CUADRO 5.3.
Cronograma Valorizado de Avance de Obra - Reprogramado
ENTIDAD : GOBIERNO REGIONAL DE TACNA MODALIDAD : ADMINISTRACION DIRECTA
OBRA : CONSTRUCCION E IMPEMENTACION DE LA I.E. CHACHACOMANI DEL DISTRITO DE TARATA PROVINCIA DE TARATA - TACNA F. INICIO : 03 DE SETIEMBRE 2012
ITEM DESCRIPCION
2012 2013
TOTAL EJECUTADOSETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE
COMPONENTE I: INFRAESTRUCTURA
01 TRABAJOS PRELIMINARES, OBRAS PROVISIONALES, SEGURIDAD Y SALUD, DEMOLICIO S/. 400,045.81 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### S/. 400,045.81
02 COSTRUCCION DE AMBIENTES DE NIVEL INICIAL S/. 128,699.66 ### ### ### ### S/. 128,699.66
03 SERVICIOS HIGIENICOS - INICIAL S/. 27,753.70 5551 5551 5551 5551 5551 S/. 27,753.70
04 COCINA Y S.U.M. - COMEDOR S/. 117,679.34 ### ### ### ### ### ### S/. 117,679.34
05 COSTRUCCION DE AMBIENTES DE NIVEL PRIMARIO S/. 176,331.47 ### ### ### ### ### ### ### ### ### ### ### S/. 176,331.47
06 SERVICIOS HIGIENICOS - PRIMARIA S/. 53,976.71 5398 5398 5398 5398 5398 5398 5398 5398 5398 5398 S/. 53,976.71
07 MEJORAMIENTO Y ACONDICIONAMIENTO DE INFRAESTRUCTURA EXISTENTE S/. 88,383.10 ### ### ### ### ### S/. 88,383.10
08 AREAS VERDES Y JUEGOS S/. 21,473.84 4295 4295 4295 4295 4295 S/. 21,473.84
09 CONSTRUCCION DE PLATAFORMAS Y VIAS DE CIRCULACION S/. 228,126.90 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 9125 S/. 228,126.90
10 CERCO PERIMETRICO S/. 400,203.48 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### S/. 400,203.48
11 INSTALACIONES SANITARIAS S/. 97,540.02 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 4064 S/. 97,540.02
12 INSTALACIONES ELECTRICAS S/. 54,506.11 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 1703 S/. 54,506.11
13 VARIOS S/. 702.64 ### S/. 702.64
COMPONENTE II: MOBILIARIO Y EQUIPAMIENTO
01 MOBILIARIO Y EQUIPAMIENTO S/. 42,002.00 S/. - S/. - S/. - S/. - S/. - S/. 21,001.00 S/. - S/. - S/. - S/. - S/. 21,001.00 S/. - S/. -
COSTO DIRECTO OBRAS CIVILES S/. 1,837,424.78 S/. 116,041.59 S/. 73,245.61 S/. 197,283.77 S/. 143,245.94 S/. 170,515.05 S/. 285,866.01 S/. 217,804.76 S/. 196,373.91 S/. 193,929.75 S/. 140,944.44 S/. 27,814.26 S/. 66,843.78 S/. 7,515.90 S/. 1,837,424.78
GASTOS GENERALES (15.60%) S/. 286,638.27 S/. 18,102.49 S/. 11,426.32 S/. 30,776.27 S/. 22,346.37 S/. 26,600.35 S/. 44,595.10 S/. 33,977.54 S/. 30,634.33 S/. 30,253.04 S/. 21,987.33 S/. 4,339.03 S/. 10,427.63 S/. 1,172.48 S/. 286,638.27
PRESUPUESTO TOTAL ASIGNADO (CD+GG) S/.= 2,124,063.04 134,144.07 84,671.93 228,060.04 165,592.31 197,115.40 330,461.11 251,782.30 227,008.24 224,182.79 162,931.77 32,153.29 77,271.42 8,688.38 2,124,063.04
PROCENTAJE DE AVANCE MENSUAL REPROGRAMADO (%) = 100.00% 6.32% 3.99% 10.74% 7.80% 9.28% 15.56% 11.85% 10.69% 10.55% 7.67% 1.51% 3.64% 0.41% 100.00%
PORCCENTAJE DE AVANCE ACUMULADO (%) = 6.32% 10.30% 21.04% 28.83% 38.11% 53.67% 65.53% 76.21% 86.77% 94.44% 95.95% 99.59% 100.00%
* Fuente de elaboracion según Cronograma Reprogramado de avance de obra reprogramado (ver cuadro 5.1)
EXP. TEC. + ADIC. N°01+02+03+04 DED.
