Informe de Capitalización del Proyecto DIPECHO Río Grande (Inglés)

  • Upload
    acf-e

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    1/53

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    2/53

    Table of contens

    Chapter I: Introduction

    Introduction.............................................................................5

    1.1 Objective of the capitalization .........................................5

    1.2 Aim of the capitalization.....................................................5

    1.3 Axis of the capitalization.....................................................6

    1.4 Objective group of the capitalization ................. .......... . 61.5 Mechanisms of compilation of information,

    organization, analysis and synthesis. ......... ......... ......... .. 6

    1.6 Levels of participation .........................................................8

    1.7 Mechanisms of communication.......................................9

    Chapter II: Description of the Project

    2.1 Name of the experience ...................................................10

    2.2 Topic areas of intervention..............................................10

    2.3 Location data........................................................................112.4 Period of de implementation ........................................12

    2.5 Identification of participants involved................. ....... 12

    2.6 Context....................................................................................14

    2.7 Description of the tackled problem................. ......... ... 16

    2.8 Proposal of intervention...................................................17

    2.9 Unexpected achievements and relevant difficulties in

    the implementation ...........................................................18

    Chapter III: Capitalization of Experiences3.1 Introduction to capitalization.........................................25

    3.2 Capitalization........................................................................25

    3

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    3/53

    3.3 Lessons learned ..............................................................................41

    3.4 Testimonies of participants in the DIPECHO Rio Grande

    Project ..............................................................................................43

    Chapter IV: Recommendations

    Recommendations ......................................................................47

    Annex 1: List of systemised products

    4

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    4/53

    5

    Chapter I

    Introduction

    1.1 Objective of the capitalization

    The objective in this document is to recover experiences and

    knowledge through a systematic and analytical reflection, with the

    final purpose of facilitating access to information by groups of

    interest, and contribute thus to the overcoming difficulties in the

    field of preparation for disasters from accumulated experiences by

    DIPECHO Rio Grande Project.

    1.2 Aim of the capitalization

    The purpose of the capitalization are the preparation and

    organization activities facing disasters fostered by different

    participants involved in emergencies caused by the overflowing of

    the Rio Grande in the Department of Santa Cruz (Bolivia). Among

    such local participants the following stand out: Civil Defence,

    Departmental Emergency Operations Centre (Centro de

    Operaciones de Emergencias COED) municipalities, rescue groups,

    health services, and very specially, leaders and community based

    organizations. The activities carried out with them during the

    implementation of the project include training in different topics

    Fifth DIPECHO Action Plan for South America

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    5/53

    6

    Fifth DIPECHO Action Plan for South America

    related to the response to emergencies, strengthening of inter-

    institutional coordination, implementation of mitigation measures,

    and reinforcement of Early Warning Systems (EWS), scientific

    research about hydrological behaviour of the Rio Grande, etc. The

    project had an exceptional duration of 16.5 months, from September

    15, 2007 to January 31, 2009, because of the delays caused by social-

    political problems that affected the area of intervention.

    This document will focus on:

    Innovative aspects of the activities carried out

    New knowledge provided by the execution of the project

    1.3 Axis of the capitalization

    The central axis that regulates this capitalization is the improvement

    of the disaster preparedness by local participants.

    1.4 Objective group of the capitalization

    This document of capitalization is focused on organizations in

    charge of the design and implementation of DIPECHO projects,

    technicians and authorities of the areas exposed to flood risks, as

    well as public in general aware of the search for a better preparation

    of institutions and civil society facing natural disasters.

    1.5 Mechanisms of compilation of information, organization,

    analysis and synthesis.

    This document has been prepared by a consultant and has been

    complemented by the technical team of the DIPECHO Rio Grande

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    6/53

    Fifth DIPECHO Action Plan for South America

    7

    project. The process of capitalization and systematisation (in this

    regard, a DVD has been created with all the generated products),

    was developed between January and March 2009.

    A participative methodology was privileged, allowing the

    compilation of primary and secondary information due to individual

    interviews and focal dialogues with key participants and informants:authorities directly involved in the execution of the project at a

    departmental and municipal level, technical team from Action

    against Hunger. Besides, a documentary review was carried out of

    the different document and tools generated by the project. All

    selected documentation was analysed and tabulated to be socialized

    later toward the people involved and interested in the DIPECHO

    Rio Grande Project.

