Upload
katie-myers
View
222
Download
0
Embed Size (px)
Citation preview
JOINT OPERATING AGREEMENTS: WHICH ISSUES ARE
LIKELY TO BE THE MOST SENSITIVE TO THE PARTIES
AND HOW CAN A GOOD CONTRACT DESIGN LIMIT THE
DAMAGE FROM SUCH DISPUTES?
Nkaepe Etteh
ABSTRACT: As with most contractual arrangements, there is scope for disputes to arise
between the parties to a JOA. This Paper examines the issues which are most sensitive to the parties
that could result in disputes. It will also discuss how damage arising from disputes involving these
issues may be limited by a well drafted contract. Tackling these issues through good contract drafting
will greatly limit the scope for disputes to arise later on between the parties of a JV.
The author is an LLM Petroleum Law and Policy candidate at the CEPMLP with an LLB (Hons) in
Law from Kings College, London. She is also a UK qualified lawyer affiliated with the Association of
International Petroleum Negotiators, The Energy Institute, The Society of Petroleum Engineers, The
Law Society and the Young International Arbitration Group.
ii
TABLE OF CONTENTS
ABBREVIATIONS ............................................................................................. iii
1 INTRODUCTION ................................................................................................. 1
2 JOINT OPERATING AGREEMENTS .............................................................. 1
2.1 What Is a Joint Operating Agreement ............................................................. 1
2.2 Functions of a Joint Operating Agreement ..................................................... 2
3 THE PARTIES TO A JOINT OPERATING AGREEMENT .......................... 2
3.1 The Operator ................................................................................................... 3
3.2 The Non-Operators .......................................................................................... 4
4 ISSUES MOST SENSITIVE TO THE PARTIES AND CONTRACTUAL
SOLUTIONS ......................................................................................................... 4
4.1 CONTROL AND DECISION MAKING ....................................................... 5
4.1.1 Joint Operating Committee .......................................................................... 5
4.1.2 Voting Procedure ......................................................................................... 6
4.1.3 Approval of Programmes, Budgets and Expenditure .................................. 6
4.2 ISSUES RELATING TO JOINT-OPERATION ............................................ 7
4.2.1 Sole Risk ...................................................................................................... 7
4.2.2 Non-Consent ................................................................................................ 8
4.3 ISSUES RELATING TO DEFAULT ............................................................. 8
4.3.1 Suspension of Rights ................................................................................... 9
4.3.2 Forfeiture ................................................................................................... 10
4.3.3 Buying Out the Defaulting Party‟s Interest ............................................... 11
4.3.4 Security For Decommissioning Costs ....................................................... 11
5 CONCLUSION .................................................................................................... 12
BIBLIOGRAPHY
iii
ABBREVIATIONS
AFE Approval for Expenditure
AAPL JOA the American Association of Petroleum Landmen Form 610
model form operating agreement 1989
AIPN JOA the Association of International Petroleum Negotiators model
form international operating agreement 2002
CAPL JOA the Canadian Association of Petroleum Landmen operating
procedure 2007
DCPD Decommissioning Cost Provision Deed
HC Host Country
JOA Joint Operating Agreement
JOC Joint Operating Committee
JV Joint Venture
OGUK JOA the Oil and Gas UK standard joint-operating agreement 2007
PI Percentage Interest
PL Production Licence
UK United Kingdom
US United States of America
1
1 INTRODUCTION
“If the Joint Operating Agreement forms an alliance similar to a marriage, it is likely
to have 16 parties: four richer, four poor, four better and four worse. Operating
Committee meetings are likely to be more like a nightmare than a honeymoon.” 1
The
JOA is one of the most frequently used agreements in Oil and Gas law. The parties
enter the contract to conduct joint-operations. They bring with them their different
ideas of how the operations will be conducted. The JOA must provide a set of rules
which will govern the parties for the duration of the JV. These rules must last a very
long time and apply to a vast range of activities.2 The design of the JOA must
therefore address issues that are most sensitive to the parties and which can lead to
disputes which threaten the stability and longevity of the JV. The question posed in
this Paper „Which issues are likely to be the most sensitive to the parties and how can
a good contract design limit the damage from such disputes?‟ is very important as
JOAs are necessary and fundamental to the Oil and Gas industry. If potentially
contentious issues are not addressed at the outset, disputes arising later on could prove
disruptive and may lead to termination of the joint-operations. The author will adopt a
comparative methodology in writing this Paper. The paper commences by describing
the nature and purpose of a JOA. Chapter three will discuss the parties to a JOA. The
fourth Chapter discusses the issues that are most sensitive to the parties to a JOA and
goes on to highlight how modern JOAs have the addressed these issues. The author
concludes in Chapter five.
