes/jor9.- Jor 0.2500 $705.21 $176.30Subtotal= $176.30
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $176.30 $8.82Subtotal= $8.82
COSTO DIRECTO $227.71COSTO INDIRECTO 22% $50.10PRECIO UNITARIO $277.80
Tubería poliflex naranja de 1/2" para uso eléctrico
CLAVE: IEC.3 UNIDAD: LOTE___
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cable de 600 v. Calibre No 12 m 25.8 $6.03 $155.57Chalupa pieza 6 $2.57 $15.42Cinta aislante pieza 0.1 $9.48 $0.95
Subtotal= $171.94
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 (4 lotes/jor).- Jor 0.2500 $705.21 $176.30 Subtotal= $176.30
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $176.30 $8.82Subtotal= $8.82
COSTO DIRECTO $357.06COSTO INDIRECTO 22% $78.55PRECIO UNITARIO $435.61
CLAVE: IEC.3 UNIDAD: LOTE___
INSTALACIÓN ELÉCTRICA EN MUROS Y LOSA (CABLEADO E INSTALACIÓN DE CHALUPAS). INCL. MATERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIA
SUMINISTRO E INSTALACIÓN DE CENTROS INCANDESCENTES. INCL. MATERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIA
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Soquet de porcelana de 1/2" pieza 1 $8.19 $8.19Apagador sencillo pieza 1 $16.81 $16.81Placa de 3 ventanas pieza 1 $15.95 $15.95Luminaria fluorescente pieza 1 $43.00 $43.00
Subtotal= $83.95
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 ( 8 salidas/ jor).- Jor 0.1250 $705.21 $88.15 Subtotal= $88.15
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $88.15 $4.41Subtotal= $4.41
COSTO DIRECTO $176.51COSTO INDIRECTO 22% $38.83PRECIO UNITARIO $215.34
CLAVE: IEC.4 UNIDAD: SDA__
SUMINISTRO E INSTALACIÓN DE CONTACTOS. INCL. MATERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Contacto polarizado pieza 1 $16.81 $16.81Placa de 2 ventanas pieza 1 $15.95 $15.95
Subtotal= $32.76
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 ( 8 salidas/ jor9.- Jor 0.1250 $705.21 $88.15 Subtotal= $88.15
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $88.15 $4.41Subtotal= $4.41
COSTO DIRECTO $125.32COSTO INDIRECTO 22% $27.57PRECIO UNITARIO $152.89
CLAVE: IEC.5 UNIDAD: SDA__
SUMINISTRO, CONEXIÓN Y COLOCACIÓN DE TUBO Y MUFA VERTICAL DE 1 1/4"Ø. INCLUYE HERAMIENTA, MATERIALES Y MANO DE OBRA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Tubo para mufa pieza 1 $86.00 $86.00Mufa galvanizada pieza 1 $9.00 $9.00
Subtotal= $95.00
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 ( 4 pzas/ jor).- Jor 0.2500 $705.21 $176.30 Subtotal= $176.30
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $176.30 $8.82Subtotal= $8.82
COSTO DIRECTO $280.12COSTO INDIRECTO 22% $61.63PRECIO UNITARIO $341.74
CLAVE: IEC.6 UNIDAD: PIEZA__
SUMINISTRO Y COLOCACIÓN DE BASE PARA MEDIDOR. INCLUYE CONEXIÓN, HERRAMIENTAS Y MANO DE OBRA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Base para medidor pieza 1 $72.41 $72.41 Subtotal= $72.41
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 ( 4 pzas/ jor).- Jor 0.2500 $705.21 $176.30 Subtotal= $176.30
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $176.30 $8.82Subtotal= $8.82
COSTO DIRECTO $257.53COSTO INDIRECTO 22% $56.66PRECIO UNITARIO $314.18
CLAVE: IEC.7 UNIDAD: PZA__
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Centro de carga para una pastilla pieza 1 $91.00 $91.00Pastilla termomagnética pieza 1 $43.00 $43.00
Subtotal= $134.00
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C7 ( 4 pzas jor).- Jor 0.2500 $705.21 $176.30 Subtotal= $176.30
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $176.30 $8.82Subtotal= $8.82
COSTO DIRECTO $319.12COSTO INDIRECTO 22% $70.21PRECIO UNITARIO $389.32
CLAVE: IEC.8 UNIDAD: PIEZA__
SUMINISTRO Y COLOCACIÓN DE CENTRO DE CARGA CON 1 PASTILLA TERMOMAGNÉTICA DE 30 AMP. INCLUYE MATERIALES, HERRAMIENTAS Y MANO DE OBRA.
