Upload
albert-palacios
View
217
Download
0
Embed Size (px)
Citation preview
7/21/2019 Cronograma Fisico Financiero Agua Potable
1/18
MEJORAMIENTO Y AMPLIACION DEL SAP Y ALCANTARILLADO TEMBLADERA
01.00.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL
01.01.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL S/. 1,279.38
02.00.00 CAJA DE CAPTACIN DE FONDO
02.01.00 TRABAJOS PRELIMINARES
02.01.01 DEMOLICION DE CONCRETO ARMADO EN TECHO DE CAPTACION S/. 3,840.41
02.01.02 LIMPIEZA DE TERRENO, CAPTACIN S/. 109.20
02.01.03 TRAZO Y REPLANTEO S/. 6.85
02.02.00 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACIN MANUAL CAJA DE VALVULAS S/. 28.81
02.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 21.36
02.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 1.6202.03.00 OBRAS DE CONCRETO SIMPLE
02.03.01 CONCRETO FC=140 KG/CM2 (CAJA VLVULAS) S/. 9,893.62
02.03.02 PIEDRA 4" ASENTADA CON MORTERO 1:8 EN CAPTACION S/. 572.48
02.03.03 ENCOFRADO Y DESENCOFRADO S/. 43.43
02.04.00 OBRAS DE CONCRETO ARMADO
02.04.01 CONCRETO FC=175 KG/CM2 S/. 4,968.85
02.04.02 ACERO FY = 4200 KG/CM2. S/. 331.64
02.04.03 ENCOFRADO Y DESENCOFRADO S/. 1,787.14
02.05.00 REVOQUES Y ENLUCIDOS
02.05.01 TARRAJEO EXTERIOR S/. 1,015.11
02.05.02 TARRAJEO INTERIOR S/. 1,695.04
02.06.00 VALVULAS Y ACCESORIOS
02.06.01 VALVULAS Y ACCESORIOS 8" S/. 768.53
02.07.00 VARIOS
02.07.01 PINTADO DE ESTRUCTURAS S/. 534.32
02.07.02 TAPA SANITARIA 0.60X0.60 S/. 271.72
03.00.00 LINEA DE CONDUCCIN A R1
03.01.00 TRABAJOS PRELIMINARES
03.01.01 TRAZO Y REPLANTEO S/. 2,132.47
03.02.00 EXCAVACIN DE ZANJAS
03.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10
03.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 88,011.78
03.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 5,764.59
03.02.04 CAMA DE APOYO PARA TUBERA S/. 472.99 S/. 236.50
03.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 65,036.40
03.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 155,742.47 S/. 155,742.47
03.04.00 PRUEBA HIDRAULICA
03.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,153.28
04.00.00 LINEA DE CONDUCCIN A R2
04.01.00 TRABAJOS PRELIMINARES
04.01.01 TRAZO Y REPLANTEO S/. 2,270.89
04.02.00 EXCAVACIN DE ZANJAS
04.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10
04.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 95,293.49
04.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 6,142.50
04.02.04 CAMA DE APOYO PARA TUBERA S/. 504.00 S/. 252.00
04.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 69,300.00
04.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 165,952.50 S/. 165,952.50
04.04.00 PRUEBA HIDRAULICA
04.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,360.00
05.00.00 RESERVORIO CIRCULAR APOYADO: 100 M3
05.01.00 TRABAJOS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL S/. 58.83
05.01.02 TRAZO Y REPLANTEO S/. 115.96
05.02.00 MOVIMIENTO DE TIERRAS
05.02.01 EXCAVACION MANUAL S/. 499.90
05.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 464.77
05.02.03 NIVELACION Y COMPACTACION MANUAL S/. 91.74
05.02.04 AFIRMADO S/. 244.65
M1 M2 M3 M4 M5 M6 M7 M8
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 1
7/21/2019 Cronograma Fisico Financiero Agua Potable
2/18
05.03.00 OBRAS DE CONCRETO SIMPLE
05.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 131.78
05.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 364.54
05.03.03 OBRAS DE CONCRETO ARMADO
05.03.04 CONCRETO FC = 210 KG/CM2 S/. 42,636.38
05.03.05 ENCOFRADO Y DESENCOFRADO S/. 568.45 S/. 3,410.68
05.03.06 ACERO FY = 4200 KG/CM2. S/. 1,388.62 S/. 8,331.71
05.04.00 REVOQUES Y ENLUCIDOS
05.04.01 TARRAJEO EXTERIOR S/. 3,332.14
05.04.02 TARRAJEO INTERIOR S/. 2,850.49
05.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,385.27
05.05.00 VALVULAS Y ACCESORIOS05.06.01 ACCESORIOS PARA VENTILACIN S/. 625.92
05.07.00 VARIOS
05.07.01 PINTURA EN EXTERIORES S/. 1,047.95
05.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03
05.07.03 TAPA SANITARIA METLICA S/. 165.86
06.00.00 RESERVORIO CIRCULAR APOYADO: 75 M3
06.01.00 TRABAJOS PRELIMINARES
06.01.01 LIMPIEZA DE TERRENO MANUAL S/. 52.80
06.01.02 TRAZO Y REPLANTEO S/. 101.39
06.02.00 MOVIMIENTO DE TIERRAS
06.02.01 EXCAVACION MANUAL S/. 437.09
06.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 406.39
06.02.03 NIVELACION Y COMPACTACION MANUAL S/. 80.22
06.02.04 AFIRMADO S/. 427.96
06.03.00 OBRAS DE CONCRETO SIMPLE
06.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 115.36
06.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 12,794.25
06.03.03 OBRAS DE CONCRETO ARMADO
06.03.04 CONCRETO FC = 210 KG/CM2 S/. 17,578.49
06.03.05 ENCOFRADO Y DESENCOFRADO S/. 525.61 S/. 3,153.66
06.03.06 ACERO FY = 4200 KG/CM2. S/. 1,231.30 S/. 7,387.79
06.04.00 REVOQUES Y ENLUCIDOS
06.04.01 TARRAJEO EXTERIOR S/. 3,183.93
06.04.02 TARRAJEO INTERIOR S/. 2,575.35
06.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,180.27
06.05.00 VALVULAS Y ACCESORIOS
06.06.00 ACCESORIOS PARA VENTILACIN S/. 625.92
06.07.00 VARIOS
06.07.01 PINTURA EN EXTERIORES S/. 652.63
06.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03
06.07.03 TAPA SANITARIA METLICA S/. 165.86
07.00.00 CASETA DE VALVULAS
07.01.00 TRABAJOS PRELIMINARES
07.01.01 LIMPIEZA DE TERRENO MANUAL S/. 23.39
07.01.02 TRAZO Y REPLANTEO S/. 37.65
07.02.00 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION MANUAL S/. 188.69
07.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 175.45
07.02.03 NIVELACION Y COMPACTACION MANUAL S/. 29.7907.02.04 LECHO DE GRAVA S/. 132.91
07.03.00 OBRAS DE CONCRETO SIMPLE
07.03.01 CONCRETO FC=175 KG/CM2 S/. 1,293.78
07.03.02 ENCOFRADO Y DESENCOFRADO S/. 738.82
07.04.00 OBRAS DE CONCRETO ARMADO
07.04.01 CONCRETO FC=175 KG/CM2 S/. 406.70
07.04.02 ACERO FY = 4200 KG/CM2. S/. 381.62
07.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA S/. 328.02
07.05.00 REVOQUES Y ENLUCIDOS
07.05.01 TARRAJEO EXTERIOR S/. 743.74
07.05.02 TARRAJEO INTERIOR S/. 506.09
07.06.03 VALVULAS Y ACCESORIOS DE 8" (INGRESO CASETA)
M1 M2 M3 M4 M5 M6 M7 M8
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 2
7/21/2019 Cronograma Fisico Financiero Agua Potable
3/18
07.06.03.1 VALVULAS Y ACCESORIOS 8" (INGRESO CAS. VALVULAS) S/. 768.53
07.07.00 VARIOS
07.07.01 TAPA SANITARIA METLICA S/. 331.72
07.07.02 PINTURA EN EXTERIORES S/. 364.74 S/. 91.18
08.00.00 RED DE DISTRIBUCIN R1 Y R2
08.01.00 TRABAJOS PRELIMINARES
08.01.01 TRAZO Y REPLANTEO S/. 651.95 S/. 630.92 S/. 651.95 S/. 630.92 S/. 651.95 S/. 651.95 S/. 609.89
08.02.00 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,988.74 S/. 21,505.60
08.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 805.48 S/. 779.50 S/. 805.48 S/. 779.50 S/. 805.48 S/. 805.48 S/. 753.51