2 JOINT OPERATING AGREEMENTS
2.1 What Is a Joint Operating Agreement
The basic agreement for a petroleum JV is the JOA. The JOA is usually negotiated
following the award of a PL to joint licensees. The JOA performs the same role as a
partnership agreement or a memorandum and articles of association of a company.3 A
JOA is a contract between two or more parties creating a contractual framework for a
JV between them under which they will conduct petroleum operations. The JOA sets
out the structure of the JV, the allocation of risks and costs and the method for sharing
1 Martyn, D. Upstream Oil and Gas Agreements (1996) at 13
2 Ibid.
3 Taylor, M. and Tyne, S., Taylor and Winsor on Joint Operating Agreements (1992) at xix
2
production and profit.4 Petroleum operations are hardly ever conducted by a single
party. This is because the risk, expense and investment required for such operations
are too great for one company to shoulder alone. Oil exploration is a capital intensive
and risky enterprise with heavy upfront costs albeit one which offers high rewards to
successful parties.5 By entering into a JV oil companies can mitigate these high risks
and share in the costs required for capital intensive exploration, development and
production activities. The JV will also enable cost savings and economies of scale.
The operations can be handled with fewer employees and equipment thereby
promoting greater efficiency.6
2.2 Functions of a Joint Operating Agreement
The JOA serves two main functions:
1) A basis for the sharing of rights and liabilities under the PL. Usually this is
allocated according to each party‟s PI under the JOA. The declaration of PI is
one of the essential provisions in a JOA. All rights and liabilities arising in
connection with the PL will be shared between the licensees in proportion to
their PIs
2) To provide a set of rules for the conduct of operations under the PL. Operation
involves designating one of the licensees as operator for the responsible for
conducting the day-to-day operations subject to the supervision of a JOC
which is representative of all licensees.
The JOA will also deal with important ancillary matters such as default by licensees
in meeting their obligations under the JOA and assignment of interests in a JOA.7
3 THE PARTIES TO A JOINT OPERATING AGREEMENT
There are two classes of party to a JOA. The operator and the non-operators. The
operator is the party who implements the collective will of the JV and is responsible
for day-to-day management of the operations. The other members are known as non-
4 Blinn, K. et al., International Petroleum Exploration and Exploitation Agreements (1986) at 193
5 Oil and Gas Law – Current Practice and Emerging Trends (Greg Gordon et al. eds., 2007) at 265
6 Ibid.
7 Taylor, M. and Tyne, S., Taylor and Winsor on Joint Operating Agreements (1992) at xxiii
3
operators. The „institutional link‟ between the operator and the non-operators is the
JOC on which all the parties to the JOA sit.8
3.1 The Operator
There is usually a single operator and his identity is usually specified in the JOA.9 In
most international JOAs the operator is the party with the largest interest in the PL. It
is usually considered imperative by the parties to a JOA that the operator should have
a substantial PI in the PL. This is because a party with a less substantial interest may
not be willing to commit limited technical resources to the project. Further the non-
operators may doubt the operator‟s commitment to the project and fear that its
motivation arises from a desire to make a profit from its position. As a result the
companies in the JV will expect that the operator is financially sound and technically
capable to carry out the operations. In some countries, the operator‟s appointment
must also be approved by the state agency in charge of overseeing petroleum
operations.10
Usually the operator will not receive remuneration for acting as the operator but will
be entitled to reimbursement of its costs. A fundamental feature of the JOA is that the
operator works gratuitously on behalf of the JV.11
Instead he only takes the profit that
it is entitled to pursuant to its PI. Why then would any member of the JOA choose to
act as an operator? Possibly because of the degree of control that the operator is able
to exert over the project. The reward for being operator is greater power as opposed to
greater profits. The JOA will also contain provisions for the removal of the operator
and his replacement by another party. The operator has the same liabilities as the
other parties to the JOA. When contracting on behalf of the JV, the operator will be
acting as agent for the JV who is the principal. In the case of a typical JOA, the
operator will be simultaneously a joint principal along with other parties to the JOA as
