Upload
israel-lopez
View
530
Download
0
Embed Size (px)
Citation preview
Proyecto: Fecha Inicio: Fecha Fin: Nmero de das: Horas del Proyecto (BAC): Horas Presupuestadas del Proyecto (BAC):
6/23/2008 7/31/200838
350 79,250.00
Semana
Fecha
PV
Datos a introducir EV
AC
Indicadores SPI CPI
1 2 3 4 5
6/30/2008 7/7/2008 7/14/2008 7/21/2008 7/28/2008
7,500.00 11,250.00 21,250.00 40,250.00 79,250.00
3,750.00 10,000.00 19,000.00 39,000.00 75,000.00
7,500.00 12,000.00 26,000.00 47,000.00 80,000.00
0.50 0.89 0.89 0.97 0.95
0.50 0.83 0.73 0.83 0.94
50,000.00
10,000.00 EV PV AC
20,000.00
30,000.00
40,000.00
60,000.00
70,000.00
80,000.00
90,000.00
0.00 6/30/20087/2/2008
7/4/2008 7/6/2008 7/8/2008 7/10/2008 7/12/2008 7/14/2008 7/16/20087/18/2008
7/20/2008 7/22/2008 7/24/2008 7/26/20087/28/2008