INSTALACIÓN SANITARIA EN LA CIMENTACIÓN Y EN MUROS (RAMALEO) INCLUYE MATERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIA
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Tubo de PVC sanitario de 2" m 1 $11.16 $11.16Tubo de PVC sanitario de 4" m 3.2 $24.57 $78.62
Codo de PVC de 2" pza 1 $2.15 $2.15Cespol de 2" pza 1 $30.17 $30.17
Reducción de 4 x 2" pza 1 $7.76 $7.76Tee de PVC 2" m2 1 $3.00 $3.00
Pegamento para PVC pza 0.5 $47.41 $23.71Lija fina pza 1 $5.17 $6.46
Subtotal= $163.03
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C6.- (2 lotes/jor) jor 0.5 $752.80 $376.40Subtotal= $376.40
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % 0.05 $376.40 $18.82Subtotal= $18.82
COSTO DIRECTO $558.25COSTO INDIRECTO 22% $122.81
CLAVE: HS1 UNIDAD: LOTE
PRECIO UNITARIO $681.06
INSTALACIÓN HIDRAÚLICA EN LA CIMENTACIÓN Y EN MUROS (RAMALEO). INCLUYE MSTERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIA
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Tubo de cobre de 1/2" ml 4.5 $53.88 $242.46Codo de cobre de 1/2" pza 1 $5.00 $5.00
Llave de nariz pza 1 $26.00 $26.00Carrete de soldadura pza 0.5 $112.07 $56.04
Gas butano pza 0.5 $25.86 $12.93abrazadera para hidrotoma pza 1 $38.79 $38.79
Cinta teflón pza 1 $4.74 $4.74Lija fina pza 1 $6.46 $5.17
Válvula de inserción pza 1 $121.00 $121.00Subtotal= $512.13
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C6.- (3 lotes/jor) Jor 0.333 $693.19 $230.83Subtotal= $230.83
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $230.83 $11.54Andamio Metalico renta/dia 0.08125 $16.00 $1.30
Subtotal= $12.84
CLAVE: HS2 UNIDAD: LOTE
COSTO DIRECTO $755.80COSTO INDIRECTO 22% $166.28PRECIO UNITARIO $922.08
SUMINISTRO Y COLOCACIÓN DEL TINACO DE 750 LT. INCLUEYE MANO DE OBRA Y HERRAMIENTA NECESARIA
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Tinaco rotoplas de 750 lt pza 1 $1,099.13 $1,099.13Mezcla cemento arena 1:4 m3 0.006 $985.15 $5.91
Block sólido pza 4 $6.47 $25.88Subtotal= $1,130.92
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C6.- (1 m3/jor) Jor 0.084 $752.80 $63.24Subtotal= $63.24
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $63.24 $3.16Subtotal= $3.16
COSTO DIRECTO $1,197.32COSTO INDIRECTO 22% $263.41PRECIO UNITARIO $1,460.73
CLAVE: HS3 UNIDAD: PZA
SUMINISTRO E INSTALACIÓN DEL W.C. INCLUYE MATERIALES, MANO DE OBRA Y HERRAMINETA NECESARIA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Juego de inodoro Jgo 1 $603.49 $603.49Cuello de cera pza 1 $10.34 $10.34
Manguera de extensión para WC pza 1 $24.35 $24.35Pijas para WC pza 2 $5.00 $10.00
Lechada de cemento blanco m3 0.0025 $4,189.33 $10.47Subtotal= $658.65
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C6.- (03 pzas/jor) Jor 0.33 $752.80 $248.42Subtotal= $248.42
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Herramienta menor % Mano de obra 0.05 $248.42 $12.42Subtotal= $12.42
COSTO DIRECTO $919.50COSTO INDIRECTO 22% $202.29
CLAVE: HS 4 UNIDAD: PZA
PRECIO UNITARIO $1,121.79
SUMINISTRO E INSTALACIÓN DEL LAVABO. INCLUYE MATERIALES, ACCERSORIOS, MANO DE OBRA Y HERRAMIENTA NECESARIA.
MATERIALESDESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Lavabo pza 1 $172.41 $172.41Llave de aleta pza 1 $202.61 $202.61Contrarejilla pza 1 $106.96 $106.96
Cespol cromado p/ lavabo pza 1 $111.84 $111.84Pijas de 1/4" x 1" pza 8 $1.57 $12.56
Adaptador de hule pza 1 $10.43 $10.43Manguera de extensión pza 1 $30.43 $30.43
Accesorios de baño jgo 1 $85.85 $85.85Lechada de cemento blanco m3 0.0025 $4,189.33 $10.47
Subtotal= $743.56
MANO DE OBRADESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
Cuadrilla C6.- (3 pzas/jor) Jor 0.3300 $752.80 $248.42Subtotal= $248.42
HERRAMIENTA Y EQUIPODESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
CLAVE: HS 5 UNIDAD: PZA
Herramienta menor % Mano de obra 0.05 $248.42 $12.42Subtotal= $12.42
COSTO DIRECTO $1,004.41COSTO INDIRECTO 22% $220.97PRECIO UNITARIO $1,225.37
PRESUPUESTO DE OBRA
DESCRIPCION UNIDAD CANTIDAD P.U. TOTAL
m2 27.72 $6.72 $186.28
m2 27.72 $3.95 $109.49
m3 12.65 $119.68 $1,513.95Consolidación de fondo de excavación en cepas para cimentación con pizon de mano. m2 15.81 $12.75 $201.58
Plantilla de concreto simple f'c=100 kg/cm2, con proporción C-A-G 1:3:4 con 5cm de espesor. Incluye cimbrado m2 29.42 $85.91 $2,527.47
ml 25.42 $617.17 $15,688.46Murete de Block de 13x15x40 junteado con mezcla cemento arena, proporcion 1:4 con 1 cm de espesor. m2 16.59 $244.92 $4,063.22
ml 27.65 $264.49 $7,313.15
ml 5.55 $245.77 $1,364.02
m3 4.58 $70.63 $323.49
ml 24.4 $225.69 $5,506.84
Limpieza del terreno tipo zacatal, con herramienta menor considerando retiro y quema del material producto de limpieza. Altura máxima de arbustos 2.00 mts.
Trazo de la obra, considerando posicionamiento de punto de apoyo, distancia entre ejes y encalado de ancho de cepas.
Excavación manual en material tipo B, en cepas para cimentación, con pico y pala. Incluye afine de taludes, y acarreo en carretilla del material producto de excavación, profundidad máxima de excavación de 0.00 a 0.80
Zapata Corrida de Cimentación de 80 x 15 cm, armada con 4 varillas longitudinales de 3/8" de Ø @ 20 cms, varillas transversales de 3/8" de Ø @ 20 cms. Concreto f'c=200 kg/cm2, agregado máximo de 3/4" revenimiento 8-10 cm, prop; C-A-G 1:2:2.5. Incluye suministro, habilitado, armado, colado, traslapes, y desperdicios de acero, elaboración y colocación de concreto. Habilitado cimbrado y descimbrado.
