CRONOGRAMA DE EJECUCIÓN VALORIZADO Proyecto:"MEJORAMIENTO DEL JIRON TUPAC AMARU DESDE LA 5TA., 6TA., 7MA., 8VA., 9NA., CUADRA Y SU PROLONGACION Y EL PASAJE MIRADOR DEL DISTRITO DE ANDAHUAYLAS, PROVINCIA DE ANDAHUAYLAS- APURIMAC". MES 0 MES 1 MES 2 MES 3 MES 4 CONSTRUCCIÓN DE LA INFRAETRUCTURA S/. 2,882,094.48 S/. 54,412.11 S/. 903,371.56 S/. 1,173,378.65 S/. 750,932.16 Avance Físico Programado 100.00% 1.89% 31.34% 40.71% 26.06% 1 PAVIMENTO RIGIDO 1,618,247.53 S/.41,933.89 S/.305,101.04 S/.713,847.91 S/.557,364.69 1.01 OBRAS PROVISIONALES 11,495.60 S/.11,495.60 01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 1,772.47 S/.1,772.47 01.01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS PARA LA 7,500.00 S/.7,500.00 01.01.03 CAMPAMENTO PROVISIONAL DE LA OBRA 2,223.13 S/.2,223.13 1.02 TRABAJOS PRELIMINARES 41,780.56 S/.30,438.29 S/.11,342.27 01.02.01 LIMPIEZA DE TERRENO MANUAL 27,673.84 S/.19,154.38 S/.8,519.46 01.02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION 14,106.72 S/.11,283.91 S/.2,822.81 1.03 MOVIMIENTO DE TIERRAS 293,775.37 S/.293,758.77 S/.16.60 01.03.01 CORTE MASIVO CON MAQUINARIA 134,380.64 S/.134,380.64 01.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 159,394.73 S/.159,378.13 S/.16.60 1.04 MEJORAMIENTO DE TERRENO 313,372.38 S/.313,372.38 01.04.01 EXTRACCION DE MATERIAL DE BASE Y SUB-BASE 58,739.89 S/.58,739.89 01.04.02 PERFILADO Y COMPACTADO DE SUB-RASANTE 151,598.36 S/.151,598.36 01.04.03 CARGUIO TRASPORTE DE MATERIAL DE BASE Y SUB - BASE 62,254.04 S/.62,254.04 01.04.04 TENDIDO Y COMPACTADO DE SUB BASE Y BASE 40,780.09 S/.40,780.09 1.05 CONCRETO EN LOZA MACIZA E=0.2 957,823.62 S/.400,458.93 S/.557,364.69 01.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO 20,454.77 S/.9,916.17 S/.10,538.60 01.05.02 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO 130,104.22 S/.56,253.96 S/.73,850.26 01.05.03 CONCRETO f'c=210 kg/cm2 E=0.2M /MESCLADORA 614,201.82 S/.265,566.20 S/.348,635.62 01.05.04 CURADO DE CONCRETO 31,653.12 S/.11,040.25 S/.20,612.87 01.05.05 JUNTA ASFALTICA DE E=1" 92,709.58 S/.92,709.58 01.05.06 PINTADO DE SEÑALIZACION DE VIA 11,017.76 S/.11,017.76 01.05.07 CANAL DE CONCRETO CON TAPA RANURADA DE CONCRETO, S 57,682.35 S/.57,682.35 2 REPOSICION DEL SISTEMA DE AGUA Y DESAGUE 11,369.19 S/.541.01 S/.10,828.18 2.01 RECONEXION DOMICILIARIA DEL AGUA POTABLE 8,732.90 S/.305.70 S/.8,427.20 02.01.01 EXCAVACION DE ZANJA EN TERRENO COMPACTO HASTA H=1. 118.26 S/.118.26 02.01.02 REFINE DE ZANJA PARA AGUA POTABLE 163.80 S/.163.80 02.01.03 PREPARACION DE CAMA DE APOYO E=0.10M PARA TUBERIA 39.42 S/.23.64 S/.15.78 02.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO 111.02 S/.111.02 02.01.05 PROVISION E INSTALACION TUBERIA PVC - SAP C-10 D-1 8,300.40 S/.8,300.40 2.02 RECONEXION DOMICILIARIA DESAGUE 2,636.29 S/.235.31 S/.2,400.98 02.02.01 EXCAVACION DE ZANJA EN TERRENO COMPACTO HASTA H=1. 78.84 S/.78.84 02.02.02 REFINE DE ZANJA PARA DESAGUE 109.20 S/.109.20 02.02.03 PREPARACION DE CAMA DE APOYO E=0.10M PARA TUBERIA 78.84 S/.47.27 S/.31.57 02.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO 37.01 S/.37.01 02.02.05 PROVICION EINSTALACION DE CONEXION DOMICILIARIA DE 2,332.40 S/.2,332.40 3 VEREDAS 210,202.56 S/.10,541.40 S/.30,779.49 S/.147,811.53 S/.21,070.14 3.01 TRABAJOS PRELIMINARES 10,179.32 S/.8,272.38 S/.1,906.94 03.01.01 TRAZO Y REPLANTEO DE OBRA 1,945.56 S/.1,945.56 03.01.02 DEMOLICION DE VEREDAS DE 0.10 m 1,624.86 S/.1,624.86 03.01.03 ACARREO DE DESMONTE HASTA ZONA DE ACOPIO 4,701.96 S/.4,701.96 03.01.04 ELIMINACION DE DESMONTE PROVENIENTE DE LA DEMOLICI 1,906.94 S/.1,906.94 3.02 MOVIMIENTO DE TIERRAS 32,248.58 S/.2,269.02 S/.28,872.55 S/.1,107.01 03.02.01 EXCAVACION EN TERRENO COMPACTO A NIVEL DE SUB RASA 5,187.88 S/.2,269.02 S/.2,918.86 03.02.02 ELIMINACION DE MATERIAL EXCEDENTE D=3KM 2,757.09 S/.2,757.09 03.02.03 PERFILADO Y COMPACTADO MANUAL DE SUB RASANTE 24,303.61 S/.23,196.60 S/.1,107.01