N°01+02+03
CUADRO 5.2.Cronograma Valorizado de Avance Financiero Reprogramado
ENTIDAD : GOBIERNO REGIONAL DE TACNA : ADMINISTRACION DIRECTAOBRA
RESIDENT: ING. HENRY CHIQUE CALDERON : FEBRERO 2015SUPERVIS: ING. ALFREDO CASANOVA VÉLEZ
1,810,826.59 9,378.62 66.71% 0.80%AÑO 2014 AÑO 2014 AÑO 2015
SALDOAÑO 2013 ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIMBRE OCTUBRE NOVIEMBRE DICIEMBRE JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE
programado (S/.) 24,517.59 68,107.00 263,973.00 159,068.00 179,094.00 360,866.00 132,658.00 285,743.00 207,391.00 10,620.00 10,119.00 17,290.00 91,380.00 5,163.80 14,546.80 67,256.00 44,540.00 664,021.28 107,946.81 2,714,301.28 18,900.19programado (%) 0.90% 2.51% 9.73% 5.86% 6.60% 13.29% 4.89% 10.53% 7.64% 0.39% 0.37% 0.64% 3.37% 0.19% 0.54% 2.48% 1.64% 24.46% 3.98% 100% 0.00%Ejecutado (S/.) 24,517.59 68,107.00 263,973.00 159,068.00 179,094.00 360,866.00 132,658.00 285,743.00 207,391.00 10,620.00 10,119.00 17,290.00 91,380.00 5,163.80 14,546.80 67,156.00 44,540.00 664,021.59 146,847.19 2,753,101.97 0.00Ejecutado (%) 0.90% 2.51% 9.73% 5.86% 6.60% 13.29% 4.89% 10.53% 7.64% 0.39% 0.37% 0.64% 3.37% 0.19% 0.54% 2.47% 1.64% 24.46% 5.41% 101% 0.00%
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.00 0.00 -0.31 -38,900.38 -38,800.69AÑO 2014 AÑO 2015
SALDOAÑO 2013 ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIMBRE OCTUBRE NOVIEMBRE DICIEMBRE JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE NOVIEMBRE
programado (S/.) 24,517.59 68,107.00 47,301.00 160,557.00 362,935.00 100,654.00 396,917.00 258,917.00 151,244.00 53,449.00 19,019.00 74,730.00 92,480.00 5,163.80 14,546.80 67,256.00 44,540.00 764,021.28 46,846.00 2,753,201.47 -20,000.00programado (%.) 0.89% 2.47% 1.72% 5.83% 13.18% 3.66% 14.42% 9.40% 5.49% 1.94% 0.69% 2.71% 3.36% 0.19% 0.54% 2.48% 1.64% 28.15% 1.73% 100% 0.00%Ejecutado (S/.) 24,517.59 68,107.00 47,301.00 160,557.00 362,935.00 100,654.00 396,917.00 258,917.00 151,244.00 53,449.00 19,019.00 74,730.00 92,480.00 5,163.80 14,546.80 67,256.00 44,540.00 764,021.28 46,846.00 2,753,201.47 0.00Ejecutado (%) 0.89% 2.47% 1.72% 5.83% 13.18% 3.66% 14.42% 9.40% 5.49% 1.94% 0.69% 2.71% 3.36% 0.19% 0.54% 2.48% 1.64% 28.15% 1.73% 100% 0.00%
: MEJ. CAMINO VECIN. PRINCIPAL DESDE LA ASOC. VIV. PROTER SAMA PROG. 0+00 - 04+770 Y PROG. 08+00 - 10+050 EN EL SECTOR PROTER DEL DISTRITO INCLAN EN EL SECTOR PROTER DEL DISTRITO INCLAN - TACNA
FINANCIERO COMPROMISOS
TOTAL PRESUPUESTO
ASIGNADO
FINANCIERO DEVENGADO
TOTAL PRESUPUESTO
ASIGNADO
CUADRO 5.3.