well as acting as agent.12
8 Oil and Gas Law – Current Practice and Emerging Trends (Greg Gordon et al. eds., 2007) at 277
9 Ibid.
10 Taylor, M. and Tyne, S., Taylor and Winsor on Joint Operating Agreements (1992) at 1-3
11 See Greg Gordon et al., supra note 8 at 277-281
12 See Greg Gordon et al., supra note 11
4
The operator will owe a duty of care to the other parties in its capacity as operator. It
is good industry practice to prescribe an objective standard in relation to the duty of
care owed by the operator.13
The standard is usually that the operator will not be liable
for any loss of production or profits or other consequential loss in the absence of gross
negligence and/or willful misconduct.14
3.2 The Non-Operators
The role of the non-operators in the JV is „one of non-operating‟. The most important
duty of a non-operator is to provide a share of the funds whenever there is a cash-call.
However non-operators are active investors and they can have an active say in the
managing of the JV through the JOC. Ultimate responsibility for the management of
the JV is entrusted to the JOC in some JOAs. 15
The JOC is comprised of
representatives of all parties to the JOA. The JOC will supervise and control all
matters related to the joint-operation.16
The JOC arrives at decisions according to a
voting procedure specified in the JOA.17
Voting on the JOC is usually weighted to
reflect each parties PI. The value of any percentage voting right is affected by the
pass-mark laid down in the JOA. The pass-mark is a matter for negotiation between
the parties, dependent on the contractual strength of the parties.18
4 ISSUES MOST SENSITIVE TO THE PARTIES AND CONTRACTUAL
SOLUTIONS
Several complex issues may arise in the context of negotiation a JOA. These issues
may be further aggravated by the financial difficulty currently affecting the world‟s
economy. Operators and non-operators are increasingly demanding that their interests
are adequately protected in the JOA.19
The issues that are most sensitive to the parties
are subjective and non-exhaustive in nature. For the purposes of this paper, the author
has grouped these issues into the following umbrella headings:
13
Daintith, T. and Willoughby, G., Manual of United Kingdom Oil and Gas Law (1984) at 99 14
Philip Weems and Michael Bolton Highlight of Key Revisions – 2002 AIPN Model Form
International Operating Agreement at www.kslaw.com/library/pdf/2002_JOA.pdf at 4 15
See Greg Gordon et al., supra note 12 at 286 16
See Taylor, M. And Tyne, S., supra note 10 at 21 17
See Daintith, T. and Willoughby, G., Supra note 13 at 100 18
See Greg Gordon et al., Supra note 15 19
Howard L Boigon, Joint operating agreement part 1 [1987/88] 11 OGLTR 320
5
4.1 CONTROL AND DECISION MAKING
Oil and gas industry practice is to permit the operator to act on behalf of the JV and to
have full control of day-to day operations within the limits of the JOA. There is need
for a mechanism to control the operator due to the very high costs of operation,
especially off shore. Particularly as JOAs usually exclude any liability on the
operator's part for a failure to act which is anything other than wilful misconduct or
gross negligence,20
and these are particularly difficult to prove.21
Strict and continuing
supervision over the operator‟s activities is necessary and will be a most sensitive
issue .22
If such control is not exerted, the parties to the JOA run the risk of losing
their investment. Such control can be achieved by the following means:
4.1.1 Joint Operating Committee
The principal method of addressing this issue is by making the operator‟s conduct of
the JV subject to the supervision of the JOC. The AIPN JOA provides that the
operator shall “perform Joint-operations in accordance with the provisions of the
Contract, the Laws / Regulations, this Agreement, and the decisions of the Operating
Committee not in conflict with this Agreement.”23
This position is also found in the
OGUK JOA at section 6.1.1.24
However, the operator may prefer to act without the
restriction of JOC supervision. This can be provided for in the JOA. For instance the
AAPL JOA25
provides that the operator has full control of all operations in the
contract area and is not subject to the control of the non-operators. The CAPL JOA26
provides that the operator has freedom to act subject only to the obligation to consult
with the parties and to keep them informed about the joint-operations. Neither of these
JOA‟s refers to a JOC.27
20
Ibid at 321 21
Peter Roberts, Fault lines in Joint Operating Agreements, I.E.L.R 290 (2008) at 3 22
See Daintith, T. and Willoughby, G., Supra note 13 at 100 23
AIPN JOA section 4.2 B(1) 24
See Roberts, P., Supra note 21 at 3 25
AAPL JOA 26
CAPL JOA 3.01A 27
See Roberts, P., Supra note 21 at 2
6
4.1.2 Voting Procedure
As mentioned above, the JOC reaches decisions according to a voting procedure and
the requisite pass-mark specified in the JOA. This is crucial as it determines which of
the parties has the power to veto any proposed activity.28
The party with a large
percentage may seek a high pass-mark so that it can approve or veto any decision.