Cronograma de Ejecución Valorizado

Embed Size (px)

DESCRIPTION

Hoja de cálculo para desarrollar cronogramas de ejecución con la respectiva valorización de acuerdo al cronograma Pert CPM.

Citation preview

Page 1: Cronograma de Ejecución Valorizado

CRONOGRAMA DE EJECUCIÓN VALORIZADOProyecto:"MEJORAMIENTO DEL JIRON TUPAC AMARU DESDE LA 5TA., 6TA., 7MA., 8VA., 9NA., CUADRA Y SU PROLONGACION Y EL PASAJE MIRADOR DEL DISTRITO DE ANDAHUAYLAS, PROVINCIA DE ANDAHUAYLAS- APURIMAC".

MES 0 MES 1 MES 2 MES 3 MES 4CONSTRUCCIÓN DE LA INFRAETRUCTURA S/. 2,882,094.48 S/. 54,412.11 S/. 903,371.56 S/. 1,173,378.65 S/. 750,932.16 Avance Físico Programado 100.00% 1.89% 31.34% 40.71% 26.06%

1 PAVIMENTO RIGIDO 1,618,247.53 S/.41,933.89 S/.305,101.04 S/.713,847.91 S/.557,364.691.01 OBRAS PROVISIONALES 11,495.60 S/.11,495.60

01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m 1,772.47 S/.1,772.4701.01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS PARA LA OBRA 7,500.00 S/.7,500.0001.01.03 CAMPAMENTO PROVISIONAL DE LA OBRA 2,223.13 S/.2,223.13

1.02 TRABAJOS PRELIMINARES 41,780.56 S/.30,438.29 S/.11,342.2701.02.01 LIMPIEZA DE TERRENO MANUAL 27,673.84 S/.19,154.38 S/.8,519.4601.02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION 14,106.72 S/.11,283.91 S/.2,822.81

1.03 MOVIMIENTO DE TIERRAS 293,775.37 S/.293,758.77 S/.16.6001.03.01 CORTE MASIVO CON MAQUINARIA 134,380.64 S/.134,380.6401.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 159,394.73 S/.159,378.13 S/.16.60

1.04 MEJORAMIENTO DE TERRENO 313,372.38 S/.313,372.3801.04.01 EXTRACCION DE MATERIAL DE BASE Y SUB-BASE 58,739.89 S/.58,739.8901.04.02 PERFILADO Y COMPACTADO DE SUB-RASANTE 151,598.36 S/.151,598.3601.04.03 CARGUIO TRASPORTE DE MATERIAL DE BASE Y SUB - BASE 62,254.04 S/.62,254.0401.04.04 TENDIDO Y COMPACTADO DE SUB BASE Y BASE 40,780.09 S/.40,780.09

1.05 CONCRETO EN LOZA MACIZA E=0.2 957,823.62 S/.400,458.93 S/.557,364.6901.05.01 TRAZO Y REPLANTEO DURANTE EL PROCESO 20,454.77 S/.9,916.17 S/.10,538.6001.05.02 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO 130,104.22 S/.56,253.96 S/.73,850.2601.05.03 CONCRETO f'c=210 kg/cm2 E=0.2M /MESCLADORA 614,201.82 S/.265,566.20 S/.348,635.6201.05.04 CURADO DE CONCRETO 31,653.12 S/.11,040.25 S/.20,612.8701.05.05 JUNTA ASFALTICA DE E=1" 92,709.58 S/.92,709.5801.05.06 PINTADO DE SEÑALIZACION DE VIA 11,017.76 S/.11,017.7601.05.07 CANAL DE CONCRETO CON TAPA RANURADA DE CONCRETO, SEGÚN DISEÑO 57,682.35 S/.57,682.35