08.02.03 REFINE Y CONFORMACIN DE FONDOS S/. 1,656.56 S/. 1,656.56 S/. 1,711.78 S/. 1,656.56 S/. 1,711.78 S/. 1,711.78 S/. 1,601.34
08.02.04 CAMA DE APOYO PARA TUBERA S/. 1,057.18 S/. 1,132.69 S/. 1,170.44 S/. 1,132.69 S/. 1,170.44 S/. 1,170.44 S/. 1,094.9308.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 1,868.94 S/. 18,689.36 S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 19,312.34 S/. 18,066.38
08.02.06 OBRAS DE CONCRETO SIMPLE
08.02.06.1 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 9,318.58 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,559.83 S/. 11,749.52
08.03.00 TUBERA Y ACCESORIOS
08.03.01 SUMINISTRO E INSTALACION TUBERA U.F. 160 MM. C-7.5 S/. 6,180.54 S/. 10,300.89 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 10,644.26 S/. 9,957.53
08.03.02 SUMINISTRO TUBERA U.F. 110 MM. C-7.5 S/. 4,187.31 S/. 6,978.84 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 7,211.47 S/. 6,746.21
08.03.03 SUMINISTRO TUBERA U.F. 90 MM. C-7.5 S/. 86.49 S/. 144.16 S/. 148.96 S/. 144.16 S/. 148.96 S/. 148.96 S/. 139.35
08.03.04 SUMINISTRO TUBERA U.F. 63 MM. C-7.5 S/. 665.18 S/. 1,108.63 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 1,145.58 S/. 1,071.67
08.03.05 TUBERA PVC SAP 1/2" C-7.5 S/. 8,235.13 S/. 13,725.21 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 14,182.72 S/. 13,267.70
08.05.00 ACCESORIOS DE RED DE DISTRIBUCION
08.05.01 TEE PVC 6"X6" S/. 1.53 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.47
08.05.02 TEE PVC 6"X4" S/. 1.53 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.47
08.05.03 TEE PVC 4"X4" S/. 0.59 S/. 0.98 S/. 1.02 S/. 0.98 S/. 1.02 S/. 1.02 S/. 0.95
08.05.04 TEE PVC 2"X2" S/. 0.12 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.19
08.05.05 TEE PVC 6"X2" S/. 1.06 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.71
08.05.06 REDUC. PVC 6"-2" S/. 1.06 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.71
08.05.07 CODO. PVC 4"X 90 S/. 0.12 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.19
08.05.08 CODO. PVC 6"X 90 S/. 0.35 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.57
08.05.09 CRUZ PVC 6"X6" S/. 1.30 S/. 2.16 S/. 2.23 S/. 2.16 S/. 2.23 S/. 2.23 S/. 2.09
08.05.10 CRUZ PVC 6"X4" S/. 2.24 S/. 3.73 S/. 3.86 S/. 3.73 S/. 3.86 S/. 3.86 S/. 3.61
08.05.11 CRUZ PVC 6"X2" S/. 0.35 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.57
08.05.12 CRUZ PVC 4"X4" S/. 0.47 S/. 0.79 S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.81 S/. 0.76
08.05.13 CRUZ PVC 4"X2" S/. 0.12 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.19
08.06.00 PRUEBA HIDRAULICA
08.06.01 PRUEBA HIDRAULICA+DESINFECCION S/. 549.02 S/. 915.03 S/. 945.54 S/. 915.03 S/. 945.54 S/. 945.54 S/. 884.53
09.00.00 CAJA DE VALVULAS DE CONTROL
09.01.00 TRABAJOS PRELIMINARES
09.01.01 LIMPIEZA DE TERRENO MANUAL S/. 7.05 S/. 6.82 S/. 7.05 S/. 6.82 S/. 7.05 S/. 7.05 S/. 6.59
09.01.02 TRAZO Y REPLANTEO S/. 3,555.05 S/. 3,555.05 S/. 3,673.55 S/. 3,555.05 S/. 3,673.55 S/. 3,673.55 S/. 3,436.55
09.02.00 MOVIMIENTO DE TIERRAS
09.02.01 EXCAVACION MANUAL S/. 320.50 S/. 384.60 S/. 397.42 S/. 384.60 S/. 397.42 S/. 397.42 S/. 371.78
09.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 577.85 S/. 559.21 S/. 577.85 S/. 559.21 S/. 577.85 S/. 577.85 S/. 540.57
09.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 14.44 S/. 13.97 S/. 14.44 S/. 13.97 S/. 14.44 S/. 14.44 S/. 13.51
09.03.00 CONCRETO SIMPLE
09.03.01 CONCRETO FC=140 KG/CM2 S/. 218.47 S/. 211.43 S/. 218.47 S/. 211.43 S/. 218.47 S/. 218.47 S/. 204.38
09.03.02 ENCOFRADO Y DESENCOFRADO S/. 269.74 S/. 261.04 S/. 269.74 S/. 261.04 S/. 269.74 S/. 269.74 S/. 252.33
09.04.00 TARRAJEO
09.04.01 TARRAJEO EXTERIOR S/. 91.39 S/. 88.44 S/. 91.39 S/. 88.44 S/. 91.39 S/. 91.39 S/. 85.49
09.05.00 VALVULAS Y ACCESORIOS09.05.01 VALVULAS Y ACCESORIOS 4" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.52
09.05.02 VALVULAS Y ACCESORIOS 6" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.52
09.05.03 VALVULAS Y ACCESORIOS 2" S/. 2.03 S/. 1.96 S/. 2.03 S/. 1.96 S/. 2.03 S/. 2.03 S/. 1.90
09.06.00 VARIOS
09.06.01 TAPA SANITARIA METLICA
10.00.00 CAJA DE VALVULAS DE PURGA
10.01.00 TRABAJOS PRELIMIINARES
10.01.01 LIMPIEZA DE TERRENO MANUAL
10.01.02 TRAZO Y REPLANTEO
10.02.00 MOVIMIENTO DE TIERRAS
10.02.01 EXCAVACION MANUAL
10.02.02 ELIMINACION DE MATERIAL EXCEDENTE
M1 M2 M3 M4 M5 M6 M7 M8
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 3
7/21/2019 Cronograma Fisico Financiero Agua Potable
4/18
10.03.00 OBRAS DE CONCRETO SIMPLE
10.03.01 CONCRETO FC=140 KG/CM2
10.03.02 ENCOFRADO Y DESENCOFRADO
10.04.00 TARRAJEO
10.04.01 TARRAJEO EXTERIOR
10.05.00 VALVULAS Y ACCESORIOS PURGA
10.06.00 VARIOS
10.06.01 TAPA SANITARIA METLICA
11.00.00 CONEXIONES DOMICILIARIAS
11.01.00 TRABAJOS PRELIMIINARES
11.01.01 LIMPIEZA DE TERRENO MANUAL S/. 406.11 S/. 393.01 S/. 406.11 S/. 393.01 S/. 406.11 S/. 406.11 S/. 379.91
11.01.02 TRAZO Y REPLANTEO S/. 700.73 S/. 724.89 S/. 749.05 S/. 724.89 S/. 749.05 S/. 749.05 S/. 700.7311.02.00 MOVIMIENTO DE TIERRAS
11.02.01 EXCAVACION MANUAL S/. 1,875.28 S/. 2,344.10 S/. 2,422.23 S/. 2,344.10 S/. 2,422.23 S/. 2,422.23 S/. 2,265.96
11.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 194.51 S/. 243.14 S/. 251.25 S/. 243.14 S/. 251.25 S/. 251.25 S/. 235.04
11.02.03 RELLENO Y COMPACTACIN DE ZANJAS S/. 160,116.00
11.03.00 OBRAS DE CONCRETO SIMPLE
11.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 1,186.06 S/. 3,953.52 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 4,085.31 S/. 3,821.74
11.03.02 CONCRETO FC=140 KG/CM2 S/. 120.97 S/. 403.23 S/. 416.67 S/. 403.23 S/. 416.67 S/. 416.67 S/. 389.79
11.03.03 ENCOFRADO Y DESENCOFRADO S/. 186.02 S/. 620.07 S/. 640.74 S/. 620.07 S/. 640.74 S/. 640.74 S/. 599.40
11.04.00 OBRAS DE CONCRETO ARMADO
11.04.01 CONCRETO FC=175 KG/CM2 S/. 38.62 S/. 128.73 S/. 133.02 S/. 128.73 S/. 133.02 S/. 133.02 S/. 124.44
11.04.02 ACERO FY = 4200 KG/CM2. S/. 25.62 S/. 85.41 S/. 88.26 S/. 85.41 S/. 88.26 S/. 88.26 S/. 82.56
11.04.03 ENCOFRADO Y DESENCOFRADO S/. 28.34 S/. 94.46 S/. 97.61 S/. 94.46 S/. 97.61 S/. 97.61 S/. 91.31
11.05.00 CONEXIONES DOMICILIARIAS
11.05.01 CONEXIN DOMICILIARIA DE AGUA 6" S/. 39.28 S/. 84.17 S/. 86.97 S/. 84.17 S/. 86.97 S/. 86.97 S/. 81.36
11.05.02 CONEXIN DOMICILIARIA DE AGUA 4" S/. 44.89 S/. 96.19 S/. 99.40 S/. 96.19 S/. 99.40 S/. 99.40 S/. 92.99
11.05.03 CONEXIN DOMICILIARIA DE AGUA 3" S/. 3.09 S/. 6.61 S/. 6.83 S/. 6.61 S/. 6.83 S/. 6.83 S/. 6.39
11.05.04 CONEXIN DOMICILIARIA DE AGUA 2" S/. 26.19 S/. 56.11 S/. 57.98 S/. 56.11 S/. 57.98 S/. 57.98 S/. 54.24
11.05.05 SUMINISTRO E INSTALACION DE MEDIDORES S/. 4,593.97 S/. 9,844.22 S/. 10,172.36 S/. 9,844.22 S/. 10,172.36 S/. 10,172.36 S/. 9,516.08