Cadena de Desplante de 15 x 20 cm, armada con 4 varillas de 3/8" de Ø, estribos de 1/4"@ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2 prop; C-A-G 1:2:3.5, habilitado, cimbrado y descimbrado.
Trabe de Liga de Cimentación de 30 x 15 cm, armada con 6 varillas de 3/8"Ø y estribos de 1/4" @ 10 cm y 20 cm, respectivamente. Incluye suministro, habilitado, armado y colocación de acero de refuerzo. Concreto f'c=200 kg/cm2 en proporción C-A-G 1:2:2.5. Incluye habilitado, cimbrado y descimbrado.
Relleno y compactación de material producto de excavación en cepas de cimentación con pala y pizon de mano en cepas de 20 cm. Incluye acarreo dentro de la obra.
Castillo de 13 x 13 cm, armado con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo. Concretos f'c=150 kg/cm2, prop; C-A-G 1:2:3.5. Habilitado, cimbrado y descimbrado.
ml 21.35 $250.33 $5,344.55
DESCRIPCION UNIDAD CANTIDAD P.U. TOTAL
ml 27.11 $268.17 $7,270.09
ml 5.85 $340.98 $1,994.73
ml 25.36 $263.13 $6,672.98
ml 13.21 $263.13 $3,475.95
m2 38.08 $641.65 $24,434.03
Muro de Block de 13 x 15 x 40 cm, junteado con mezcla de cem-arena, prop 1:4 con 1.5 cm de espesor promedio m2 60.03 $265.38 $15,930.76
Firmes de concreto f'c=200 kg/cm2 proporción C-A-G 1:2:3.5, espesor de 8 cm acabado rustico con regla. m2 19.05 $171.03 $3,258.12
m2 19.05 $252.12 $4,802.89
m2 85.86 $124.18 $10,662.09
m2 38.43 $151.94 $5,839.05
Pintura vinilica en muros y losa. Trabajo terminado, incluye preparación de superficie y mano de obra. m2 124.29 $43.59 $5,417.80
Castillo de 13 x 20 cm, armado con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo. Concretos f'c=150 kg/cm2, prop; C-A-G 1:2:3.5. Habilitado, cimbrado y descimbrado.
Cadena Intermedia de 13 x 20 cms, armada con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2, proporción C-A-G 1:2:3.5. Habilitado, cimbrado y descimbrado.
Trabe de Refuerzo de 15 x 40 cms, armada con 6 varillas de 3/8"Ø, y estribod de 1/4" @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2 proporción C-A-G 1:2:3.5. Habilitado, cimbrado y descimbrado
Cadena de Remate de 13 x 20 cms, armada con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2, proporción C-A-G 1:2:3.5. Habilitado, cimbrado y descimbrad
Cadena de Cerramiento de 13 x 20 cms, armada con 4 varillas de 3/8" Ø y estribos de 1/4" Ø @ 20 cms. Incluye suministro, habilitado, armado y colocación de acero de refuerzo, concreto f'c=150 kg/cm2, proporción C-A-G 1:2:3.5. Habilitado, cimbrado y descimbrado.
Losa Plana de concreto armado de 10 cms de espesor, armada con 4 varillas de 3/8" Ø @20cms en ambos sentidos. Concreto f'c= 200 kg/cm2, agregado máximo de 3/4" revenimiento 8-10 cm. Incluye materiales, desperdicios, traslapes, ganchos y bastones. Elaboración, colocacion, curado de concreto. Habilitado, cimbrado y descimbrado.
Suministro y colocación de piso de lozeta de 60 x 60 cm, asentado con pegazulejo y juntas de cemento blanco. Incluye cortes rectos, rebabas, remates y desperdicios.
Aplanado acabado fino en marcos de 1.5 cm de espesor con mortero cemento- arena, proporcion 1:5 a plomo y regla. Incluye mano de obra y desperdicios.