Parties with smaller interests may seek protection to ensure against the risk of one or
two parties preventing or forcing a cause of action. This issue would be very sensitive
to the parties.29
For example, in the AIPN JOA the voting procedure allows for a
series of alternatives, including a provision that JOC decisions are only validly made
by a pass-mark vote of a certain number of parties.30
The OGUK JOA also provides a
pass-mark voting mechanism,31
together with a list of items in respect of which
unanimous consent is advised. If the operator has the largest percentage share which
meets the threshold of the pass-mark, it can carry the vote. This could make this
provision fail to adequately control the operator. This problem can be avoided by
imposing a requirement for unanimity in respect of certain items in the JOA. However
this could result in deadlock. Most JOAs which provide for the possibility of
unanimity of voting (including the AIPN JOA and the OGUK JOA) do not provide a
meaningful deadlock resolution provision,32
the implication being that the parties
can‟t progress in the JOC until some sort of mutually acceptable position is achieved.
It is possible to not refer JV decisions to a voting procedure. This can be provided for
in the JOA by not conferring control rights on the JOC for example under the AAPL
JOA or under the CAPL JOA.33
4.1.3 Approval of Programmes, Budgets and Expenditure
The operator has authority to execute all approved programmes and budgets. The
approval of such is of utmost importance to the parties in controlling the joint-
operations and their exposure to costs.34
Therefore an effective method of controlling
expenditure is vital. AIPN JOA at 6.7B Alternative 2 and 3 provides for express
approval. The CAPL JOA also has provision that the operator must have an AFE,
28
See Daintith, T. and Willoughby, G., Supra note 13 at 100 29
See Martyn, D., Supra note 1 at 18 30
AIPN JOA 5.9 31
OGUK 9.8 32
See Roberts, P., Supra note 21 33
See Roberts, P., Supra note 21 at 2 34
See Martyn, D., Supra note 1 at 19
7
approved by all the parties, before spending beyond a specified amount can be
incurred in the performance of the joint-operations.35
AIPN JOA 6.7B Alternative 2
allows for approval by conduct where the JOC fails to approve an AFE within the
permitted time period. An operator could side step this mechanism if its PI reaches the
threshold for pass-mark unless the JOA requires unanimity. It may be prudent to
include a similar provision mentioned at Section 4.1.2 above which provides that
pass-mark vote is only attained when a certain number of parties vote in favour.
4.2 ISSUES RELATING TO JOINT-OPERATION
The JOC, voting procedure and pass-mark may not be enough to protect all the
varying interests of the parties. Parties with small PIs may not want to be bound to
activities they do not support or cannot afford. Also, parties with significant interest
may not want to be prevented from developing the particular project36
. In order to
protect these diverging interests, JOA‟s usually permit sole risk and non-consent
operations.
4.2.1 Sole Risk
A sole risk provision allows parties to undertake a project rejected by a majority of
the JOC. The effect of this provision is that all costs and all entitlements to petroleum
from the project costs rest wholly with the sole risk party or parties.37
The clause
recognizes that a project may be considered worthwhile by some of the parties but
may fail to meet pass-mark.38
The AIPN JOA39
provides for what it calls ‘exclusive
operations‟. Under this mechanism, a party can propose an operation (outside of the
agreed joint-operations programme) such that a party may proceed with that exclusive
operation in its own right. The other parties are free to participate or not, as they
prefer. The CAPL JOA40
has a similar provision known as independent operations.