12.00.00 CASETA DE CLORACIN
12.01.00 MUROS DE LADRILLOS DE SOGA S/. 177.99 S/. 489.47
12.02.00 COBERTURA DE CALAMINA S/. 16.35
12.03.00 CARPINTERIA METALICA S/. 1,305.21
12.04.00 TARRAJEO EM MUROS S/. 215.03
12.05.00 CERRAJERIA S/. 13.20 S/. 5.66
12.06.00 PINTURA EN MUROS S/. 169.07 S/. 72.46
12.07.00 VIDRIOS S/. 163.62
13.00.00 EDUCACIN SANITARIA Y CAPACITACION EN AOM.
13.01.00 EDUCACIN SANITARIA S/. 4,960.00 S/. 4,800.00 S/. 4,960.00 S/. 4,800.00 S/. 4,960.00 S/. 4,320.00
13.03.00 CAPACITACIN EN A+O+M S/. 26,401.15 S/. 25,549.50 S/. 26,401.15 S/. 25,549.50 S/. 26,401.15 S/. 22,994.55
14.00.00 FLETE
14.01.00 FLETE TERRESTRE S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 223.08
14.02.00 FLETE RURAL S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 223.08
15.00.00 CONTROL DE CALIDAD
15.01.00 DISE O DE MEZCLAS DE CONCRETO S/. 31.30 S/. 30.29 S/. 31.30 S/. 30.29 S/. 31.30 S/. 31.30 S/. 29.28
15.02.00 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.78 S/. 10.08
16.00.00 DESAGE
16.01.00 OBRAS PRELIMINARES
16.01.01 LIMPIEZA DE TERRENO MANUAL S/. 8,950.41
16.01.02 TRAZO Y REPLANTEO S/. 10,393.6316.01.03 CINTA DE PELIGRO S/. 17,333.58 S/. 20,000.28 S/. 2,666.70
16.02.00 MOVIMIENTO DE TIERRAS
16.02.01 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 69,399.49 S/. 10,676.84
16.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 11,056.75 S/. 1,701.04
16.02.03 EXCAVACION C/MAQ EN TERRENO CONGLOMERADO HASTA 2.40 MPROF. S/. 2,756.37
16.02.04 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 45,728.75 S/. 53,045.35
16.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA S/. 3,334.95
16.03.00 OBRAS DE CONCRETO SIMPLE
16.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 41,487.95 S/. 80,210.05
16.04.00 SUMINISTRO E INSTALACION DE TUBERIA
16.04.01 SUMINISTRO E INSTALACION TUBERIA PVC 200 mm.x 6m S26 S/. 186,671.20 S/. 251,600.32 S/. 48,696.84
16.04.02 REFINE, NIVELACION Y CONF. DE FONDO T.C. S/. 37,283.41 S/. 50,251.55 S/. 9,726.11
M1 M2 M3 M4 M5 M6 M7 M8
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 4
7/21/2019 Cronograma Fisico Financiero Agua Potable
5/18
16.04.03 PREPARACION DE CAMA DE APOYO P/TUBERIA S/. 5,480.40 S/. 7,386.62 S/. 1,429.67
16.04.04 INSTALACION TUBERIA PVC 200 MM.X 6M S25 S/. 18,662.81 S/. 44,503.63 S/. 43,068.03 S/. 1,435.60
16.04.05 CONEXION DE TUBERIA PVC A CONCRETO DE BUZON S/. 634.57 S/. 6,557.22 S/. 6,345.70 S/. 2,326.76
16.04.06 PRUEBA HIDRAULICA EN TUBERIA PVC S/. 4,281.04 S/. 3,210.78
16.05.00 CONSTRUCCION DE BUZONES
16.05.01 BUZON ESTANDAR HASTA 0.70M DE PROF. S/. 900.37 S/. 2,147.03 S/. 1,108.14
16.05.02 BUZON ESTANDAR HASTA 0.80M DE PROF. S/. 1,350.55 S/. 3,220.54 S/. 1,662.22
16.05.03 BUZON ESTANDAR HASTA 0.90M DE PROF. S/. 450.18 S/. 1,073.51 S/. 554.07
16.05.04 BUZON ESTANDAR HASTA 1.20M DE PROF. S/. 65,561.50 S/. 156,338.95 S/. 80,691.07
16.05.05 BUZON ESTANDAR HASTA 2.40M DE PROF. S/. 1,098.56 S/. 2,619.64 S/. 1,352.07
16.06.00 CONEXIONES DOMICILIARIAS
16.06.01 MOVIMIENTO DE TIERRAS16.06.01.1 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 9,875.60 S/. 11,774.75 S/. 11,394.92 S/. 11,774.75 S/. 11,774.75 S/. 11,015.09
16.06.01.2 CORTE DE PAVIMENTO CON MOLADORA S/. 914.60 S/. 1,090.49 S/. 1,055.31 S/. 1,090.49 S/. 1,090.49 S/. 1,020.13
16.06.01.3 RELLENO CON MATERIAL PROPIO S/. 5,658.65 S/. 6,287.38 S/. 6,496.96 S/. 6,496.96 S/. 6,077.80
16.06.01.4 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 64,583.15 S/. 71,759.06 S/. 74,151.03 S/. 74,151.03 S/. 69,367.09
16.06.02 TENDIDO E INSTALACION DE TUBERIAS
16.06.02.1 CONEXION DOMICILIARIA 200M T. CONGLOMERADO S/. 25,765.74 S/. 72,612.54 S/. 70,270.20 S/. 72,612.54 S/. 72,612.54 S/. 67,927.86
16.06.02.2 CONEXION DOMICILIARIA 160M T. CONGLOMERADO S/. 818.77 S/. 2,307.43 S/. 2,233.00 S/. 2,307.43 S/. 2,307.43 S/. 2,158.57
16.06.03 FLETE
16.06.03.1 FLETE TERRESTRE ALCANTARILLADO S/. 86.67 S/. 103.33 S/. 100.00 S/. 103.33 S/. 103.33 S/. 96.67
16.06.04 CONTROL DE CALIDAD
16.06.04.1 DISEO DE MEZCLAS DE CONCRETO S/. 6.42 S/. 16.92
16.06.04.2 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 1.88 S/. 54.62
16.06.05 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES
16.06.05.1 CONSTRUCCION DE 2 LAGUNAS FACULTATIVAS EN PARALELO. AREA TOTAL=2.2HA S/. 17,198.47 S/. 38,082.32 S/. 38,082.32 S/. 35,625.40
16.06.05.2 CONSTRUCCION DE CERCO PERIMETRICO
17.00.00 TANQUE IMHOFF - CAMARAS DE REJAS Y DESARENADOR
17.01.00 OBRAS PRELIMINARES
17.01.01 TRAZO Y REPLANTEO S/. 39.84
17.01.02 LIMPIEZA DE TERRENO MANUAL S/. 21.06
17.02.00 MOVIMIENTO DE TIERRAS
17.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 61.42
17.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 104.86
17.03.00 OBRAS DE CONCRETO SIMPLE
17.03.01 CONCRETO FC=140 KG/CM2 S/. 1,203.44
17.03.02 ACERO FY = 4200 KG/CM2. S/. 680.24
17.03.03 ENCOFRADO Y DESENCOFRADO S/. 877.93
17.04.00 REVOQUES Y ENLUCIDOS
17.04.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 1,113.16
17.04.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 102.71
17.05.00 EQUIPAMIENTO
17.05.01 COMPUERTA METALICA DE 0.30X0.50 E=3/16 S/. 470.84
17.05.02 PLANCHA METALICA 0.65X0.4 DE E=1/2 S/. 840.21
17.05.03 REJA P/RETENCION DE SOLIDOS PLAT. 11/2X3/8 MARCO L 11/2X11/2X1/4 S/. 73.54
18.00.00 TANQUE IMHOFF
18.01.00 OBRAS PRELIMINARES
18.01.01 TRAZO Y REPLANTEO S/. 91.68
18.01.02 LIMPIEZA DE TERRENO MANUAL S/. 43.88
18.02.00 MOVIMIENTO DE TIERRAS
18.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 1,858.8318.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 4,293.94
18.03.00 OBRAS DE CONCRETO SIMPLE
18.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 44.34
18.04.00 OBRAS DE CONCRETO ARMADO
18.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 13,039.81
18.04.02 ACERO FY = 4200 KG/CM2. S/. 14,438.31
18.04.03 ENCOFRADO Y DESENCOFRADO S/. 5,391.86
18.05.00 REVOQUES Y ENLUCIDOS
18.05.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 3,421.12
18.05.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 220.89
19.00.00 LECHO DE SECADO
19.01.00 OBRAS PRELIMINARES
M1 M2 M3 M4 M5 M6 M7 M8
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 5
7/21/2019 Cronograma Fisico Financiero Agua Potable
6/18
19.01.01 TRAZO Y REPLANTEO S/. 249.00
19.01.02 LIMPIEZA DE TERRENO MANUAL S/. 135.00
19.02.00 MOVIMIENTO DE TIERRAS
19.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 671.90
19.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 11,176.38
19.03.00 OBRAS DE CONCRETO SIMPLE
19.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 149.04
19.04.00 OBRAS DE CONCRETO ARMADO
19.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 4,213.07
19.04.02 ACERO FY = 4200 KG/CM2. S/. 97.30
19.04.03 ENCOFRADO Y DESENCOFRADO S/. 7,365.86
19.05.00 MUROS DE MAMPOSTERIA
19.05.01 MURO DE SOGA LADRILLO PANDERETA CON CEMENTO - CAL - ARENA S/. 646.24
19.05.02 CUBIERTA DE LADRILLO PASTELERO ASENTADO Y FRAGUADO S/. 8,856.95 S/. 11,809.27
19.06.00 REVOQUES Y ENLUCIDOS
19.06.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 2,292.86
19.07.00 SUMINISTRO Y COLOCACION
19.07.01 ARENA GRUESA SELECCIONADA S/. 998.25
19.07.02 PIEDRA CLASIFICADA DE 3/4 - 2 S/. 1,250.85
19.07.03 PIEDRA CLASIFICADA DE 1/4 - 3/4 S/. 312.48
19.07.04 PIEDRA CLASIFICADA DE 1/16 - 1/4 S/. 468.72
20.00.00 MITIGACION AMBIENTAL
20.01.00 MITIGACION AMBIENTAL S/. 563.64 S/. 545.45 S/. 563.64 S/. 545.45 S/. 563.64 S/. 563.64 S/. 527.27
Total S/. 969,370.72 S/. 1,120,584.96 S/. 837,739.50 S/. 525,314.92 S/. 448,550.37 S/. 455,727.83 S/. 438,452.06
M1 M2 M3 M4 M5 M6 M7 M8
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 6
7/21/2019 Cronograma Fisico Financiero Agua Potable
7/18
MEJORAMIENTO Y AMPLIACION DEL SAP Y ALCANTARILLADO TEMBLADERA
01.00.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL
01.01.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL
02.00.00 CAJA DE CAPTACIN DE FONDO
02.01.00 TRABAJOS PRELIMINARES
02.01.01 DEMOLICION DE CONCRETO ARMADO EN TECHO DE CAPTACION
02.01.02 LIMPIEZA DE TERRENO, CAPTACIN
02.01.03 TRAZO Y REPLANTEO
02.02.00 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACIN MANUAL CAJA DE VALVULAS
02.02.02 ELIMINACION DE MATERIAL EXCEDENTE
02.02.03 NIVELACION INTERIOR APISONADO MANUAL
02.03.00 OBRAS DE CONCRETO SIMPLE
02.03.01 CONCRETO FC=140 KG/CM2 (CAJA VLVULAS)
02.03.02 PIEDRA 4" ASENTADA CON MORTERO 1:8 EN CAPTACION
02.03.03 ENCOFRADO Y DESENCOFRADO
02.04.00 OBRAS DE CONCRETO ARMADO
02.04.01 CONCRETO FC=175 KG/CM2
02.04.02 ACERO FY = 4200 KG/CM2.
02.04.03 ENCOFRADO Y DESENCOFRADO
02.05.00 REVOQUES Y ENLUCIDOS
02.05.01 TARRAJEO EXTERIOR
02.05.02 TARRAJEO INTERIOR
02.06.00 VALVULAS Y ACCESORIOS
02.06.01 VALVULAS Y ACCESORIOS 8"
02.07.00 VARIOS
02.07.01 PINTADO DE ESTRUCTURAS
02.07.02 TAPA SANITARIA 0.60X0.60
03.00.00 LINEA DE CONDUCCIN A R1
03.01.00 TRABAJOS PRELIMINARES
03.01.01 TRAZO Y REPLANTEO
03.02.00 EXCAVACIN DE ZANJAS03.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO
03.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA
03.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS.