Aplanadofino en losa con mortero cemento-arena prop; 1:5 a plomo y regla dejando 2 cm de espesor. Incluye mano de obra y desperdicios.
Impermeabilizante en azotea, trabajo terminado, incluye preparación de superficie y mano de obra. m2 38.08 $99.91 $3,804.57
Limpieza de pisos, con cepillo, agua, jabon. m2 19.09 $17.77 $339.23
pieza 3 $4,169.24 $12,507.72
DESCRIPCION UNIDAD CANTIDAD P.U. TOTAL
pieza 2 $1,693.97 $3,387.94
Suministro y colocación de Salida incandecente de 22 wats. Incluye foco, socced, cableado y mano de obra. Salida 8 $376.01 $3,008.08Salida para contacto polarizado sencillo. Incluye tubería, cableado, artefactos, y mano de obra. Salida 4 $395.24 $1,580.96Suministro y colocación de apagador sencillo. Incluye tubería, cableado, artefactos y mano de obra. Salida 2 $204.32 $408.64Salida para contacto polarizado trifacico. Incluye tubería, cableado, artefactos, y mano de obra. Salida 4 $276.90 $1,107.60Limpieza total de obra terminada con escoba, rastillo, agua, jabon, etc. m2 27.72 $19.78 $548.30
Total de presupuesto sin iva $160,594.04Total de presupuesto con iva $186,289.08
Suministro y colocación de puerta de madera entablerada de 0.90 x 2.10 mts. Elaborada con madera de primera, acabado con sellador y laca. Incluye materiales y mano de obra.
Suministro y colocación de ventana de perfiles tubulares, medidas de 0.80 x 1.20. Inlcluye primera pintura, bagueta y vidrio de 6 mm de espesor y perfiles necesarios.
ANALISIS DE COSTO HORARIO
vibrador para concreto de gasolina de 4hp fecha flexible (chicote)
CONCEPTO OPERACION COSTO HORARIO1.- INTERES SOBRE CAPITAL ### x 0.15 /aῆo
0.71I=(Va)i/Ha
2400 horas /aῆ
2.- DEPRECIACION $10,070.000.84
D=Va/Vf 12000 horas
3.- REPARACIONES0.50 X $0.84 0.42
R= Q D
SUMA DE EQUIPO INACTIVO 1.97
FACTOR DE UTILIZACION12/4MESES X
3
SUBTOTAL HORARIO GASTOS F5.90
6.- COMBUSTIBLE0.3litros x4hp/horasx$2.10
2.52E= cPc
7.- LUBRICANTES 0.01litros x 4hp/hora x $ 11.50 0.46
L= aPl
9.- OPERACION$ 3159.23 peon/mes
15.80O= So/H
200 horas/mes
SUBTOTAL HORARIO GASTOS DE OPERACION $18.78
TOTAL $24.67
COSTO POR M³=24.45 X 8HORA
$ 9.78/M³20M³
COSTO HORARIO DE MAQUINARIAS
Unidad :hora
Vad = Valor de adquisición = 13300.00 $ Pnom = Potencia nominal = 8.00000 hpPn = Valor de llantas = 1040.00 $ Tipo de combustible: GasolinaPa = Valor de piezas especiales = 0.00 $ Pc = Precio del combustible = 7.03 $ litroVm = Valor neto = Vad-Pn-Pa = 12260.00 $r = Factor de rescate = 0.20000Vr = Valor de rescate = Vm*r = 2452.00 $i = Tasa de interés = 7.34 % anuals = Prima de seguros = 2.00 % anual Pac = Precio del aceite = 5.78 $ litroKo = Factor de mantenimiento = 0.10000 Vn = Vida económica de llantas = 2400.00 hrsVe = Vida económica = 2500.00 hrsVa = Vida económica de piezas especiales = 0.00 hrs Gh = Cantidad de combustible = 0.80000 lts/hrHea = Tiempo trabajado por año = 650.00 hrs Ah = Cantidad de aceite = 0.01200 lts/hr Clave Fórmula Operaciones TotalCargos FijosDepreciación: D = (Vm-Vr)/Ve = (12260.00-2452.00)/2500.00 = 3.92Inversión: Im = [(Vm+Vr)/2Hea]i = [(12260.00+2452.00)/2*650.00)]0.073400 = 0.83Seguros: Sm = [(Vm+Vr)/2Hea]s = [(12260.00+2452.00)/2*650.00)]0.020000 = 0.23Mantenimiento: Mn = Ko*D = 0.10000*3.92 = 0.39Total de Cargos Fijos 5.37ConsumosCOMBUSTIBLES Co = Gh*Pc = 0.80000*7.03 = 5.62LUBRICANTES Lb = Ah*Pac = 0.01200*5.78 = 0.07LLANTAS N = Pn/Vn = 1040.00/2400.00 = 0.43Total de Consumos 6.12
Revolvedora para concreto marca Cipsa modelo R10 de un saco tipo trompo, cap. 5 m3/hr, motor a gasolina marca Kohler de 8 HP, con reductor, montada sobre ruedas tipo B78X-13, peso de la máquina con motor 363 kg.