Under this mechanism any party can serve notice upon the other parties of its
intention to conduct a particular operation, whereupon each other party may elect to
participate, or not, in that operation.41
35
CAPL JOA 3.01B 36
Se Martyn, D., Supra note 1 at 22 37
See Daintith, T. and Willoughby, G., Supra note 13 at 106 38
See Martyn, D., Supra note 1 at 23 39
AIPN JOA 7 40
CAPL JOA 10.4 41
See Roberts, P., Supra note 21 at 4
8
4.2.2 Non-Consent
A non-consent clause will provide that no party can be compelled to participate in any
major operation, such as drilling without its consent.42
Where this provision is
invoked the objecting party will be excluded from the particular joint-operation which
will then be undertaken by all of the consenting parties and will be accounted for
separately from the JV.43
Non consent and the sole risk rights represent the possibility that operations can
carried out under the JOA by less than all the parties. However these rights are
incompatible with the intended JOA philosophy which is majority rule. This is
particularly the case with the non-consent right, where the consenting parties are left
with the burden of having to share the particular project costs in proportions which are
greater than the original PIs they had bargained for.44
Therefore such clauses are
controversial.
An operator might be eager to see these rights excluded, or at least greatly limited,
under the JOA. However, a non-consent right is particularly valuable to non-operating
parties in protecting such a party from being forced into an operation which it might
not have the financial ability to pursue.45
4.3 ISSUES RELATING TO DEFAULT
These relate to the long term protection of the parties rights and interests in the JV.
Each JOA is built on the presumption that the burden if financial operations shall be
shared. The operator will issue periodic cash-calls. The most important duty of all
parties to a JOA is to provide funds when they are requested under a cash-call.46
If a
co-venturer breaches its financial obligations, it breaches its most basic duty under the
JOA. Such breach will cause real financial difficulty to the other parties who will
have to make good the shortfall.47
42
See Daintith. T. and Willoughby, G., Supra note 13 at 107 43
See Roberts, P., supra note 21 at 4 44
Ibid. 45
See Roberts, P., supra note 21 at 4 46
Peter Roberts forfeiture 1 47
See Greg Gordon et al., supra note 8 at 289
9
A default situation arises where a party fails to meet its PI share of the expenditure
made on behalf of the JV. When such default occurs one or more of the non-
defaulting parties have to step in the meet the defaulter‟s share of the expenditure.
Provisions should be made in the JOA to protect the operator from having to bear the
burden of funding the default.48
Default is more relevant now as production in the
north-sea matures coupled with the current financial climate. Major operators will be
looking to rid themselves of their less productive assets. This is because there is little
incentive to stay as the PL is no longer an asset but a liability due to impending
decommissioning costs. Where the PL is divested to smaller companies, they are
more likely to go bankrupt than major companies.49
The non-defaulting parties will be
keen to see that default and remediation does not become an established pattern of
behaviour by a party and so the JOA will need to provide a swift and effective
sanction in circumstances of default.50
Default situations can be addressed in the JOA
in the following manner:
4.3.1 Suspension of Rights
The JOA can stipulate that in the event of default some of the defaulting party rights
become suspended. For example, the right to receive information, the right to attend
and vote in the JOC, the right to participate in areas of mutual interest acquisitions or
to receive notices of future well operations. Boigon suggests that legally, it may not
be possible to suspend only some performance while at the same time continuing to
insist on performance of other JOA provisions. As a practical solution, the threat of
selective suspension may prove to be an effective influence against the defaulter51
.
The AIPN JOA provides for a suspension of the aforementioned rights during the
„default period‟.52
If the default is still un-remedied then the ultimate sanction is that
all of the defaulting party's interest in the JV is forfeited to the non-defaulting
parties.53
48
See Daintith. T. and Willoughby, G., Supra note 13 at 103 49
See Greg Gordon et al., supra note 8 at 290 50
Peter Roberts, Fault-lines in the joint operating agreement: forfeiture I.E.L.R. 274 (2008) 2 51
Howard L Boigon, Joint operating agreement part 2 [1987/88] 11 OGLTR 320 at 30 52
AIPN JOA 8.2 53
See Roberts, P., supra note 50.