2 REPOSICION DEL SISTEMA DE AGUA Y DESAGUE 11,369.19 S/.541.01 S/.10,828.182.01 RECONEXION DOMICILIARIA DEL AGUA POTABLE 8,732.90 S/.305.70 S/.8,427.20

02.01.01 EXCAVACION DE ZANJA EN TERRENO COMPACTO HASTA H=1.00M 118.26 S/.118.2602.01.02 REFINE DE ZANJA PARA AGUA POTABLE 163.80 S/.163.8002.01.03 PREPARACION DE CAMA DE APOYO E=0.10M PARA TUBERIA 39.42 S/.23.64 S/.15.7802.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO 111.02 S/.111.0202.01.05 PROVISION E INSTALACION TUBERIA PVC - SAP C-10 D-1/2" 8,300.40 S/.8,300.40

2.02 RECONEXION DOMICILIARIA DESAGUE 2,636.29 S/.235.31 S/.2,400.9802.02.01 EXCAVACION DE ZANJA EN TERRENO COMPACTO HASTA H=1.00M 78.84 S/.78.8402.02.02 REFINE DE ZANJA PARA DESAGUE 109.20 S/.109.2002.02.03 PREPARACION DE CAMA DE APOYO E=0.10M PARA TUBERIA 78.84 S/.47.27 S/.31.5702.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO 37.01 S/.37.0102.02.05 PROVICION EINSTALACION DE CONEXION DOMICILIARIA DESAGUE 2,332.40 S/.2,332.40

3 VEREDAS 210,202.56 S/.10,541.40 S/.30,779.49 S/.147,811.53 S/.21,070.143.01 TRABAJOS PRELIMINARES 10,179.32 S/.8,272.38 S/.1,906.94

03.01.01 TRAZO Y REPLANTEO DE OBRA 1,945.56 S/.1,945.5603.01.02 DEMOLICION DE VEREDAS DE 0.10 m 1,624.86 S/.1,624.8603.01.03 ACARREO DE DESMONTE HASTA ZONA DE ACOPIO 4,701.96 S/.4,701.9603.01.04 ELIMINACION DE DESMONTE PROVENIENTE DE LA DEMOLICION DE VEREDA 1,906.94 S/.1,906.94

3.02 MOVIMIENTO DE TIERRAS 32,248.58 S/.2,269.02 S/.28,872.55 S/.1,107.0103.02.01 EXCAVACION EN TERRENO COMPACTO A NIVEL DE SUB RASANTE 5,187.88 S/.2,269.02 S/.2,918.8603.02.02 ELIMINACION DE MATERIAL EXCEDENTE D=3KM 2,757.09 S/.2,757.0903.02.03 PERFILADO Y COMPACTADO MANUAL DE SUB RASANTE 24,303.61 S/.23,196.60 S/.1,107.01

Page 2: Cronograma de Ejecución Valorizado

CRONOGRAMA DE EJECUCIÓN VALORIZADOProyecto:"MEJORAMIENTO DEL JIRON TUPAC AMARU DESDE LA 5TA., 6TA., 7MA., 8VA., 9NA., CUADRA Y SU PROLONGACION Y EL PASAJE MIRADOR DEL DISTRITO DE ANDAHUAYLAS, PROVINCIA DE ANDAHUAYLAS- APURIMAC".

MES 0 MES 1 MES 2 MES 3 MES 4CONSTRUCCIÓN DE LA INFRAETRUCTURA S/. 2,882,094.48 S/. 54,412.11 S/. 903,371.56 S/. 1,173,378.65 S/. 750,932.16 Avance Físico Programado 100.00% 1.89% 31.34% 40.71% 26.06%

3.03 OBRAS DE CONCRETO EN VEREDAS 167,774.66 S/.146,704.52 S/.21,070.1403.03.01 CONCRETO f'c=175 kg/cm2 PARA SARDINEL DE VEREDA 11,349.14 S/.9,456.83 S/.1,892.3103.03.02 ENCOFRADO Y DESENCOFRADO EN SARDINELES 24,199.14 S/.21,777.55 S/.2,421.5903.03.03 EMPEDRADO PARA VEREDA TAMAÑO MAX. 6" 69,987.16 S/.67,649.39 S/.2,337.7703.03.04 ENCOFRADO Y DESENCOFRADO EN VEREDAS 4,638.19 S/.4,174.05 S/.464.1403.03.05 CONCRETO f'c=175 kg/cm2 EN VEREDA 38,566.08 S/.32,135.72 S/.6,430.3603.03.06 JUNTA ASFALTICA DE E=1" 5,220.62 S/.5,220.6203.03.07 BRUÑAS EN VEREDA 13,814.33 S/.11,510.98 S/.2,303.35

