CONTROL DE PROYECTOS CON GRÁFICA DE GANTT

PROYECTO

TAREA DURACION INICIOTAREA A 1 11-11-15TAREA B 2 13-11-15TAREA C 5 15-11-15TAREA D 7 20-11-15TAREA E 3 21-11-15TAREA F 6 21-11-15TAREA G 14 27-11-15TAREA H 7 27-11-15

CASA UNIFAMILIAR: TRABAJOS PRELIMINARES

Page 2: Grafica de Gantt
Page 3: Grafica de Gantt

CONTROL DE PROYECTOS CON GRÁFICA DE GANTT

FIN DESCRIPCION12-11-15 A= LIMPIEZA DEL TERRENO15-11-15 B= TRAZO Y NIVELACION20-11-15 C= EXCAVACION27-11-15 D= PLANTILLA24-11-15 E= CIMBRA EN CIMENTACION

27-11-15 F= ACERO DE REFUERZO EN LA CIMENTACION

11-12-15 G= COLADO DE LA CIMENTACION

04-12-15 H= ACERO EN CADENA DE DESPLANTE

CASA UNIFAMILIAR: TRABAJOS PRELIMINARES

Page 4: Grafica de Gantt
Page 5: Grafica de Gantt

PLANNING

Page 6: Grafica de Gantt

PLANNING