10
4.3.2 Forfeiture
Forfeiture is basically a forced transfer of the defaulting party's interest. To complete
such a transfer the JOA may also provide that each party irreversibly appoints each
other party as its attorney, for the purpose of concluding such a transfer if the need
arises, rather than having to force the defaulting party to complete the necessary
transfer documents at the time of forfeiture, running the risk of the defaulting party
refusing to do so.54
The AIPN JOA provides an option for forfeiture in the event of
default.55
However such forfeiture may be held to be penal because the amount in
question is “extravagant and unconscionable in amount in comparison with the
greatest loss that could conceivably be proved to have followed from the breach.”56
Roberts suggest that the potential impact of forfeiture can be moderated in the JOA so
as not to constitute a penalty by adopting a „withering interest‟ forfeiture clause.57
Under such a clause the defaulting party‟s interest is decreased in proportion to the
amount by which it is in default. Withering interest clauses are complex to apply and
all they do is to moderate the degree of punishment instead of removing the risk of
penalty.58
Roberts suggests a withering interest formulation is one whereby the
defaulting party can re-acquire the interest which it had forfeited by making good the
amount of the default at a later date. This is attractive for the defaulting party but
unattractive for the non-defaulting parties.59
A further consideration relating to the forfeiture remedy is whether a defaulting party
could claim equitable relief against forfeiture. In practice the risk of a forfeiture clause
being struck down by the courts is small because the only relief which the courts will
be willing to grant is to give the debtor to time to pay his debt. The time period is
arguably provided by most JOAs.60
Another consideration is that such a clause may
be seen to frustrate the operations of insolvency law. In English law especially,
forfeiture may be struck down as an unfair provision which denies an insolvent
defaulting party‟s creditors of their right to share in its assets. There is yet to be a UK
case on the validity of a JOA forfeiture clause. However an Australian court in
54
Ibid. 55
AIPN JOA 8.4(D) Alternative 1 56
Dunlop Pneumatic Tyre Co., Ltd. v. New Garage and Motor, Ltd., [1915] A.C. 79 57
See Roberts, P., supra note 50 at 3 58
See Greg Gordon et al., Supra note 15at 294 59
See Roberts, P., supra note 50 at 3 60
See Greg Gordon et al., Supra note 15 at 298
11
Mosaic Oil NL v Angaari Pty Ltd61
had to consider this particular issue. It was held
that in the event of the defaulting party‟s insolvency, such a forfeiture clause would
not be upheld.62
4.3.3 Buying Out the Defaulting Party’s Interest
Because of the potential problems with the enforceability of forfeiture clauses, the JV
members can completely avoid this issue by including a buy-out alternative in the
JOA. The consideration for such sale would be assessed on the presumption of a fair
market value and with recourse to an independent expert in the event of a dispute
between the parties.63
The AIPN JOA64
includes a buy-out alternative to forfeiture to
allow parties completely ignore forfeiture enforceability issues65
. The CAPL JOA
requires a forced sale of the defaulting party's JOA interest on the open market.66
The
operator is granted a first-ranking lien over each party's interest under the JOA in
order to secure payment by that party of its share of the costs of the joint-operations.
In order to remedy a party's default the operator may take possession of the defaulting
party's interest under the JOA and sell that interest on reasonable commercial terms.
The proceeds of the sale are used to remedy the default and the balance is returned to
the defaulting party. The AAPL JOA67
also has a similar mechanism as an alternative
to forfeiture.68
This sort of clause may be controversial as the non-defaulting parties
may wish to have a say with regard to who buys the defaulting party‟s interest.
4.3.4 Security For Decommissioning Costs
Decommissioning is an issue which is becoming more relevant as existing oil fields
mature. If all the parties to a JOA decide to withdraw they will have to wind up the
JOA in a manner that satisfies the relevant governing laws and regulations.69
Usually
the parties are jointly and severally liable for the costs of decommissioning under the
PL. The parties will be keen to ensure that they bear only that share of
61
(1990) 8 ACLC 780 (NSW Supreme Court) 62
Ibid at 299 63
See Roberts, P., supra note 50 at 3 64
AIPN JOA 8.4(D) Alternative 2 65
See Weems, P. and Bolton, M., supra note 14 at 12 66
CAPL JOA 5.05B(g) 67
AAPL JOA VIIB 68
See Roberts, P., supra note 50 at 4 69
Blinn, W. et al., International Oil and Gas Agreements (2009) at 302
12
decommissioning costs that is proportionate to their PI.70
It is now increasingly
popular for HC laws to require that parties contribute in advance to a
decommissioning fund. This makes decommissioning an important issue for JV
members which if not immediately sensitive to them, should be brought to their
attention during negotiations. No party would want to be saddled with the liability for
decommissioning where the other parties have become bankrupt before the event of
decommissioning.71
To prevent this, most JOAs will authorise several types of security including a
guarantee or a standby letter of credit issued by an accredited bank, an on demand
bond issued by a surety company, a corporate guarantee, or some financial security
agreed on by the parties.72
The AIPN JOA provides an option for „Abandonment
Security‟ which obliges the parties to negotiate a security agreement during the
preparation of the development plan in respect of decommissioning.73
The OGUK
JOA provides for such security by attaching a DCPD to the JOA (ideally to be
executed at the same time as the JOA). The advantage of this is that decommissioning
issues will be dealt with from the outset in the JOA. Clause 3 of the OGUK JOA
confirms that decommissioning is an important part of joint-operations.