    The information was processed as it is described below:

    Compilation and analysis of secondary information of the

    project.

    Compilation and analysis of primary information: field

    work, meetings with the technical team of Action against

    Hunger, semi-structured meetings and interviews with

    community leaders, those in charge of Municipal

    Emergency Operation Centres (Centro de Operaciones de

    Emergencias COEM), representatives of the Departmental

    Emergency Operation Centre (COED) and Departmental

    Civil Defence.

    Processing and analysis of information. Besidessystematizing the preceding sources of information, the

    group of documents generated by the project was

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    7/53

    reviewed, such as the

    systematisation of KAP

    surveys, the hydrological

    hydraulic study or even

    t h e s y s t e m a t i s a t i o n

    documents from different

    activities carried out alongthe project.

    Writing of the f inal

    document considering the

    contribution from the

    projects team.

    1.6 Levels of participation

    R e p r e s e n t a t i v e s f r o m

    institutions involved in the

    execution of the project, from

    t h e D e p a r t m e n t a l

    Emergency Operation Centre

    (COED), Departmental

    Delegation of Civil Defence, Municipal Governments in the area of

    influence of the project, Rescue and Search Force of SAR-FAB, as

    well as direct beneficiaries in communities of the area of intervention,

    contributed key information for the execution of this capitalization.

    The process has been led by a consultant together with the projects

    technical team.

    8

    Fifth DIPECHO Action Plan for South America

    Photo 1. Systems of cell phone telephonyinstalled in order to expand the Early WarningSystems coverage in communities of high riskof floods.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    8/53

    9

    Fifth DIPECHO Action Plan for South America

    1.7 Mechanisms of communication

    The diffusion of this document, besides the digital support of all

    the relevant information generated by the project will be sent to

    all DIPECHO associates, those in charge, and participants interested

    and/or involved in the reduction and preparation for disasters.

    Specifically, this document will be sent to the Municipalities andinstitutions that have been part of the action, together with those

    systematised products and materials.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    9/53

    10

    Chapter II

    Description of the Project

    2.1 Name of the experience

    The project is entitled Strengthening of local and departmental

    capability to face the threat of floods in the Lower Basin of the Rio

    Grande, Department of Santa Cruz Bolivia. Simply put, the project

    has been announced among the beneficiary population and

    institutions such as DIPECHO Rio Grande Project.

    2.2 Topic areas of intervention

    The Project intervened in the sub-sectors pre-defined next:

    1. Elements of local management of emergencies:

    Early Warning System (EWS)

    Mapping and data processing

    Creation and training of local capabilities

    2. Institutional links and lobbying:

    Incidence Facilitation of coordination

    Institutional strengthening

    Fifth DIPECHO Action Plan for South America

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    10/53

    Fifth DIPECHO Action Plan for South America

    11

    3. Information, Education and Communication:

    Raising public awareness

    Education

    Divulgation

    4. Works in small infrastructures and services:

    Supporting infrastructure

    Mitigation works

    2.3 Location data

    The project was developed in the Department of Santa Cruz (a

    department in the Bolivian East) in six municipalities located in the

    Lower Basin of the Rio Grande: Pailn, El Puente, Cuatro Caadas,

    San Julin, Okinawa and Saavedra. The work of communal

    strengthening and preparation was carried out in 33 rural

    communities and 2 neighbourhoods in the urban area of the

    Municipality of Pailon.

    Figure 1. Area of intervention of the DIPECHO Project

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    11/53

    12

    Fifth DIPECHO Action Plan for South America

    2.4 Period of implementation

    The project was developed in a period of 16.5 months of duration,

    from September 15, 2007 to January 31, 2009.