Curva "S" de Avance Fisico y Financiero
ENTIDAD : GOBIERNO REGIONAL DE TACNA MODALIDAD : ADMINISTRACION DIRECTA
OBRAF. DE INICIO : 01 OCTUBRE
RESIDENTE : ING. HENRY CHIQUE CALDERON FECHA : NOVIEMBRE 2014SUPERVISOR : ING. ALFREDO CASANOVA VÉLEZ
RESUMEN DE EJECUCION FISICA
AÑO MESFISICO VALORIZADO PROGRAMADO FISICO VALORIZADO EJECUTADO
PARCIAL ACUMULADO % PARCIAL % ACUMULADO PARCIAL ACUMULADO % PARCIAL % ACUMULADO
2013 AÑO 2013 0 0 0
2014
ENERO 0 0 0
FEBRERO S/. 151,080.81 S/. 151,080.81 5.53% 5.53% 151080.81 151080.81 5.53% 5.53%MARZO 350,799.45 501,880.26 12.83% 18.36% 350,799.45 501,880.26 12.83% 18.36%ABRIL 124,489.33 626,369.59 4.55% 22.92% 124,489.33 626,369.59 4.55% 22.92%MAYO 144,948.92 771,318.51 5.30% 28.22% 144,948.92 771,318.51 5.30% 28.22%JUNIO 24,639.70 795,958.21 0.90% 29.12% 24,639.70 795,958.21 0.90% 29.12%JULIO 546.77 796,504.98 0.02% 29.14% 546.77 796,504.98 0.02% 29.14%
AGOSTO 0.00 796,504.98 0.00% 29.14% 0.00 796,504.98 0.00% 29.14%SEPTIEMBRE 0.00 796,504.98 0.00% 29.14% 0.00 796,504.98 0.00% 29.14%
OCTUBRE 0.00 796,504.98 0.00% 29.14% 0.00 796,504.98 0.00% 29.14%NOVIEMBRE 0.00 796,504.98 0.00% 29.14% 0.00 796,504.98 0.00% 29.14%DICIEMBRE 989,423.76 1,785,928.74 36.20% 65.34% 48,253.20 844,758.18 1.77% 30.91%
2015
JUNIO 0.00 1,785,928.74 0.00% 65.34% 0.00 844,758.18 0.00% 30.91%JULIO 0.00 1,785,928.74 0.00% 65.34% 0.00 844,758.18 0.00% 30.91%
AGOSTO 0.00 1,785,928.74 0.00% 65.34% 0.00 844,758.18 0.00% 30.91%SEPTIMBRE 63,315.19 1,849,243.93 2.32% 67.66% 0.00 844,758.18 0.00% 30.91%OCTUBRE 883,958.04 2,733,201.97 32.34% 100.00% 0.00 844,758.18 0.00% 30.91%
NOVIEMBRE 0.00 0.00% 100.00% 0.00% 30.91%
S/. 2,733,201.97 S/. -0.00 100.00% 0.00% S/. 844,758.18 30.91%
S/. 2,733,201.97
RESUMEN DE EJECUCION FINANCIERA (PRESUPUESTO ANALITICO)
AÑO MESFINAN. VALORIZADO PROGRAMADO FINAN. VALORIZADO EJECUTADO - DEVENGADO
PARCIAL ACUMULADO % PARCIAL % ACUMULADO PARCIAL ACUMULADO % PARCIAL % ACUMULADO
2013 AÑO 2013 24,517.59 24,517.59 0.90% 0.90% 24,517.59 24,517.59 0.89% 0.89%
2014
ENERO 68,107.00 92,624.59 2.51% 3.41% 68,107.00 92,624.59 2.47% 3.36%FEBRERO 263,973.00 356,597.59 9.73% 13.14% 47,301.00 139,925.59 1.72% 5.08%
MARZO 159,068.00 515,665.59 5.86% 19.00% 160,557.00 300,482.59 5.83% 10.91%ABRIL 179,094.00 694,759.59 6.60% 25.60% 362,935.00 663,417.59 13.18% 24.10%MAYO 360,866.00 1,055,625.59 13.29% 38.89% 100,654.00 764,071.59 3.66% 27.75%JUNIO 132,658.00 1,188,283.59 4.89% 43.78% 396,917.00 1,160,988.59 14.42% 42.17%JULIO 285,743.00 1,474,026.59 10.53% 54.31% 258,917.00 1,419,905.59 9.40% 51.57%