4 CUNETAS PARA LA EVACUACION DE AGUAS PLUVIALES 205,372.11 S/.508.46 S/.41,009.31 S/.163,854.344.01 OBRAS DE CONCRETO EN CUNETA 205,372.11 S/.508.46 S/.41,009.31 S/.163,854.34

04.01.01 TRAZO Y REPLANTEO DE OBRA 1,713.43 S/.1,713.4304.01.02 ENCOFRADO Y DESENCOFRADO EN CUNETA 97,041.98 S/.25,306.51 S/.71,735.4704.01.03 CONCRETO f'c=175 kg/cm2 96,885.25 S/.9,678.43 S/.87,206.8204.01.04 JUNTA ASFALTICA DE E=1" 4,204.31 S/.4,204.3104.01.05 ENSAYO DE DENSIDAD DE CAMPO 1,931.92 S/.1,931.9204.01.06 ENSAYO DE DENSIDAD DE AFIRMADO 1,931.92 S/.1,931.9204.01.07 DISEÑO DE MEZCLA 508.46 S/.508.4604.01.08 PRUEBA DEL CONCRETO (COMPRESION) 804.84 S/.447.10 S/.357.7404.01.09 PLACA RECORDATORIA 350.00 S/.350.00

5 OBRAS DE ARTE 826,903.09 S/.563,786.75 S/.256,820.50 S/.6,295.845.01 ALCANTARILLA DE CONCRETO CON TAPA METALICA S/DISEÑO 14,177.20 S/.11,340.28 S/.2,836.925.02 TUBERÍA DE AGUAS PLUVIALES D=10" UF S-25, INC. EXCAV.,CAMA Y RELLEN 17,285.60 S/.13,826.68 S/.3,458.925.03 MUROS DE CONTENCIÓN 795,440.29 S/.563,786.75 S/.231,653.54

05.03.01 DEMOLICION DE MUROS DE CONTENCIÓN DE CONCRETO CICLÓPEO 11,079.10 S/.11,079.1005.03.02 ACARREO DE DESMONTE HASTA ZONA DE ACOPIO 8,794.64 S/.8,794.6405.03.03 ELIMINACION DE DESMONTE PROVENIENTE DE LA DEMOLICION DE MUROS 3,566.78 S/.3,566.7805.03.04 MURO DE CONCRETO ARMADO. INC. BARANDAS METÁLICAS SEGÚN DISEÑO 771,999.77 S/.540,346.23 S/.231,653.54

6 FLETE TERRESTRE LOCAL 10,000.00 S/.1,428.36 S/.3,163.27 S/.3,061.22 S/.2,347.156.01 FLETE TERRESTRE LOCAL 10,000.00 S/.1,428.36 S/.3,163.27 S/.3,061.22 S/.2,347.15

(1) COSTO DIRECTO S/. 2,882,094.48 S/. 54,412.11 S/. 903,371.56 S/. 1,173,378.65 S/. 750,932.16 (2) GASTOS GENERALES 7% ((1)*0.07) S/. 201,746.61 S/. 3,808.85 S/. 63,236.01 S/. 82,136.51 S/. 52,565.25

(3) UTILIDAD 5% ((1)*0.05) S/. 144,104.72 S/. 2,720.61 S/. 45,168.58 S/. 58,668.93 S/. 37,546.61 (4) SUB TOTAL ((1)+(2)+(3)) S/. 3,227,945.82 S/. 60,941.56 S/. 1,011,776.15 S/. 1,314,184.09 S/. 841,044.02

(5) I.G.V. 18% ((4)*0.18) S/. 581,030.25 S/. 10,969.48 S/. 182,119.71 S/. 236,553.14 S/. 151,387.92 (6) VALOR REFERENCIAL ((4)+(5)) S/. 3,808,976.06 S/. 71,911.04 S/. 1,193,895.85 S/. 1,550,737.22 S/. 992,431.94 (7) SUPERVISIÓN 2.5% ((6)*0.025) S/. 95,224.40 S/. 1,797.78 S/. 29,847.40 S/. 38,768.43 S/. 24,810.80

(8) EXPEDIENTE TÉCNICO S/. 41,302.36 S/. 41,302.36 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 (9) TOTAL PRESUPUESTADO (6)+(7)+(8) S/. 3,945,502.82 S/. 41,302.36 S/. 73,708.81 S/. 1,223,743.25 S/. 1,589,505.65 S/. 1,017,242.74

Avance Financiero Programado 100.00% 1.89% 31.34% 40.71% 26.06%