    2.5 Identification of participants involved

    A basic premise of the project has been the largest possible

    collaboration and participation with different institutions and local

    participants, each of them in their specialty field, without ACH

    substituting any of them. It is worth mentioning the participation

    of organization such as the Departmental Government of Santa

    Cruz together with the Departmental Emergency Operation Centre

    and its different commissions, the SENAMHI; SEARPI; Municipal

    Governments of Pailn, Cuatro Caadas, San Julin, El Puente,

    Okinawa, Saavedra; the University Gabriel Ren Moreno, the Institute

    of Popular Training (Instituto de Capacitacin Popular ICAP); the

    association of Municipalities of Santa Cruz (AMDECRUZ); the rescue

    and search team of the Air Force SAR FAB and other cooperation

    institutions. Special emphases deserve the thirty five beneficiary

    communities of the project. In the next table, it is offered a global

    vision of the previous participants:

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    12/53

    Fifth DIPECHO Action Plan for South America

    13

    Chart 1. Main participants involved

    S u b -se c to r Ty p e o f ac tiv ity S tatu te D e tailT o t a l n u m b e r o f

    b e n e f ic iar ie s

    Inhabitants of communities withestablished Civil Defence Brigades anddeveloped Contingency Plans

    14.405L o c al m an ag e m e n tof emergencies

    Creation and trainingof local capa bilit ies

    Local population

    M e m b e r s o f t r a in e d an d e q u ip p e d

    Community Civil Defence Brigades

    29 9

    E m e rg e n c y i n fr a st ru c t ur e L o c al p o p ul a ti o n Capability of the improved temporaryshelters,according to SPHERE standards

    3.400Works of smallinfrastructures andservices

    M itig atio n w orks Lo c al po pulatio n Inhabitants of communities benef itedwith the protection of water supply wells

    8 .460

    Institutional linksand lobbying

    Institutional strengthening Local Techniciansand Authorit ies

    Technicians and municipal authorit ies

    trained in COEM operation12 4

    Technicians andLocal Author it ies //NG O

    Technicians and municipal anddepartme ntal authorit ies trained withspecialization courses on RiskM an ag e m e n t

    38

    Local professionalsof Health

    Professional of Health trained onpreparation for disasters in the healthf ield

    40

    Inst itut ional strengthening /Creation (Training) of localcapabilit ies for localinstitutions of RiskM an ag e m e n t

    Local volunteers ofsalvage 36

    Elements of localm an ag e m e n t o f emergencies

    Contingency planningTechnicians and

    Local Authorit ies

    Technicians and representatives of

    institutions30

    Facilitation of coordinationTechnicians andLocal Authorit ies //NG O

    Technicians f rom dif ferent institutionsthat participate in the design of theDepartmental Contingency Plan

    98

    Institutionallinks andlobbying

    Institutional StrengtheningTechnicians andLocal Authorit ies

    Technicians and COED and COEMauthorit ies trained in the use of softwareD e p ar t m e n t al E m e r g e n c y M an ag e m e n tSystem (SIGED)

    29

    Technicians andLocal Authorit ies //NG O

    Technicians f rom dif ferent institutionsthat participate in DIPECHOpresentation and DIRD commemoration

    50Information,education,c o m m u n ic at io n

    Public awareness

    Lo c al po pulatio n Par ticip ants of D IR D events 250

    Research and socialization

    Others M ap p in g an d dat aprocessing

    Technicians andLocal Authorit ies //NGO // Localpopulation

    Technicians f rom public institutions,authorit ies and decision makers ingeneral f rom the Lower Bas in of the

    Rio G r an de10 0

    Creation and training of local capabilit ies

    Technicians andLocal Authorit ies //NG O

    Technicians f rom institutionsparticipating in training on mea suring

    e q u ip m e n t m an ag e m e n t

    20

    Elements of localm an ag e m e n t o f emergencies

    Early Alert System (SAT)Technicians and

    Local Authorit ies

    Technicians f rom institutionsparticipating in SAT diagnosisworkshops and its dinamization

    30

    Volunteers f rom salvage and helpteams trained on rescue techniquesand equipped

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    13/53

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    14/53

    Fifth DIPECHO Action Plan for South America

    15

    In this environment of high exposure to natural disasters (partially

    flooded in five occasions, since 1996), thousand of families coming

    from the Andean Bolivian Highlands and Valleys have settled down

    here. This process of colonization of tropical lands has been part of

    one of the strategic axis of long term development in the Bolivian

    Republic for three decades, based on offering an alternative to the

    dominantly rural population from the West of the country, wherethe agricultural and climatic conditions are very unfavourable and

    the demographic growth has downsized family farms to a size under

    the limits of subsistence.