03.02.04 CAMA DE APOYO PARA TUBERA
03.02.05 RELLENO Y COMPACTACIN DE ZANJAS
03.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5
03.04.00 PRUEBA HIDRAULICA
03.04.01 PRUEBA HIDRULICA + DESINFECCIN
04.00.00 LINEA DE CONDUCCIN A R2
04.01.00 TRABAJOS PRELIMINARES
04.01.01 TRAZO Y REPLANTEO
04.02.00 EXCAVACIN DE ZANJAS
04.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO
04.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA
04.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS.
04.02.04 CAMA DE APOYO PARA TUBERA
04.02.05 RELLENO Y COMPACTACIN DE ZANJAS
04.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS04.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5
04.04.00 PRUEBA HIDRAULICA
04.04.01 PRUEBA HIDRULICA + DESINFECCIN
05.00.00 RESERVORIO CIRCULAR APOYADO: 100 M3
05.01.00 TRABAJOS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL
05.01.02 TRAZO Y REPLANTEO
05.02.00 MOVIMIENTO DE TIERRAS
05.02.01 EXCAVACION MANUAL
05.02.02 ELIMINACION DE MATERIAL EXCEDENTE
05.02.03 NIVELACION Y COMPACTACION MANUAL
05.02.04 AFIRMADO
M8 M9 M10 M11 M12 M13 M14 M15
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 7
7/21/2019 Cronograma Fisico Financiero Agua Potable
8/18
05.03.00 OBRAS DE CONCRETO SIMPLE
05.03.01 SOLADO DE CONCRETO FC=100 KG/CM2
05.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO
05.03.03 OBRAS DE CONCRETO ARMADO
05.03.04 CONCRETO FC = 210 KG/CM2
05.03.05 ENCOFRADO Y DESENCOFRADO
05.03.06 ACERO FY = 4200 KG/CM2.
05.04.00 REVOQUES Y ENLUCIDOS
05.04.01 TARRAJEO EXTERIOR
05.04.02 TARRAJEO INTERIOR
05.04.03 PENDIENTE DE FONDO, MORTERO 1:5
05.05.00 VALVULAS Y ACCESORIOS
05.06.01 ACCESORIOS PARA VENTILACIN
05.07.00 VARIOS
05.07.01 PINTURA EN EXTERIORES
05.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR
05.07.03 TAPA SANITARIA METLICA
06.00.00 RESERVORIO CIRCULAR APOYADO: 75 M3
06.01.00 TRABAJOS PRELIMINARES
06.01.01 LIMPIEZA DE TERRENO MANUAL
06.01.02 TRAZO Y REPLANTEO
06.02.00 MOVIMIENTO DE TIERRAS
06.02.01 EXCAVACION MANUAL
06.02.02 ELIMINACION DE MATERIAL EXCEDENTE
06.02.03 NIVELACION Y COMPACTACION MANUAL
06.02.04 AFIRMADO
06.03.00 OBRAS DE CONCRETO SIMPLE
06.03.01 SOLADO DE CONCRETO FC=100 KG/CM2
06.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO
06.03.03 OBRAS DE CONCRETO ARMADO
06.03.04 CONCRETO FC = 210 KG/CM2
06.03.05 ENCOFRADO Y DESENCOFRADO06.03.06 ACERO FY = 4200 KG/CM2.
06.04.00 REVOQUES Y ENLUCIDOS
06.04.01 TARRAJEO EXTERIOR
06.04.02 TARRAJEO INTERIOR
06.04.03 PENDIENTE DE FONDO, MORTERO 1:5
06.05.00 VALVULAS Y ACCESORIOS
06.06.00 ACCESORIOS PARA VENTILACIN
06.07.00 VARIOS
06.07.01 PINTURA EN EXTERIORES
06.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR
06.07.03 TAPA SANITARIA METLICA
07.00.00 CASETA DE VALVULAS
07.01.00 TRABAJOS PRELIMINARES
07.01.01 LIMPIEZA DE TERRENO MANUAL
07.01.02 TRAZO Y REPLANTEO
07.02.00 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION MANUAL
07.02.02 ELIMINACION DE MATERIAL EXCEDENTE
07.02.03 NIVELACION Y COMPACTACION MANUAL07.02.04 LECHO DE GRAVA
07.03.00 OBRAS DE CONCRETO SIMPLE
07.03.01 CONCRETO FC=175 KG/CM2
07.03.02 ENCOFRADO Y DESENCOFRADO
07.04.00 OBRAS DE CONCRETO ARMADO
07.04.01 CONCRETO FC=175 KG/CM2
07.04.02 ACERO FY = 4200 KG/CM2.
07.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA
07.05.00 REVOQUES Y ENLUCIDOS
07.05.01 TARRAJEO EXTERIOR
07.05.02 TARRAJEO INTERIOR
07.06.03 VALVULAS Y ACCESORIOS DE 8" (INGRESO CASETA)
M8 M9 M10 M11 M12 M13 M14 M15
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 8
7/21/2019 Cronograma Fisico Financiero Agua Potable
9/18
07.06.03.1 VALVULAS Y ACCESORIOS 8" (INGRESO CAS. VALVULAS)
07.07.00 VARIOS
07.07.01 TAPA SANITARIA METLICA
07.07.02 PINTURA EN EXTERIORES
08.00.00 RED DE DISTRIBUCIN R1 Y R2
08.01.00 TRABAJOS PRELIMINARES
08.01.01 TRAZO Y REPLANTEO S/. 651.95 S/. 630.92 S/. 651.95 S/. 630.92 S/. 651.95 S/. 651.95 S/. 630.92
08.02.00 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,988.74 S/. 22,247.17
08.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 805.48 S/. 779.50 S/. 805.48 S/. 779.50 S/. 805.48 S/. 805.48 S/. 779.50
08.02.03 REFINE Y CONFORMACIN DE FONDOS S/. 1,711.78 S/. 1,656.56 S/. 1,711.78 S/. 1,656.56 S/. 1,711.78 S/. 1,711.78 S/. 1,656.56
08.02.04 CAMA DE APOYO PARA TUBERA S/. 1,170.44 S/. 1,132.69 S/. 1,170.44 S/. 1,132.69 S/. 1,170.44 S/. 1,170.44 S/. 1,132.69
08.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 19,312.34 S/. 18,689.36
08.02.06 OBRAS DE CONCRETO SIMPLE
08.02.06.1 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,559.83 S/. 12,154.67
08.03.00 TUBERA Y ACCESORIOS
08.03.01 SUMINISTRO E INSTALACION TUBERA U.F. 160 MM. C-7.5 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 10,644.26 S/. 10,300.89
08.03.02 SUMINISTRO TUBERA U.F. 110 MM. C-7.5 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 7,211.47 S/. 6,978.84
08.03.03 SUMINISTRO TUBERA U.F. 90 MM. C-7.5 S/. 148.96 S/. 144.16 S/. 148.96 S/. 144.16 S/. 148.96 S/. 148.96 S/. 144.16
08.03.04 SUMINISTRO TUBERA U.F. 63 MM. C-7.5 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 1,145.58 S/. 1,108.63
08.03.05 TUBERA PVC SAP 1/2" C-7.5 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 14,182.72 S/. 13,725.21