5 CONCLUSION
The JOA is indeed one of the most important agreements in the development of oil
and gas resources. In order to answer the question posed by this paper, the paper has
analysed the JOA and the members to a JOA. The JOA is expected to represent an
amalgam of the varying interests of the respective parties to the JOA. As a result it is
not possible to provide a definitive list of issues which are most sensitive to the
parties as such interests and their sensitivity are subjective to the parties. However the
paper provides a detailed analysis of the issues of control and decision making, joint
operations and default which are of great importance to the parties to a JOA. The
consequences of failing to address these issues in the JOA can be detrimental to the
parties and their investment. As a result of comparative analysis of the way these
issues have been addressed by modern JOAs we find that damage as a result of
70
DCPD Guidance at www.oilandgasuk.co.uk/new/events/eventDetail.cfm?frmEventID 71
Peter Cameron Lecture notes 72
See Blinn, W. et al., supra note 69 at 302 73
AIPN JOA 10.3
13
disputes arising from the issue of control and decision making can be limited by
providing for a JOC in the JOA along with a voting procedure and a requirement for
approval of programmes, budgets and expenditure; disputes arising from joint-
operating can be mitigated by providing for sole risk and non-consent operations;
instances of default can be remedied by provisions in the JOA relating to the
suspension of the defaulting party‟s rights, forfeiture of the defaulter‟s PI or
alternatively, buying out of the defaulters PI; and default related to decommissioning
can be avoided by a provision in JOA requiring security for decommissioning costs.
By addressing these issues in the JOA the parties negotiate what is effectively a
blueprint which has the capacity to limit the impact of disputes arising from the
aforementioned issues at a later date.
14
BIBLIOGRAPHY
PRIMARY SOURCES
Judicial Decisions
Dunlop Pneumatic Tyre Co., Ltd. v. New Garage and Motor, Ltd., [1915] A.C. 79
Mosaic Oil NL v Angaari Pty Ltd (1990) 8 ACLC 780 (NSW Supreme Court)
SECONDARY SOURCES
Books
Blinn, W. et al., International Oil and Gas (1986)
Blinn, W. et al., International Oil and Gas Agreements (2009)
Daintith, T. and Willoughby, G., Manual of United Kingdom Oil and Gas Law (1984)
Martyn, D. Upstream Oil and Gas Agreements (1996)
Oil and Gas Law – Current Practice and Emerging Trends (Greg Gordon et al. eds.,
2007)
Taylor, M. and Tyne, S., Taylor and Winsor on Joint Operating Agreements (1992)
Articles
Howard L Boigon, Joint operating agreement part 1 [1987/88] 11 OGLTR 320
Howard L Boigon, Joint operating agreement part 2 [1987/88] 11 OGLTR 320
Martin, P., The Joint Operating Agreement - An Unsettled Relationship? in Vol 50
Institute on Oil and Gas Law and Taxation 91-133 (1999)
OTHERS
Internet Sources
DCPD Guidance at
(www.oilandgasuk.co.uk/new/events/eventDetail.cfm?frmEventID [accessed 12
January 2010])
Peter Roberts., Fault Lines in the Joint Operating Agreement: Decision-Making, at
(https://login.westlaw.co.uk/ [accessed 18 November 2009])
Peter Roberts., Fault-lines in the joint operating agreement: forfeiture I.E.L.R. 274
(2008) (https://login.westlaw.co.uk/ [accessed 18 November 2009])
15
Philip Weems and Michael Bolton Highlight of Key Revisions – 2002 AIPN Model
Form International Operating Agreement at
www.kslaw.com/library/pdf/2002_JOA.pdf
The Association of International Petroleum Negotiators model form international
operating agreement 2002 at
https://my.dundee.ac.uk/webapps/portal/frameset.jsp?tab_tab_group_id=_2_1&url=%
2Fwebapps%2Fblackboard%2Fexecute%2Flauncher%3Ftype%3DCourse%26id%3D
_25521_1%26url%3D (accessed 2 December 2009)