    Despite the initial planning effort, many families and communities

    of the colonization have not improved their living conditions over

    the years. The deterioration of the situations is favouring the gradual

    substitution of these colonies by large properties dedicated to the

    mechanized farming of oilseeds (soybean, sunflower, rape). The

    floods, stimulated by the progress of the agricultural border up to

    the very river bank, has also contributed to the fleeing from thecommunities and internal emigration from its old inhabitants, toward

    the latter areas still with forests in the region, or toward the urban

    peripheries of the main cities in the Department of Santa Cruz.

    During the last decade, almost every year, the Lower Basin of the

    Rio Grande (Department of Santa Cruz) has been affected by

    catastrophic floods. These events have been especially intense in

    2006, 2007 and 2008. The threat of overflowing and floods caused

    by the Rio Grande worsen every year, in an area that has gone

    through a quick demographic growth and where more than 70%

    of the population lives in poverty conditions3.

    - 3 National Institute of Statistics (INE, Department Statistics of Bolivia,2005

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    15/53

    16

    Fifth DIPECHO Action Plan for South America

    2.7 Description of the tackled problem

    According to the Study Hydrologic Hydraulic of the Rio Grande4

    carried out in the framework of the DIPECHO Project, its Lower Basin

    has a very scarce slope, is subjected to important yearly rainfall

    (1,400 mm), and a high phreatic stratum, which as a group, causes

    the communities settled over it, suffer permanent floods, with lossof lives, goods and crops. During rainy seasons, the basin of the Rio

    Grande grows significantly and it also brings along sediments that

    are placed in this part the basin that has a very low slope that

    favours floods.

    - 4 Final Report Hydrological Hydraulic Study of the low areas in the Lower Basin of the R io Grande Action against Hunger DIPECHO V

    - 5 Final Report Hydrological Hydraulic Study of the low areas in the Lower Basin of the R io Grande Action against Hunger DIPECHO V

    Figure 2. Map of Flood Risk Area5

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    16/53

    Fifth DIPECHO Action Plan for South America

    17

    According to the context described, the main problems tackled by

    the project are mentioned next:

    Organizational weakness of communities and municipalities

    in the Lower Basin of the Rio Grande.

    Lack of appropriate knowledge to adapt local living means

    to a context of high exposure to floods. Lack of municipal requirements responsible for the

    preparation and assistance to emergencies and disasters.

    Degradation of the natural defences of the Rio Grande bank

    which increases the exposure to floods in the community.

    Scarce inter-institutional coordination regarding the

    preparation, alert and response to adverse events.

    Departmental and Municipal Emergency Operation Centres

    having deficiencies in their damage evaluation processes

    generated for disasters, information analysis and decision

    making in emergencies.

    Municipalities having scarce response capability facing

    adverse events.

    2.8 Proposal of intervention

    The projects main purpose was to contribute to the decrease of

    risks in the Department of Santa Cruz (East of Bolivia), through the

    sustainable strengthening of response capabilities facing disasters

    of the most vulnerable population and the local risk management

    coordinated and appropriated inter-institutionally6. The project

    contemplated the following four results jointed to the objectivedescribed before:

    - 6 Interim Report, DIPECHO V Action against Hunger, 2008

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    17/53

    18

    Fifth DIPECHO Action Plan for South America

    Result 1. Inhabitants of communities with high risk to floods have

    been prepared and organized to respond to emergencies and

    mitigate disasters.

    Result 2. Authorities and technicians from institutions in the Lower

    Basin of the Rio Grande have improved their skills to face disaster

    situations.

    Result 3. Technicians and authorities at departmental and municipal

    levels know better about the risks to which the population in the

    Lower Basin of the Rio Grande is exposed and how to respond to

    disasters efficiently and co-ordinately.

    Result 4. Local authorities and technicians operate an improved and

    enhanced Early Warning System properly and co-ordinately and its

    indications and alerts are appropriately interpreted by the population

    most vulnerable to floods in the Lower Basin of the Rio Grande.

    The project identified the environmental sustainability as the main

    transversal axis and more specifically the adjustment of local means

    of living and the territorial organization to the limitations imposed

    by periodically flooded plains.