08.05.00 ACCESORIOS DE RED DE DISTRIBUCION
08.05.01 TEE PVC 6"X6" S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.55
08.05.02 TEE PVC 6"X4" S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.55
08.05.03 TEE PVC 4"X4" S/. 1.02 S/. 0.98 S/. 1.02 S/. 0.98 S/. 1.02 S/. 1.02 S/. 0.98
08.05.04 TEE PVC 2"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20
08.05.05 TEE PVC 6"X2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.77
08.05.06 REDUC. PVC 6"-2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.77
08.05.07 CODO. PVC 4"X 90 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20
08.05.08 CODO. PVC 6"X 90 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.59
08.05.09 CRUZ PVC 6"X6" S/. 2.23 S/. 2.16 S/. 2.23 S/. 2.16 S/. 2.23 S/. 2.23 S/. 2.16
08.05.10 CRUZ PVC 6"X4" S/. 3.86 S/. 3.73 S/. 3.86 S/. 3.73 S/. 3.86 S/. 3.86 S/. 3.7308.05.11 CRUZ PVC 6"X2" S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.59
08.05.12 CRUZ PVC 4"X4" S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.81 S/. 0.79
08.05.13 CRUZ PVC 4"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20
08.06.00 PRUEBA HIDRAULICA
08.06.01 PRUEBA HIDRAULICA+DESINFECCION S/. 945.54 S/. 915.03 S/. 945.54 S/. 915.03 S/. 945.54 S/. 945.54 S/. 915.03
09.00.00 CAJA DE VALVULAS DE CONTROL
09.01.00 TRABAJOS PRELIMINARES
09.01.01 LIMPIEZA DE TERRENO MANUAL S/. 7.05 S/. 6.82 S/. 7.05 S/. 6.82 S/. 7.05 S/. 7.05 S/. 6.82
09.01.02 TRAZO Y REPLANTEO S/. 3,673.55 S/. 3,555.05 S/. 3,673.55 S/. 3,555.05 S/. 3,673.55 S/. 3,673.55 S/. 3,555.05
09.02.00 MOVIMIENTO DE TIERRAS
09.02.01 EXCAVACION MANUAL S/. 397.42 S/. 384.60 S/. 397.42 S/. 384.60 S/. 397.42 S/. 397.42 S/. 384.60
09.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 577.85 S/. 559.21 S/. 577.85 S/. 559.21 S/. 577.85 S/. 577.85 S/. 559.21
09.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 14.44 S/. 13.97 S/. 14.44 S/. 13.97 S/. 14.44 S/. 14.44 S/. 13.97
09.03.00 CONCRETO SIMPLE
09.03.01 CONCRETO FC=140 KG/CM2 S/. 218.47 S/. 211.43 S/. 218.47 S/. 211.43 S/. 218.47 S/. 218.47 S/. 211.43
09.03.02 ENCOFRADO Y DESENCOFRADO S/. 269.74 S/. 261.04 S/. 269.74 S/. 261.04 S/. 269.74 S/. 269.74 S/. 261.04
09.04.00 TARRAJEO
09.04.01 TARRAJEO EXTERIOR S/. 91.39 S/. 88.44 S/. 91.39 S/. 88.44 S/. 91.39 S/. 91.39 S/. 88.44
09.05.00 VALVULAS Y ACCESORIOS09.05.01 VALVULAS Y ACCESORIOS 4" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.57
09.05.02 VALVULAS Y ACCESORIOS 6" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.57
09.05.03 VALVULAS Y ACCESORIOS 2" S/. 2.03 S/. 1.96 S/. 2.03 S/. 1.96 S/. 2.03 S/. 2.03 S/. 1.96
09.06.00 VARIOS
09.06.01 TAPA SANITARIA METLICA
10.00.00 CAJA DE VALVULAS DE PURGA
10.01.00 TRABAJOS PRELIMIINARES
10.01.01 LIMPIEZA DE TERRENO MANUAL
10.01.02 TRAZO Y REPLANTEO
10.02.00 MOVIMIENTO DE TIERRAS
10.02.01 EXCAVACION MANUAL
10.02.02 ELIMINACION DE MATERIAL EXCEDENTE
M8 M9 M10 M11 M12 M13 M14 M15
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 9
7/21/2019 Cronograma Fisico Financiero Agua Potable
10/18
10.03.00 OBRAS DE CONCRETO SIMPLE
10.03.01 CONCRETO FC=140 KG/CM2
10.03.02 ENCOFRADO Y DESENCOFRADO
10.04.00 TARRAJEO
10.04.01 TARRAJEO EXTERIOR
10.05.00 VALVULAS Y ACCESORIOS PURGA
10.06.00 VARIOS
10.06.01 TAPA SANITARIA METLICA
11.00.00 CONEXIONES DOMICILIARIAS
11.01.00 TRABAJOS PRELIMIINARES
11.01.01 LIMPIEZA DE TERRENO MANUAL S/. 406.11 S/. 393.01 S/. 406.11 S/. 393.01 S/. 406.11 S/. 406.11 S/. 393.01
11.01.02 TRAZO Y REPLANTEO S/. 749.05 S/. 724.89 S/. 749.05 S/. 724.89 S/. 749.05 S/. 749.05 S/. 724.89
11.02.00 MOVIMIENTO DE TIERRAS
11.02.01 EXCAVACION MANUAL S/. 2,422.23 S/. 2,344.10 S/. 2,422.23 S/. 2,344.10 S/. 2,422.23 S/. 2,422.23 S/. 2,344.10
11.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 251.25 S/. 243.14 S/. 251.25 S/. 243.14 S/. 251.25 S/. 251.25 S/. 243.14
11.02.03 RELLENO Y COMPACTACIN DE ZANJAS
11.03.00 OBRAS DE CONCRETO SIMPLE
11.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 4,085.31 S/. 3,953.52
11.03.02 CONCRETO FC=140 KG/CM2 S/. 416.67 S/. 403.23 S/. 416.67 S/. 403.23 S/. 416.67 S/. 416.67 S/. 403.23
11.03.03 ENCOFRADO Y DESENCOFRADO S/. 640.74 S/. 620.07 S/. 640.74 S/. 620.07 S/. 640.74 S/. 640.74 S/. 620.07
11.04.00 OBRAS DE CONCRETO ARMADO
11.04.01 CONCRETO FC=175 KG/CM2 S/. 133.02 S/. 128.73 S/. 133.02 S/. 128.73 S/. 133.02 S/. 133.02 S/. 128.73
11.04.02 ACERO FY = 4200 KG/CM2. S/. 88.26 S/. 85.41 S/. 88.26 S/. 85.41 S/. 88.26 S/. 88.26 S/. 85.41
11.04.03 ENCOFRADO Y DESENCOFRADO S/. 97.61 S/. 94.46 S/. 97.61 S/. 94.46 S/. 97.61 S/. 97.61 S/. 94.46
11.05.00 CONEXIONES DOMICILIARIAS
11.05.01 CONEXIN DOMICILIARIA DE AGUA 6" S/. 86.97 S/. 84.17 S/. 86.97 S/. 84.17 S/. 86.97 S/. 86.97 S/. 84.17
11.05.02 CONEXIN DOMICILIARIA DE AGUA 4" S/. 99.40 S/. 96.19 S/. 99.40 S/. 96.19 S/. 99.40 S/. 99.40 S/. 96.19
11.05.03 CONEXIN DOMICILIARIA DE AGUA 3" S/. 6.83 S/. 6.61 S/. 6.83 S/. 6.61 S/. 6.83 S/. 6.83 S/. 6.61
11.05.04 CONEXIN DOMICILIARIA DE AGUA 2" S/. 57.98 S/. 56.11 S/. 57.98 S/. 56.11 S/. 57.98 S/. 57.98 S/. 56.11
11.05.05 SUMINISTRO E INSTALACION DE MEDIDORES S/. 10,172.36 S/. 9,844.22 S/. 10,172.36 S/. 9,844.22 S/. 10,172.36 S/. 10,172.36 S/. 9,844.22