AGOSTO 207,391.00 1,681,417.59 7.64% 61.95% 151,244.00 1,571,149.59 5.49% 57.07%SEPTIEMBRE 10,620.00 1,692,037.59 0.39% 62.34% 53,449.00 1,624,598.59 1.94% 59.01%
OCTUBRE 10,119.00 1,702,156.59 0.37% 62.71% 19,019.00 1,643,617.59 0.69% 59.70%NOVIEMBRE 17,290.00 1,719,446.59 0.64% 63.35% 74,730.00 1,718,347.59 2.71% 62.41%DICIEMBRE 91,380.00 1,810,826.59 3.37% 66.71% 92,480.00 1,810,827.59 3.36% 65.77%
2015
JUNIO 5,163.80 1,815,990.39 0.19% 66.90% 5,163.80 1,815,991.39 0.19% 65.96%JULIO 14,546.80 1,830,537.19 0.54% 67.44% 14,546.80 1,830,538.19 0.54% 66.50%
AGOSTO 67,256.00 1,897,793.19 2.48% 69.92% 67,256.00 1,897,794.19 2.48% 68.98%SEPTIMBRE 44,540.00 1,942,333.19 1.64% 71.56% 44,540.00 1,942,334.19 1.64% 70.62%OCTUBRE 664,021.28 2,606,354.47 24.46% 96.02% 764,021.28 2,706,355.47 28.15% 98.76%
NOVIEMBRE 107,946.81 2,714,301.28 3.98% 100% 46,846.00 2,753,201.47 1.73% 100%
S/. 2,714,301.28 -18,900.69 100.00% S/. 2,753,201.47 100.49%
: MEJ. CAMINO VECIN. PRINCIPAL DESDE LA ASOC. VIV. PROTER SAMA PROG. 0+00 - 04+770 Y PROG. 08+00 - 10+050 EN EL SECTOR PROTER DEL DISTRITO INCLAN - TACNA - TACNA
TOTAL PRESUPUESTO ASIGNADO (CD+GG+MONT.)
TOTAL PRESUPUESTO ASIGNADO
AÑO 2013
ENERO FEBRERO
MARZO
ABRIL MAYO JUNIO JULIO AGOSTO
SEP-TIEM-BRE
OC-TUBRE
NOVIEMBRE
DI-CIEM-BRE
JUNIO JULIO AGOSTO
SEP-TIM-BRE
OC-TUBRE
NOVIEMBRE
FISICO VALORIZADO PROGRAMADO
0 0 5.53% 18.36%
22.92%
28.22%
29.12%
29.14%
29.14%
29.14%
29.14%
29.14%
65.34%
65.34%
65.34%
65.34%
67.66%
100.00%
100.00%
FISICO VALORIZADO EJECUTADO
0 0 5.53% 18.36%
22.92%
28.22%
29.12%
29.14%
29.14%
29.14%
29.14%
29.14%
30.91%
30.91%
30.91%
30.91%
30.91%
30.91%
30.91%
FINAN. VALORIZADO PROGRAMADO
0.90% 3.41% 13.14%
19.00%
25.60%
38.89%
43.78%
54.31%
61.95%
62.34%
62.71%
63.35%
66.71%
66.90%
67.44%
69.92%
71.56%
96.02%
100%
FINAN. VALORIZADO EJECUTADO - DEVENGADO
0.89% 3.36% 5.08% 10.91%
24.10%
27.75%
42.17%
51.57%
57.07%
59.01%
59.70%
62.41%
65.77%
65.96%
66.50%
68.98%
70.62%
98.76%
100%
0.05
0.15
0.25
0.35
0.45
0.55
0.65
0.75
0.85
0.95
1.05
GRAFICO - Curva de Control "S"
FISICO VALORIZADO PROGRAMADO
FISICO VALORIZADO EJECUTADO
FINAN. VALORIZADO PROGRAMADO
FINAN. VALORIZADO EJECUTADO - DEVENGADO
Meses valorizados
% d
e A
va
nce
s A
cu
mu
la
do
s
AÑO 2013
ENERO FEBRERO
MARZO
ABRIL MAYO JUNIO JULIO AGOSTO