    2.9 Unexpected achievements and relevant difficulties in theimplementation

    Synergies with other ACHs interventions

    Before the implementation of the DIPECHO Project, Action against

    Hunger was already experienced in the area of intervention by

    having developed a project of Humanitarian Help in 2006 in

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    18/53

    Fifth DIPECHO Action Plan for South America

    19

    response to the floods caused by the Rio Grande that year. This

    presence allowed the relationship with departmental, municipal

    and communal authorities to be established, in most of the cases,

    faster and with more dynamism.

    The DIPECHO Project managed to complement itself with other

    three intervention fostered by ACH in the same territory, whichcaused a remarkable increase in the number of beneficiaries in the

    impact of the work done:

    The first project, financed by AECID, was centred on the left river

    bank of the Lower Basin of the Rio Grande, allowing the increase

    to ten communities and two municipalities (Okinawa and Saavedra)

    the strengthening work of local capabilities to face natural disasters

    planned in the DIPECHO, a project that was focused on the right

    river bank (San Julian, Cuatro Caadas, Pailon and El Puente). Because

    it concerns differentiated areas of intervention, the duplication of

    actions regarding local reaching activities was avoided. AECID

    project also became the main co-financer of the DIPECHO project,

    and it covered different activities, among which, the equipping of

    search and rescue groups (FAB-SAR Groups) stand out; the training

    of technicians and authorities on risk management, as well as the

    signalling of evacuation routes.

    The second project that coincided in time with that of DIPECHO,

    was also financed by ECHO, the Catalan Agency of Cooperation for

    Development (ACCD), and AECID. Such project allowed the

    emergency assistance for floods that happened between December2007 and January 2008. The name of the intervention was

    Humanitarian Help for the vulnerable population affected by floods

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    19/53

    20

    Fifth DIPECHO Action Plan for South America

    of the Rio Grande, in the Department of Santa Cruz, Bolivia. It lasted

    6 months. It started on February 15 and finished on August 14,

    2008. Its area of influence was made up by the municipalities of

    Pailn, Cuatro Caadas, San Julin and El Puente.

    This intervention focused on the attention of basic needs regarding

    hygiene, water and cleaning up of people affected by floods whowere dispersed in shelters and camps. Well cleaning activities were

    also organized in communities and small works of mitigation, as

    well as training and formation workshops on hygiene, water and

    cleaning up, etc.

    The third project, also developed for vulnerable communities in

    the Lower Basin of the Rio Grande, was approved by the Government

    of Navarra and was called: Reduction of vulnerability of the families

    in poverty situation and with high risk of suffering floods, through

    sustainable adjustment of their means of living to the natural

    environment in the Lower Basin of the Rio Grande. It lasted 7 months.

    It started on August 1st, 2008 and finished on March 31, 2009. The

    area of intervention covered 10 communities vulnerable to floods

    distributed in the municipalities of Pailn, Cuatro Caadas, San

    Julin y El Puente.

    Navarras proposal was mainly focused on the adjustment of the

    means of living of the vulnerable communities, facing the natural

    environment of the Rio Grande and contemplated coordination

    activities and work together with extension agent technicians from

    the Agricultural Departmental Service (SEDAG), made theimplementation of demonstrative family gardens, fostered the

    participation in fairs and agriculturally productive activities and

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    20/53

    Fifth DIPECHO Action Plan for South America

    21

    reproduced a series of material for the diffusion of information

    produced by SEDAG and related to the projects issues. Through

    this intervention the knowledge acquired by the inhabitants of the

    communities in the entire area of intervention was also reinforced

    through workshops on Communal Contingency Plan and it

    contributed to the diffusion of the products generated by all the

    actions carried out by ACH in the Lower Basin of the Rio Grandebetween 2007 and 2009.

    Municipal Acquisition

    DIPECHO project decisively contributed to the awareness increase

    in some municipalities about the need to focus the preparation for

    disasters comprehensively and permanently. In this sense, the

    Municipality of Pailon ended up creating a Risk Management Unit

    which has a person, equipment and specific budget for

    comprehensive management of risks. This important step shows

    the level of empowering of these municipalities in the design of

    their own policies responding to a specific need of attention to

    risks which they have to live with.