Operación Sn = Salario tabulado = $171.43 Fsr = Factor de salario real = 1.71349 Sr = Salario real de operación = Sn*Fsr = $293.74 Ht = Horas efectivas por turno de trabajo = 0.25MOCA-004 Po = Sr/Ht = 293.74/0.25 = 1,174.96Total de Operación 1,174.96Costo Horario 1,186.45
Unidad :hora
Vad = Valor de adquisición = 6850.00 $ Pnom = Potencia nominal = 4.00000 hpPn = Valor de llantas = 0.00 $ Tipo de combustible: GasolinaPa = Valor de piezas especiales = 0.00 $ Pc = Precio del combustible = 7.03 $ litroVm = Valor neto = Vad-Pn-Pa = 6850.00 $r = Factor de rescate = 0.20000Vr = Valor de rescate = Vm*r = 1370.00 $i = Tasa de interés = 7.34 % anuals = Prima de seguros = 2.00 % anual Pac = Precio del aceite = 34.00 $ litroKo = Factor de mantenimiento = 0.20000 Vn = Vida económica de llantas = 0.00 hrsVe = Vida económica = 4800.00 hrsVa = Vida económica de piezas especiales = 0.00 hrs Gh = Cantidad de combustible = 1.45344 lts/hrHea = Tiempo trabajado por año = 1600.00 hrs Ah = Cantidad de aceite = 0.00877 lts/hr Clave Fórmula Operaciones TotalCargos FijosDepreciación: D = (Vm-Vr)/Ve = (6850.00-1370.00)/4800.00 = 1.14
Inversión: Im = [(Vm+Vr)/2Hea]i = [(6850.00+1370.00)/2*1600.00)]0.073400 = 0.19
Seguros: Sm = [(Vm+Vr)/2Hea]s = [(6850.00+1370.00)/2*1600.00)]0.020000 = 0.05Mantenimiento: Mn = Ko*D = 0.20000*1.14 = 0.23Total de Cargos Fijos 1.61ConsumosCOMBUSTIBLES Co = Gh*Pc = 1.45344*7.03 = 10.22LUBRICANTES Lb = Ah*Pac = 0.00877*34.00 = 0.30
Vibrador de gasolina marca Felsa modelo vibromax cap. 12000 VPM, con manguera de 4.00 mts, y cabezal de por 38 mm ( 1 1/2"), con motor de gasolina de 4 H. P.
Total de Consumos 10.52Operación Sn = Salario tabulado = $250.00 Fsr = Factor de salario real = 1.68803 Sr = Salario real de operación = Sn*Fsr = $422.01 Ht = Horas efectivas por turno de trabajo = 8.00MOCA-011 Po = Sr/Ht = 422.01/8.00 = 52.75Total de Operación 52.75Costo Horario 64.88