SEP-TIEM-BRE
OC-TUBRE
NOVIEMBRE
DI-CIEM-BRE
JUNIO JULIO AGOSTO
SEP-TIM-BRE
OC-TUBRE
NOVIEMBRE
FISICO VALORIZADO PROGRAMADO
0 0 5.53% 18.36%
22.92%
28.22%
29.12%
29.14%
29.14%
29.14%
29.14%
29.14%
65.34%
65.34%
65.34%
65.34%
67.66%
100.00%
100.00%
FISICO VALORIZADO EJECUTADO
0 0 5.53% 18.36%
22.92%
28.22%
29.12%
29.14%
29.14%
29.14%
29.14%
29.14%
30.91%
30.91%
30.91%
30.91%
30.91%
30.91%
30.91%
FINAN. VALORIZADO PROGRAMADO
0.90% 3.41% 13.14%
19.00%
25.60%
38.89%
43.78%
54.31%
61.95%
62.34%
62.71%
63.35%
66.71%
66.90%
67.44%
69.92%
71.56%
96.02%
100%
FINAN. VALORIZADO EJECUTADO - DEVENGADO
0.89% 3.36% 5.08% 10.91%
24.10%
27.75%
42.17%
51.57%
57.07%
59.01%
59.70%
62.41%
65.77%
65.96%
66.50%
68.98%
70.62%
98.76%
100%
0.05
0.15
0.25
0.35
0.45
0.55
0.65
0.75
0.85
0.95
1.05
GRAFICO - Curva de Control "S"
FISICO VALORIZADO PROGRAMADO
FISICO VALORIZADO EJECUTADO
FINAN. VALORIZADO PROGRAMADO
FINAN. VALORIZADO EJECUTADO - DEVENGADO
Meses valorizados
% d
e A
va
nce
s A
cu
mu
la
do
s
Resumen del Cronograma reprogramado Valorizado del Proyecto - cuadro 5.1Obra : TACNA - TACNA
Entidad : GOBIERNO REGIONAL DE TACNA
Ubicacion: TACNA - TACNA -TACNA
AÑO 2014 AÑO 2015
ITEM DESCRIPCIÓN - PARTIDA COSTO FEBRERO MARZO ABRIL MAYO JUNIO JULIO DICIEMBRE SETIEMBRE OCTUBRE
1 OBRAS PROVISIONALES Y TRABAJOS PRELIMINAR S/. 35,664.36 S/. 11,637.09 32.63% S/. 20,947.93 58.74% S/. 1,905.31 16.37% S/. 963.50 2.70% S/. 210.52 0.59%2 INSTALACIONES PROVISIONALES S/. 3,504.69 S/. 494.43 14.11% S/. 2,539.84 72.47% S/. 470.42 13.42%3 TRAZO NIVELES Y REPLANTEO S/. 13,403.07 S/. 7,330.89 54.70% S/. 1,379.53 10.29% S/. 554.07 7.56% S/. 848.07 6.33%4 SEGURIDAD Y SALUD S/. 22,938.56 S/. 15,807.13 68.91% S/. 2,870.00 12.51% S/. 2,600.00 11.33% S/. 1,530.00 6.67% S/. 131.43 0.57%5 MOVIMIENTO TIERRAS CON MAQUINARIA S/. 304,589.91 S/. 97,029.94 31.86% S/. 73,932.77 24.27% S/. 133,627.20 43.87%6 PAVIMENTOS S/. 1,683,592.82 S/. 205,520.39 12.21% S/. 98,115.87 5.83% S/. 104,928.11 6.23% S/. 3,128.40 0.19% S/. 478.80 0.03% S/. 42,080.34 2.50% 577,257.70 34.29% 796,958.20 47.34%7 SEÑALIZACION Y SEGURIDAD VIAL S/. 68,913.698 ELIMINACION DE MATERIAL EXCEDENTE PROVEN S/. 0.00 -S/. 36,964.529 MATERIAL BASE PROVENIENTE DE CANTERA S/. 115,352.65 S/. 5,368.00 4.65% S/. 17,208.39 14.92% S/. 92,776.26 80.43%