    Communal initiative

    In the case of villagers participating in the process, it could be seen

    that there has been a higher sense of awareness, identifying

    themselves as participants in the social construction of the risk,

    which produced mutual cooperation coordination among

    neighbouring communities with which to take more comprehensivemeasures of risk reduction, preparation, alert and response to

    disasters. The process of training on preparation for disasters was

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    21/53

    22

    Fifth DIPECHO Action Plan for South America

    designed starting from interest expressed by the very beneficiaries,

    outstanding among its contents, the self construction of wooden

    boats which allow providing 17 communities with essential elements

    for evacuation and rescue its inhabitants.

    Participation of local participants in the search for sustainability

    Another important result was the incorporation of the Autonomous

    University Gabriel Rene Moreno Institute of Popular Training, to

    the DIPECHO project. This allowed higher education to be part of

    the training process in the obtained results.

    In the case of the strengthening and implementation of the Early

    Warning System, the group of participants related to the EWS was

    strengthened with specialized equipment and training. The

    expansion of the group through the use of low cost and easy upkeep

    technology stands out, as well as cell phone telephony, providing

    25 communities with the necessary equipment (antennas and

    telephones) to be communicated during emergency situations.

    Main difficulties

    Among the greatest inconveniences the DIPECHO project had to

    face, the social political conflicts the Department of Santa Cruz goes

    through stand out, and they reached their culminating moment

    between the months of August and September 2008, with the closing

    of routes, taking of public institutions and discontinuation of economic

    activities. Besides stopping the proper execution of activities, thisclimate has made it extremely difficult to process inter-institutional

    coordination, one of the main work lines proposed by the project.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    22/53

    Fifth DIPECHO Action Plan for South America

    23

    T h e p e r i o d o f

    implementation also

    coincided with three

    electoral processes, which

    made it difficult to call for

    training/awareness events

    planned in communitiesand municipalities.

    The situation forced the

    ACHs team to maintain a permanent lobbying and conciliation

    attitude, emphasizing the principles of neutrality and impartiality

    of the institution. Despite this effort, some confusion occurred in

    some of the communities and municipalities about the role played

    by the different institutions related to the project.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    23/53

    24

    Fifth DIPECHO Action Plan for South America

    The social political conflicts added to the humanitarian emergency

    caused by the floods in February 2008 caused some of the local

    participants not to have the best predisposition or availability of

    human resources and time to get involved more actively in the

    activities proposed by the project.

    In general terms, technicians and authorities of the interventionarea came from a limited knowledge about the responsibilities

    assigned to them by the juridical mark stipulated by Law 21407.

    The municipalities and communities neither had, in most of the

    cases, a trajectory of jointed work in the preparation for disasters.

    - 7 Risk Reduction and emergencies atention low

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    24/53

    Fifth DIPECHO Action Plan for South America

    25

    Chapter III

    Capitalization of Experiences

    3.1 Introduction to capitalization

    For the fulfilment of the results proposed by the Project, a

    comprehensive intervention strategy was adopted; however, the

    following sub-sectors stand out given the importance assigned to

    them by the project:

    - Community Strengthening / Communal Brigades of CivilDefence

    - Expansion of the Early Warning System facing floods

    - Inter-institutional training process on preparation for disasters

    3.2 Capitalization

    Component 1.

    Community Strengthening / Communal Brigades of Civil Defence

    The component of community work is included in Result 1:

    Community inhabitants with high risk of floods have been prepared

    and organized to respond to emergencies and to mitigate disasters.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    25/53

    26

    Fifth DIPECHO Action Plan for South America

    1. Description and Converging Aspects

    This process started with the selection of beneficiary communities,

    in coordination with municipal and communal authorities,

    considering the degree of threat and vulnerability facing disasters

    the main criteria. In such communities, a communal self-diagnosis

    was carried out and one of their main products was the preparationof flood maps. The information procured at the beginning of the

    project was completed with a survey on Knowledge, Attitude and

    Practices (KAP), in relation to the preparation for floods.

    The process of community selection followed the following criteria:

    a) Identification of areas of high risk of floods in the Lower

    Basin of the Rio Grande: for that, the information

    procured from Mayoralty Resolution No. 086/2007 from

    March 27, 2007, from the Mayoralty of Santa Cruz was

    used and it states and delimits the area of high risk of

    floods in the Lower Basin of the river with geographic

    coordinates.

    b) Analysis of historic records of floods in the municipalities

    of intervention, which allowed focalising in more detail

    those areas that in the last few years have been more

    exposed to the overflowing dynamics and floods of the

    river and that have suffered more losses and damages.

    c) Consultation to local authorities and organizations:because the number of communities susceptible to

    floods in the intervention municipalities is larger than

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    26/53

    Fifth DIPECHO Action Plan for South America

    27

    the one foreseen in the project. The technical team of

    the project supplemented the initial analysis with

    interviews and meetings dedicated to agree with

    municipal technicians, the municipal government's

    authorities and leaders of the social and community

    organizations the election of the communities where

    to work.