12.00.00 CASETA DE CLORACIN
12.01.00 MUROS DE LADRILLOS DE SOGA12.02.00 COBERTURA DE CALAMINA
12.03.00 CARPINTERIA METALICA
12.04.00 TARRAJEO EM MUROS
12.05.00 CERRAJERIA
12.06.00 PINTURA EN MUROS
12.07.00 VIDRIOS
13.00.00 EDUCACIN SANITARIA Y CAPACITACION EN AOM.
13.01.00 EDUCACIN SANITARIA
13.03.00 CAPACITACIN EN A+O+M
14.00.00 FLETE
14.01.00 FLETE TERRESTRE S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 230.77
14.02.00 FLETE RURAL S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 230.77
15.00.00 CONTROL DE CALIDAD
15.01.00 DISE O DE MEZCLAS DE CONCRETO S/. 31.30 S/. 30.29 S/. 31.30 S/. 30.29 S/. 31.30 S/. 31.30 S/. 30.29
15.02.00 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.78 S/. 10.43
16.00.00 DESAGE
16.01.00 OBRAS PRELIMINARES
16.01.01 LIMPIEZA DE TERRENO MANUAL
16.01.02 TRAZO Y REPLANTEO16.01.03 CINTA DE PELIGRO
16.02.00 MOVIMIENTO DE TIERRAS
16.02.01 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO
16.02.02 CORTE DE PAVIMENTO CON MOLADORA
16.02.03 EXCAVACION C/MAQ EN TERRENO CONGLOMERADO HASTA 2.40 MPROF.
16.02.04 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 10,974.90
16.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA
16.03.00 OBRAS DE CONCRETO SIMPLE
16.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 85,741.77
16.04.00 SUMINISTRO E INSTALACION DE TUBERIA
16.04.01 SUMINISTRO E INSTALACION TUBERIA PVC 200 mm.x 6m S26
16.04.02 REFINE, NIVELACION Y CONF. DE FONDO T.C.
M8 M9 M10 M11 M12 M13 M14 M15
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 10
7/21/2019 Cronograma Fisico Financiero Agua Potable
11/18
16.04.03 PREPARACION DE CAMA DE APOYO P/TUBERIA
16.04.04 INSTALACION TUBERIA PVC 200 MM.X 6M S25
16.04.05 CONEXION DE TUBERIA PVC A CONCRETO DE BUZON
16.04.06 PRUEBA HIDRAULICA EN TUBERIA PVC
16.05.00 CONSTRUCCION DE BUZONES
16.05.01 BUZON ESTANDAR HASTA 0.70M DE PROF.
16.05.02 BUZON ESTANDAR HASTA 0.80M DE PROF.
16.05.03 BUZON ESTANDAR HASTA 0.90M DE PROF.
16.05.04 BUZON ESTANDAR HASTA 1.20M DE PROF.
16.05.05 BUZON ESTANDAR HASTA 2.40M DE PROF.
16.06.00 CONEXIONES DOMICILIARIAS
16.06.01 MOVIMIENTO DE TIERRAS
16.06.01.1 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 759.66
16.06.01.2 CORTE DE PAVIMENTO CON MOLADORA S/. 70.35
16.06.01.3 RELLENO CON MATERIAL PROPIO S/. 6,496.96 S/. 209.58
16.06 .01.4 RELLEN O Y COMPAC TACI ON D E ZANJAS C ON MAT ER IAL PR OPIO SELEC CION AD O S/. 74,151.03 S /. 2 ,391 .97
16.06.02 TENDIDO E INSTALACION DE TUBERIAS
16.06.02.1 CONEXION DOMICILIARIA 200M T. CONGLOMERADO S/. 39,819.78
16.06.02.2 CONEXION DOMICILIARIA 160M T. CONGLOMERADO S/. 1,265.37
16.06.03 FLETE
16.06.03.1 FLETE TERRESTRE ALCANTARILLADO S/. 6.67
16.06.04 CONTROL DE CALIDAD
16.06.04.1 DISEO DE MEZCLAS DE CONCRETO S/. 18.08 S/. 17.50 S/. 18.08 S/. 17.50 S/. 10.50
16.06.04.2 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 58.38 S/. 56.50 S/. 58.38 S/. 56.50 S/. 52.73
16.06.05 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES
16.06.05.1 CONSTRUCCION DE 2 LAGUNAS FACULTATIVAS EN PARALELO. AREA TOTAL=2.2HA S/. 18,426.93
16.06.05.2 CONSTRUCCION DE CERCO PERIMETRICO S/. 2,513.13
17.00.00 TANQUE IMHOFF - CAMARAS DE REJAS Y DESARENADOR
17.01.00 OBRAS PRELIMINARES
17.01.01 TRAZO Y REPLANTEO
17.01.02 LIMPIEZA DE TERRENO MANUAL
17.02.00 MOVIMIENTO DE TIERRAS17.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M
17.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO
17.03.00 OBRAS DE CONCRETO SIMPLE
17.03.01 CONCRETO FC=140 KG/CM2
17.03.02 ACERO FY = 4200 KG/CM2.
17.03.03 ENCOFRADO Y DESENCOFRADO
17.04.00 REVOQUES Y ENLUCIDOS
17.04.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR
17.04.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA
17.05.00 EQUIPAMIENTO
17.05.01 COMPUERTA METALICA DE 0.30X0.50 E=3/16
17.05.02 PLANCHA METALICA 0.65X0.4 DE E=1/2
17.05.03 REJA P/RETENCION DE SO LIDOS PLAT. 11/2X3/8 MARCO L 11/2X11/2X1/4
18.00.00 TANQUE IMHOFF
18.01.00 OBRAS PRELIMINARES
18.01.01 TRAZO Y REPLANTEO
18.01.02 LIMPIEZA DE TERRENO MANUAL
18.02.00 MOVIMIENTO DE TIERRAS
18.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M18.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO
18.03.00 OBRAS DE CONCRETO SIMPLE
18.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2
18.04.00 OBRAS DE CONCRETO ARMADO
18.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2
18.04.02 ACERO FY = 4200 KG/CM2.
18.04.03 ENCOFRADO Y DESENCOFRADO
18.05.00 REVOQUES Y ENLUCIDOS
18.05.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR
18.05.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA
19.00.00 LECHO DE SECADO
19.01.00 OBRAS PRELIMINARES
M8 M9 M10 M11 M12 M13 M14 M15
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 11
7/21/2019 Cronograma Fisico Financiero Agua Potable
12/18
19.01.01 TRAZO Y REPLANTEO
19.01.02 LIMPIEZA DE TERRENO MANUAL
19.02.00 MOVIMIENTO DE TIERRAS
19.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M
19.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO
19.03.00 OBRAS DE CONCRETO SIMPLE
19.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2
19.04.00 OBRAS DE CONCRETO ARMADO
19.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2
19.04.02 ACERO FY = 4200 KG/CM2.
19.04.03 ENCOFRADO Y DESENCOFRADO
19.05.00 MUROS DE MAMPOSTERIA
19.05.01 MURO DE SOGA LADRILLO PANDERETA CON CEMENTO - CAL - ARENA19.05.02 CUBIERTA DE LADRILLO PASTELERO ASENTADO Y FRAGUADO
19.06.00 REVOQUES Y ENLUCIDOS
19.06.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR
19.07.00 SUMINISTRO Y COLOCACION
19.07.01 ARENA GRUESA SELECCIONADA
19.07.02 PIEDRA CLASIFICADA DE 3/4 - 2
19.07.03 PIEDRA CLASIFICADA DE 1/4 - 3/4
19.07.04 PIEDRA CLASIFICADA DE 1/16 - 1/4
20.00.00 MITIGACION AMBIENTAL
20.01.00 MITIGACION AMBIENTAL S/. 563.64 S/. 545.45 S/. 563.64 S/. 545.45 S/. 563.64 S/. 563.64 S/. 545.45
Total S/. 359,852.39 S/. 118,368.49 S/. 119,625.84 S/. 115,766.94 S/. 119,612.61 S/. 119,549.38 S/. 115,692.94
M8 M9 M10 M11 M12 M13 M14 M15
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 12
7/21/2019 Cronograma Fisico Financiero Agua Potable
13/18
MEJORAMIENTO Y AMPLIACION DEL SAP Y ALCANTARILLADO TEMBLADERA
01.00.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL
01.01.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL S/. 1,279.38
02.00.00 CAJA DE CAPTACIN DE FONDO
02.01.00 TRABAJOS PRELIMINARES
02.01.01 DEMOLICION DE CONCRETO ARMADO EN TECHO DE CAPTACION S/. 3,840.41
02.01.02 LIMPIEZA DE TERRENO, CAPTACIN S/. 109.20
02.01.03 TRAZO Y REPLANTEO S/. 6.85
02.02.00 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACIN MANUAL CAJA DE VALVULAS S/. 28.81
02.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 21.36
02.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 1.62
02.03.00 OBRAS DE CONCRETO SIMPLE02.03.01 CONCRETO FC=140 KG/CM2 (CAJA VLVULAS) S/. 9,893.62
02.03.02 PIEDRA 4" ASENTADA CON MORTERO 1:8 EN CAPTACION S/. 572.48
02.03.03 ENCOFRADO Y DESENCOFRADO S/. 43.43
02.04.00 OBRAS DE CONCRETO ARMADO
02.04.01 CONCRETO FC=175 KG/CM2 S/. 4,968.85
02.04.02 ACERO FY = 4200 KG/CM2. S/. 331.64
02.04.03 ENCOFRADO Y DESENCOFRADO S/. 1,787.14
02.05.00 REVOQUES Y ENLUCIDOS
02.05.01 TARRAJEO EXTERIOR S/. 1,015.11
02.05.02 TARRAJEO INTERIOR S/. 1,695.04
02.06.00 VALVULAS Y ACCESORIOS
02.06.01 VALVULAS Y ACCESORIOS 8" S/. 768.53
02.07.00 VARIOS
02.07.01 PINTADO DE ESTRUCTURAS S/. 534.32
02.07.02 TAPA SANITARIA 0.60X0.60 S/. 271.72
03.00.00 LINEA DE CONDUCCIN A R1
03.01.00 TRABAJOS PRELIMINARES
03.01.01 TRAZO Y REPLANTEO S/. 2,132.47
03.02.00 EXCAVACIN DE ZANJAS03.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10
03.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 88,011.78
03.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 5,764.59
03.02.04 CAMA DE APOYO PARA TUBERA S/. 709.49
03.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 65,036.40
03.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 311,484.94
03.04.00 PRUEBA HIDRAULICA
03.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,153.28
04.00.00 LINEA DE CONDUCCIN A R2
04.01.00 TRABAJOS PRELIMINARES
04.01.01 TRAZO Y REPLANTEO S/. 2,270.89
04.02.00 EXCAVACIN DE ZANJAS
04.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10
04.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 95,293.49
04.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 6,142.50
04.02.04 CAMA DE APOYO PARA TUBERA S/. 756.00
04.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 69,300.00
04.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS04.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 331,905.00
04.04.00 PRUEBA HIDRAULICA
04.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,360.00