10 MATERIAL BASE PROPIO S/. 3,938.44 S/. 2,299.86 58.40% S/. 1,638.58 41.60%11 CONFORMACION DE RASANTE S/. 105,824.58 16467.73 15.56% S/. 89,356.85 84.44%12 MATERIAL AFRIMADO PROVENIENTE DE CANTERA P/ S/. 9,691.9713 OBRAS DE MITIGACION AMBIENTAL S/. 26,014.28
COMPONENTE 001: INFRAESTRUCTURA S/. 2,393,429.02 S/. 132,299.48 5.53% S/. 307,190.46 12.83% S/. 109,013.67 4.55% S/. 126,929.86 5.30% S/. 21,576.66 0.90% S/. 478.80 0.02% S/. 42,080.34 1.76% 856,901.56 35.80% 796,958.20 33.30%
S/. 739,569.27 30.90% 100.00%
COSTO DIRECTO S/. 2,393,429.02 S/. 132,299.48 5.53% S/. 307,190.46 12.83% S/. 109,013.67 4.55% S/. 126,929.86 5.30% S/. 21,576.66 0.90% S/. 478.80 0.02% S/. 42,080.34 1.76% 856,901.56 35.80% 796,958.20 33.30%
GASTOS GENERALES S/. 339,772.95 18781.33 5.53% 43608.99 12.83% S/. 15,475.66 4.55% S/. 18,019.06 5.30% S/. 3,063.04 0.90% S/. 67.97 0.02% S/. 6,172.86 1.82% 121,447.24 35.74% 113,136.79 33.30%
COMPONENTE 002: MONITOREO ARQUELOGICO
PORCENTAJE DE AVANCE PARCIAL S/. 2,733,201.97 S/. 151,080.81 5.53% S/. 350,799.45 12.83% S/. 124,489.33 4.55% S/. 144,948.92 5.30% S/. 24,639.70 0.90% S/. 546.77 0.02% S/. 48,253.20 1.77% 978,348.80 35.79% 910,094.99 33.30%S/. 844,758.18
PORCENTAJE DE AVANCE ACUMULADO 5.53% 18.36% 22.92% 28.22% 29.12% 29.14% 30.91% 66.70% 100.00%
Plazo de ejecucion del Proyecto (comp 01 + comp 02 + comp 03): 151 DIAS CALENDARIO
MEJORAMIENTO DEL SERVICIO DE EDUCACION INICIAL DE LA I.E.I. 433 SANTA TERESITA EN LA ASOCIACION DE VIVIENDA PROTER SAMA - DISTRITO INCLANA
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
COSTO(S/.)
PORCENTAJE(%)
5.43% 6.70%14.63% 18.05%19.11% 23.57%24.33% 30.00%25.21% 31.09%25.23% 31.11%25.25% 31.12%60.78%
100.00%
0.88% 0.88% 0.88%2.43% 3.31% 3.31%9.43% 12.74% 5.00%5.68% 18.42% 10.73%6.40% 24.82% 23.70%
12.89% 37.70% 27.29%4.74% 42.44% 41.47%
10.21% 52.65% 50.72%7.41% 60.06% 56.12%0.38% 60.44% 58.03%0.36% 60.80% 58.71%0.62% 61.42% 61.38%3.26% 64.68% 64.68%0.30% 64.98% 64.68%1.86% 66.84% 66.84%
27.89% 94.73% 94.73%5.27% 100.00% 100.00%
0.88% 0.88%2.43% 3.31%1.69% 5.00%5.73% 10.73%
12.96% 23.70%3.60% 27.29%
14.18% 41.47%9.25% 50.72%5.40% 56.12%1.91% 58.03%0.68% 58.71%2.67% 61.38%3.30% 64.68%0.00% 64.68%2.16% 66.84%
27.89% 94.73%5.27% 100.00%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 170.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Chart Title
Column C Column DColumn E
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 170.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Chart Title
Column C Column DColumn E