    After the selection of communities, the community diagnosis was

    carried out with each one of them, through workshops carried out

    by promoters of the DIPECHO project, with the purpose that they

    write their maps of perception of the communal risk and identify

    the strengths, weaknesses and necessities for the attention and

    response to emergencies and disasters.

    Then, they conformed to Communal Brigades of Emergency in the

    35 communities located in the six established municipalities; the

    members of the brigades were trained in the areas of: Evacuation

    of Communities, Early Alert and Activation of Response, Management

    of Shelters, First aids in Remote Areas, Controlled Burns, Forest Fire

    fighters, self-construction and maintenance of wooden boats.

    Complementarily to the training, basic equipment for response to

    emergencies was provided.

    In the final stage of implementation, Communities, Communal

    Brigades of Emergency and promoters cooperated with the

    preparation of Communal Plans of Contingency facing Floods that

    capture the coordination actions, operation and response toemergency situations. An important exercise that closed the

    activities in the communities was the development of workshops

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    27/53

    28

    Fifth DIPECHO Action Plan for South America

    of communal simulations, to be able to apply the acquired

    knowledge, to evaluate the effectiveness of the Contingency Plans

    and to familiarize with the deficiencies on which the community

    should work.

    From an initiative of the Project and Communal Brigades, inter-

    communal workshops were carried out, where Brigades from

    different communities gathered to make an interchange ofknowledge, experiences, and to consolidate the mutual support

    and coordination bonds.

    Among the activities proposed by the project, reforestation actions

    in prioritised areas over the Rio Grande bank were done. The work

    was developed in coordination with the municipalities of Pailon

    and San Julian. The support for the project for this activity was

    centred on giving forest seedling and equipment to the

    Municipality of Pailon, as well as salary payments, for a period of

    3 months (September, October and November) to 7 people incharge of the work at the nursery and transplants in prioritised

    areas in the Municipality of San Julian.

    Figure 3. Maps of the community of Port Pacay, in normal situation

    and during a flood time. Contingency Plan

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    28/53

    Fifth DIPECHO Action Plan for South America

    29

    Among other activities, there were those of protection of water

    supply wells in the communities, with the purpose of avoiding

    contamination in case of floods. Seven temporary shelters were

    also identified and adjusted so that they can be used as shelters

    in the right place, for temporarily evacuated families in future flood

    areas. In the adjustment and repair of the shelters, minimal

    regulations of the Sphere Project were taken into account.

    2. Impact, relevance and comprehensiveness

    The component has impact and relevance elements, initially with

    the work in communities through promoters, who became

    participants with knowledge of the problem facing floods in the

    area. The awareness of these local participants created a bigger

    impact on the strengthening local capabilities and a sense of

    relevance that facilitated the rapprochement, the empathy relation

    with their environment between vulnerable municipalities and

    communities.

    According to the analysis, the strongest and most impact of an

    adverse event on the communities falls on the means of living,

    and the strategy used by Action against Hunger was to strengthen

    and complement the implementation of the DIPECHO project with

    the Food Security Project financed by the Government of Navarra.

    The Food Security Project in larger measure facilitated that ten

    communities acquired the thematic of Risk Reduction and

    Preparation for Disasters by conceptualising a solution conduciveto reduce the impact that the communities considered more

    important as a result of an adverse event.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    29/53

    30

    Fifth DIPECHO Action Plan for South America

    It can be emphasized the effort of the project to cover the diffusion

    of appropriate knowledge of the preparation for disasters in the

    widest possible territory of the Lower Basin of the Rio Grande,

    overcoming climatic and logistics difficulties. This devotion has

    been recognized for the communities themselves.

    The methodological training process incorporated local demandsand made the villagers participants. The Communal Contingency

    Plans rescued key aspects about local knowledge and

    organizational appropriate actions.