05.00.00 RESERVORIO CIRCULAR APOYADO: 100 M3
05.01.00 TRABAJOS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL S/. 58.83
05.01.02 TRAZO Y REPLANTEO S/. 115.96
05.02.00 MOVIMIENTO DE TIERRAS
05.02.01 EXCAVACION MANUAL S/. 499.90
05.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 464.77
05.02.03 NIVELACION Y COMPACTACION MANUAL S/. 91.74
05.02.04 AFIRMADO S/. 244.65
TotalM15 M16 M17 M18 M19 M20
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 13
7/21/2019 Cronograma Fisico Financiero Agua Potable
14/18
05.03.00 OBRAS DE CONCRETO SIMPLE
05.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 131.78
05.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 364.54
05.03.03 OBRAS DE CONCRETO ARMADO
05.03.04 CONCRETO FC = 210 KG/CM2 S/. 42,636.38
05.03.05 ENCOFRADO Y DESENCOFRADO S/. 3,979.13
05.03.06 ACERO FY = 4200 KG/CM2. S/. 9,720.33
05.04.00 REVOQUES Y ENLUCIDOS
05.04.01 TARRAJEO EXTERIOR S/. 3,332.14
05.04.02 TARRAJEO INTERIOR S/. 2,850.49
05.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,385.27
05.05.00 VALVULAS Y ACCESORIOS
05.06.01 ACCESORIOS PARA VENTILACIN S/. 625.9205.07.00 VARIOS
05.07.01 PINTURA EN EXTERIORES S/. 1,047.95
05.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03
05.07.03 TAPA SANITARIA METLICA S/. 165.86
06.00.00 RESERVORIO CIRCULAR APOYADO: 75 M3
06.01.00 TRABAJOS PRELIMINARES
06.01.01 LIMPIEZA DE TERRENO MANUAL S/. 52.80
06.01.02 TRAZO Y REPLANTEO S/. 101.39
06.02.00 MOVIMIENTO DE TIERRAS
06.02.01 EXCAVACION MANUAL S/. 437.09
06.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 406.39
06.02.03 NIVELACION Y COMPACTACION MANUAL S/. 80.22
06.02.04 AFIRMADO S/. 427.96
06.03.00 OBRAS DE CONCRETO SIMPLE
06.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 115.36
06.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 12,794.25
06.03.03 OBRAS DE CONCRETO ARMADO
06.03.04 CONCRETO FC = 210 KG/CM2 S/. 17,578.49
06.03.05 ENCOFRADO Y DESENCOFRADO S/. 3,679.2706.03.06 ACERO FY = 4200 KG/CM2. S/. 8,619.09
06.04.00 REVOQUES Y ENLUCIDOS
06.04.01 TARRAJEO EXTERIOR S/. 3,183.93
06.04.02 TARRAJEO INTERIOR S/. 2,575.35
06.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,180.27
06.05.00 VALVULAS Y ACCESORIOS
06.06.00 ACCESORIOS PARA VENTILACIN S/. 625.92
06.07.00 VARIOS
06.07.01 PINTURA EN EXTERIORES S/. 652.63
06.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03
06.07.03 TAPA SANITARIA METLICA S/. 165.86
07.00.00 CASETA DE VALVULAS
07.01.00 TRABAJOS PRELIMINARES
07.01.01 LIMPIEZA DE TERRENO MANUAL S/. 23.39
07.01.02 TRAZO Y REPLANTEO S/. 37.65
07.02.00 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION MANUAL S/. 188.69
07.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 175.45
07.02.03 NIVELACION Y COMPACTACION MANUAL S/. 29.7907.02.04 LECHO DE GRAVA S/. 132.91
07.03.00 OBRAS DE CONCRETO SIMPLE
07.03.01 CONCRETO FC=175 KG/CM2 S/. 1,293.78
07.03.02 ENCOFRADO Y DESENCOFRADO S/. 738.82
07.04.00 OBRAS DE CONCRETO ARMADO
07.04.01 CONCRETO FC=175 KG/CM2 S/. 406.70
07.04.02 ACERO FY = 4200 KG/CM2. S/. 381.62
07.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA S/. 328.02
07.05.00 REVOQUES Y ENLUCIDOS
07.05.01 TARRAJEO EXTERIOR S/. 743.74
07.05.02 TARRAJEO INTERIOR S/. 506.09
07.06.03 VALVULAS Y ACCESORIOS DE 8" (INGRESO CASETA)
TotalM15 M16 M17 M18 M19 M20
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 14
7/21/2019 Cronograma Fisico Financiero Agua Potable
15/18
07.06.03.1 VALVULAS Y ACCESORIOS 8" (INGRESO CAS. VALVULAS) S/. 768.53
07.07.00 VARIOS
07.07.01 TAPA SANITARIA METLICA S/. 331.72
07.07.02 PINTURA EN EXTERIORES S/. 455.92
08.00.00 RED DE DISTRIBUCIN R1 Y R2
08.01.00 TRABAJOS PRELIMINARES
08.01.01 TRAZO Y REPLANTEO S/. 651.95 S/. 630.92 S/. 252.37 S/. 10,515.33
08.02.00 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 22,988.74 S/. 22,247.17 S/. 2,966.29 S/. 364,853.57
08.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 805.48 S/. 779.50 S/. 77.95 S/. 12,757.78
08.02.03 REFINE Y CONFORMACIN DE FONDOS S/. 1,711.78 S/. 1,656.56 S/. 1,546.12 S/. 28,437.62
08.02.04 CAMA DE APOYO PARA TUBERA S/. 1,170.44 S/. 1,132.69 S/. 1,132.69 S/. 19,444.46
08.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 14,951.49 S/. 320,834.0308.02.06 OBRAS DE CONCRETO SIMPLE
08.02.06.1 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,559.83 S/. 207,439.75
08.03.00 TUBERA Y ACCESORIOS
08.03.01 SUMINISTRO E INSTALACION TUBERA U.F. 160 MM. C-7.5 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 8,240.71 S/. 181,982.46
08.03.02 SUMINISTRO TUBERA U.F. 110 MM. C-7.5 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 5,583.07 S/. 123,292.86
08.03.03 SUMINISTRO TUBERA U.F. 90 MM. C-7.5 S/. 148.96 S/. 144.16 S/. 148.96 S/. 115.32 S/. 2,546.76
08.03.04 SUMINISTRO TUBERA U.F. 63 MM. C-7.5 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 886.90 S/. 19,585.75
08.03.05 TUBERA PVC SAP 1/2" C-7.5 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 10,980.17 S/. 242,478.74
08.05.00 ACCESORIOS DE RED DE DISTRIBUCION
08.05.01 TEE PVC 6"X6" S/. 2.64 S/. 2.55 S/. 2.64 S/. 0.34 S/. 43.40
08.05.02 TEE PVC 6"X4" S/. 2.64 S/. 2.55 S/. 2.64 S/. 0.34 S/. 43.40
08.05.03 TEE PVC 4"X4" S/. 1.02 S/. 0.98 S/. 1.02 S/. 0.13 S/. 16.73
08.05.04 TEE PVC 2"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.03 S/. 3.34
08.05.05 TEE PVC 6"X2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 0.24 S/. 30.10
08.05.06 REDUC. PVC 6"-2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 0.24 S/. 30.10
08.05.07 CODO. PVC 4"X 90 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.03 S/. 3.34
08.05.08 CODO. PVC 6"X 90 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.08 S/. 10.03
08.05.09 CRUZ PVC 6"X6" S/. 2.23 S/. 2.16 S/. 2.23 S/. 0.29 S/. 36.71
08.05.10 CRUZ PVC 6"X4" S/. 3.86 S/. 3.73 S/. 3.86 S/. 0.50 S/. 63.4708.05.11 CRUZ PVC 6"X2" S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.08 S/. 10.03
08.05.12 CRUZ PVC 4"X4" S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.10 S/. 13.36
08.05.13 CRUZ PVC 4"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.03 S/. 3.34
08.06.00 PRUEBA HIDRAULICA
08.06.01 PRUEBA HIDRAULICA+DESINFECCION S/. 945.54 S/. 915.03 S/. 945.54 S/. 122.00 S/. 15,555.59
09.00.00 CAJA DE VALVULAS DE CONTROL
09.01.00 TRABAJOS PRELIMINARES
09.01.01 LIMPIEZA DE TERRENO MANUAL S/. 7.05 S/. 6.82 S/. 5.00 S/. 115.96
09.01.02 TRAZO Y REPLANTEO S/. 3,673.55 S/. 3,555.05 S/. 2,725.54 S/. 60,435.84
09.02.00 MOVIMIENTO DE TIERRAS
09.02.01 EXCAVACION MANUAL S/. 397.42 S/. 384.60 S/. 358.96 S/. 6,538.20
09.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 577.85 S/. 559.21 S/. 410.08 S/. 9,506.56
09.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 14.44 S/. 13.97 S/. 10.25 S/. 237.54
09.03.00 CONCRETO SIMPLE
09.03.01 CONCRETO FC=140 KG/CM2 S/. 218.47 S/. 211.43 S/. 155.05 S/. 3,594.24
09.03.02 ENCOFRADO Y DESENCOFRADO S/. 269.74 S/. 261.04 S/. 191.43 S/. 4,437.66
09.04.00 TARRAJEO
09.04.01 TARRAJEO EXTERIOR S/. 91.39 S/. 88.44 S/. 64.85 S/. 1,503.49
09.05.00 VALVULAS Y ACCESORIOS09.05.01 VALVULAS Y ACCESORIOS 4" S/. 1.62 S/. 1.57 S/. 1.15 S/. 26.67
09.05.02 VALVULAS Y ACCESORIOS 6" S/. 1.62 S/. 1.57 S/. 1.15 S/. 26.67
09.05.03 VALVULAS Y ACCESORIOS 2" S/. 2.03 S/. 1.96 S/. 1.44 S/. 33.37
09.06.00 VARIOS
09.06.01 TAPA SANITARIA METLICA S/. 165.86 S/. 165.86
10.00.00 CAJA DE VALVULAS DE PURGA
10.01.00 TRABAJOS PRELIMIINARES
10.01.01 LIMPIEZA DE TERRENO MANUAL S/. 20.50 S/. 17.94 S/. 38.44
10.01.02 TRAZO Y REPLANTEO S/. 70.89 S/. 70.89
10.02.00 MOVIMIENTO DE TIERRAS
10.02.01 EXCAVACION MANUAL S/. 479.36 S/. 479.36
10.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 133.71 S/. 311.99 S/. 445.70
TotalM15 M16 M17 M18 M19 M20
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 15
7/21/2019 Cronograma Fisico Financiero Agua Potable
16/18
10.03.00 OBRAS DE CONCRETO SIMPLE
10.03.01 CONCRETO FC=140 KG/CM2 S/. 1,208.78 S/. 1,208.78
10.03.02 ENCOFRADO Y DESENCOFRADO S/. 1,104.90 S/. 1,104.90
10.04.00 TARRAJEO
10.04.01 TARRAJEO EXTERIOR S/. 698.03 S/. 698.03
10.05.00 VALVULAS Y ACCESORIOS PURGA S/. 10.69 S/. 16.03 S/. 26.72
10.06.00 VARIOS
10.06.01 TAPA SANITARIA METLICA S/. 431.24 S/. 1,724.94 S/. 2,156.18
11.00.00 CONEXIONES DOMICILIARIAS
11.01.00 TRABAJOS PRELIMIINARES
11.01.01 LIMPIEZA DE TERRENO MANUAL S/. 406.11 S/. 393.01 S/. 157.20 S/. 6,550.16
11.01.02 TRAZO Y REPLANTEO S/. 749.05 S/. 724.89 S/. 338.28 S/. 12,081.48
11.02.00 MOVIMIENTO DE TIERRAS11.02.01 EXCAVACION MANUAL S/. 2,422.23 S/. 2,344.10 S/. 1,484.60 S/. 39,068.28
11.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 251.25 S/. 243.14 S/. 153.99 S/. 4,052.38
11.02.03 RELLENO Y COMPACTACIN DE ZANJAS S/. 160,116.00
11.03.00 OBRAS DE CONCRETO SIMPLE
11.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 395.35 S/. 65,892.06
11.03.02 CONCRETO FC=140 KG/CM2 S/. 416.67 S/. 403.23 S/. 416.67 S/. 40.32 S/. 6,720.49
11.03.03 ENCOFRADO Y DESENCOFRADO S/. 640.74 S/. 620.07 S/. 640.74 S/. 62.01 S/. 10,334.51
11.04.00 OBRAS DE CONCRETO ARMADO
11.04.01 CONCRETO FC=175 KG/CM2 S/. 133.02 S/. 128.73 S/. 133.02 S/. 12.87 S/. 2,145.49
11.04.02 ACERO FY = 4200 KG/CM2. S/. 88.26 S/. 85.41 S/. 88.26 S/. 8.54 S/. 1,423.52
11.04.03 ENCOFRADO Y DESENCOFRADO S/. 97.61 S/. 94.46 S/. 97.61 S/. 9.45 S/. 1,574.35
11.05.00 CONEXIONES DOMICILIARIAS
11.05.01 CONEXIN DOMICILIARIA DE AGUA 6" S/. 86.97 S/. 84.17 S/. 81.36 S/. 1,402.78
11.05.02 CONEXIN DOMICILIARIA DE AGUA 4" S/. 99.40 S/. 96.19 S/. 92.99 S/. 1,603.21
11.05.03 CONEXIN DOMICILIARIA DE AGUA 3" S/. 6.83 S/. 6.61 S/. 6.39 S/. 110.17
11.05.04 CONEXIN DOMICILIARIA DE AGUA 2" S/. 57.98 S/. 56.11 S/. 54.24 S/. 935.17
11.05.05 SUMINISTRO E INSTALACION DE MEDIDORES S/. 10,172.36 S/. 9,844.22 S/. 9,516.08 S/. 164,070.33
12.00.00 CASETA DE CLORACIN
12.01.00 MUROS DE LADRILLOS DE SOGA S/. 667.4612.02.00 COBERTURA DE CALAMINA S/. 16.35
12.03.00 CARPINTERIA METALICA S/. 1,305.21
12.04.00 TARRAJEO EM MUROS S/. 215.03
12.05.00 CERRAJERIA S/. 18.86
12.06.00 PINTURA EN MUROS S/. 241.53
12.07.00 VIDRIOS S/. 163.62
13.00.00 EDUCACIN SANITARIA Y CAPACITACION EN AOM.
13.01.00 EDUCACIN SANITARIA S/. 28,800.00
13.03.00 CAPACITACIN EN A+O+M S/. 153,297.00
14.00.00 FLETE
14.01.00 FLETE TERRESTRE S/. 238.46 S/. 230.77 S/. 238.46 S/. 7.69 S/. 3,999.99
14.02.00 FLETE RURAL S/. 238.46 S/. 230.77 S/. 238.46 S/. 7.69 S/. 3,999.99
15.00.00 CONTROL DE CALIDAD
15.01.00 DISE O DE MEZCLAS DE CONCRETO S/. 31.30 S/. 30.29 S/. 31.30 S/. 1.01 S/. 525.03
15.02.00 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 10.78 S/. 10.43 S/. 10.78 S/. 0.35 S/. 180.81
16.00.00 DESAGE
16.01.00 OBRAS PRELIMINARES
16.01.01 LIMPIEZA DE TERRENO MANUAL S/. 8,950.41
16.01.02 TRAZO Y REPLANTEO S/. 10,393.6316.01.03 CINTA DE PELIGRO S/. 40,000.56
16.02.00 MOVIMIENTO DE TIERRAS
16.02.01 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 80,076.33
16.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 12,757.79
16.02.03 EXCAVACION C/MAQ EN TERRENO CONGLOMERADO HASTA 2.40 MPROF. S/. 2,756.37
16.02.04 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 109,749.00
16.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA S/. 3,334.95
16.03.00 OBRAS DE CONCRETO SIMPLE
16.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 207,439.77
16.04.00 SUMINISTRO E INSTALACION DE TUBERIA
16.04.01 SUMINISTRO E INSTALACION TUBERIA PVC 200 mm.x 6m S26 S/. 486,968.36
16.04.02 REFINE, NIVELACION Y CONF. DE FONDO T.C. S/. 97,261.07
TotalM15 M16 M17 M18 M19 M20
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 16
7/21/2019 Cronograma Fisico Financiero Agua Potable
17/18
16.04.03 PREPARACION DE CAMA DE APOYO P/TUBERIA S/. 14,296.69
16.04.04 INSTALACION TUBERIA PVC 200 MM.X 6M S25 S/. 107,670.07
16.04.05 CONEXION DE TUBERIA PVC A CONCRETO DE BUZON S/. 15,864.25
16.04.06 PRUEBA HIDRAULICA EN TUBERIA PVC S/. 7,491.82
16.05.00 CONSTRUCCION DE BUZONES
16.05.01 BUZON ESTANDAR HASTA 0.70M DE PROF. S/. 4,155.54
16.05.02 BUZON ESTANDAR HASTA 0.80M DE PROF. S/. 6,233.31
16.05.03 BUZON ESTANDAR HASTA 0.90M DE PROF. S/. 2,077.76
16.05.04 BUZON ESTANDAR HASTA 1.20M DE PROF. S/. 302,591.52
16.05.05 BUZON ESTANDAR HASTA 2.40M DE PROF. S/. 5,070.27
16.06.00 CONEXIONES DOMICILIARIAS
16.06.01 MOVIMIENTO DE TIERRAS
16.06.01.1 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 68,369.5216.06.01.2 CORTE DE PAVIMENTO CON MOLADORA S/. 6,331.86
16.06.01.3 RELLENO CON MATERIAL PROPIO S/. 37,724.29
16.06.01.4 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 430,554.36
16.06.02 TENDIDO E INSTALACION DE TUBERIAS
16.06.02.1 CONEXION DOMICILIARIA 200M T. CONGLOMERADO S/. 421,621.20
16.06.02.2 CONEXION DOMICILIARIA 160M T. CONGLOMERADO S/. 13,398.00
16.06.03 FLETE
16.06.03.1 FLETE TERRESTRE ALCANTARILLADO S/. 600.00
16.06.04 CONTROL DE CALIDAD
16.06.04.1 DISEO DE MEZCLAS DE CONCRETO S/. 105.00
16.06.04.2 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 338.99
16.06.05 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES
16.06.05.1 CONSTRUCCION DE 2 LAGUNAS FACULTATIVAS EN PARALELO. AREA TOTAL=2.2HA S/. 147,415.44
16.06.05.2 CONSTRUCCION DE CERCO PERIMETRICO S/. 2,513.13
17.00.00 TANQUE IMHOFF - CAMARAS DE REJAS Y DESARENADOR
17.01.00 OBRAS PRELIMINARES
17.01.01 TRAZO Y REPLANTEO S/. 39.84
17.01.02 LIMPIEZA DE TERRENO MANUAL S/. 21.06
17.02.00 MOVIMIENTO DE TIERRAS17.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 61.42
17.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 104.86
17.03.00 OBRAS DE CONCRETO SIMPLE
17.03.01 CONCRETO FC=140 KG/CM2 S/. 1,203.44
17.03.02 ACERO FY = 4200 KG/CM2. S/. 680.24
17.03.03 ENCOFRADO Y DESENCOFRADO S/. 877.93
17.04.00 REVOQUES Y ENLUCIDOS
17.04.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 1,113.16
17.04.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 102.71
17.05.00 EQUIPAMIENTO
17.05.01 COMPUERTA METALICA DE 0.30X0.50 E=3/16 S/. 470.84
17.05.02 PLANCHA METALICA 0.65X0.4 DE E=1/2 S/. 840.21
17.05.03 REJA P/RETENCION DE SOLIDOS PLAT. 11/2X3/8 MARCO L 11/2X11/2X1/4 S/. 73.54
18.00.00 TANQUE IMHOFF
18.01.00 OBRAS PRELIMINARES
18.01.01 TRAZO Y REPLANTEO S/. 91.68
18.01.02 LIMPIEZA DE TERRENO MANUAL S/. 43.88
18.02.00 MOVIMIENTO DE TIERRAS
18.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 1,858.83
18.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 4,293.94
18.03.00 OBRAS DE CONCRETO SIMPLE
18.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 44.34
18.04.00 OBRAS DE CONCRETO ARMADO
18.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 13,039.81
18.04.02 ACERO FY = 4200 KG/CM2. S/. 14,438.31
18.04.03 ENCOFRADO Y DESENCOFRADO S/. 5,391.86
18.05.00 REVOQUES Y ENLUCIDOS
18.05.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 3,421.12
18.05.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 220.89
19.00.00 LECHO DE SECADO
19.01.00 OBRAS PRELIMINARES
TotalM15 M16 M17 M18 M19 M20
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 17
7/21/2019 Cronograma Fisico Financiero Agua Potable
18/18
19.01.01 TRAZO Y REPLANTEO S/. 249.00
19.01.02 LIMPIEZA DE TERRENO MANUAL S/. 135.00
19.02.00 MOVIMIENTO DE TIERRAS
19.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 671.90
19.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 11,176.38
19.03.00 OBRAS DE CONCRETO SIMPLE
19.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 149.04
19.04.00 OBRAS DE CONCRETO ARMADO
19.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 4,213.07
19.04.02 ACERO FY = 4200 KG/CM2. S/. 97.30
19.04.03 ENCOFRADO Y DESENCOFRADO S/. 7,365.86
19.05.00 MUROS DE MAMPOSTERIA
19.05.01 MURO DE SOGA LADRILLO PANDERETA CON CEMENTO - CAL - ARENA S/. 646.2419.05.02 CUBIERTA DE LADRILLO PASTELERO ASENTADO Y FRAGUADO S/. 20,666.22
19.06.00 REVOQUES Y ENLUCIDOS
19.06.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 2,292.86
19.07.00 SUMINISTRO Y COLOCACION
19.07.01 ARENA GRUESA SELECCIONADA S/. 998.25
19.07.02 PIEDRA CLASIFICADA DE 3/4 - 2 S/. 1,250.85
19.07.03 PIEDRA CLASIFICADA DE 1/4 - 3/4 S/. 312.48
19.07.04 PIEDRA CLASIFICADA DE 1/16 - 1/4 S/. 468.72
20.00.00 MITIGACION AMBIENTAL
20.01.00 MITIGACION AMBIENTAL S/. 563.64 S/. 545.45 S/. 563.64 S/. 563.64 S/. 10,000.01
Total S/. 119,569.88 S/. 116,394.84 S/. 98,430.57 S/. 56,291.81 S/. 6,254,896.05
TotalM15 M16 M17 M18 M19 M20
CRONOGRAMA DE AVANCE FISICO FINANCIERO
Pgina 18