    The exercise of communal simulations incorporated the SAR Group

    as facilitators, which allowed strengthening coordination

    mechanisms of an operation requirement that at a time of an

    emergency supports the evacuation and the rescue. These exercises

    also allowed a better knowledge of the environment from the

    FAB-SAR Groups and a better degree of relation with the villagers

    in a different phase at the time of an emergency.

    Facilitators and community created a mutual coordination and

    learning space in relation to the participants affected-rescuer,

    acknowledging the exercise of the simulation as an important

    learning process and ulterior analysis of all the process of DIPECHO

    Project about communal response capabilities.

    Having physical spaces for sheltering people in case of adverse

    events, was carried out together with the municipalities, to which

    Action against Hunger technically advised about minimalrequirements these spaces must meet about water and cleaning

    up, food, solid wastes management, administration, besides the

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    30/53

    Fifth DIPECHO Action Plan for South America

    31

    selection of appropriate space for this task. It is also important to

    mention that these spaces have been adjusted through the Project

    and meet the Minimum Requirements in the SPHERE Project.

    Component 2.

    Expansion of the Early Warning System facing Floods

    The improvement of the Early Warning System (EWS)

    corresponding to Result 4. Local authorities and technicians

    operate an improved and enhanced Early Alert System,

    appropriately and co-ordinately, and its indications and alerts are

    interpreted appropriately by the population most vulnerable to

    floods in the Lower Basin of the Rio Grande.

    1. Description and concluding aspects

    The EWS strengthening and improvement process started with

    interviews, structured surveys and coordinating meetings with

    local requirements that made up the Early Warning Commission

    and Monitoring COED in the Department of Santa Cruz, such as

    the Service of Water Embankment of the Pirai River ( Servicio de

    Encauzamiento de Aguas del Ro Pira SEARPI), the Municipal

    Emergency Operation Centres and the National Service of

    Meteorology and Hydrology (Servicio Nacional de Meteorologa e

    Hidrologa SENAMHI), AASANA, Project of Non Structured Measures

    of Drainage North Area and the Direction of Territorial and Basins

    Arrangement to know the existing deficiencies in the current system.

    As a result of the actions mentioned before, the alert informationprotocols were strengthened by workshops where the institutions

    updated their alert communication protocols and means.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    31/53

    32

    Fifth DIPECHO Action Plan for South America

    In order for the EWS communication protocols may work more

    efficiently, the expansion of the alert communication system was

    carried out through installation of towers and antennas where there

    was no signal. The project provided the appropriate telephone

    equipment and manual battery charging systems. This way they

    have an easy and permanent communication not only for

    emergency situations but also for any necessary case.

    In communities, EWS operation training workshops were carried

    out including the diffusion of the meaning of alert messages to the

    population, a training that was made at a municipal level as well.

    Awareness raising campaigns about the topic were developed,

    including diffusion materials for the general population.

    From this process, the incorporation of the Early Warning component

    in the Community Contingency Plans was carried out. This way,

    alert communities methods were defined, meeting points, escape

    routes and safe areas. To facilitate these works, the signalling of

    evacuation routes was made (270 Km), distances were determined,

    approximate times between communities and safe areas, by foot

    and by vehicle, capturing all this information on the Communal

    Contingency Plans.

    The project provided SEARPI with the equipment for monitoring

    the river flows, which will allow having permanent and reliable

    statistical data of the behaviour of the river and its levels. In the

    next figure, the way in which the SAT is articulated in the Rio Grande

    is shown.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    32/53

    Fifth DIPECHO Action Plan for South America

    33

    SENAMHI Santa Cruz Observadores de SEARPI asignados almonitoreo de limnmetros en Abapo y Pailas

    SEARPI Santa Cruz

    COED (Comisin de AlertaTemprana)

    Telfono celular y reportes escritos

    Telfono celular, fax y e-mail

    Telfono celular, SMS, radioemisoras

    Centro OperacionesEmergencias

    (COEM)

    BrigadasComunitarias de

    Defensa Civil

    OTBs, ComitsCominitarios de Alerta

    Temprana

    Radioemisoraslocales

    Figure 4. Information flow and communication means used in the SATA

    of the Rio Grande

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    33/53

    34

    Fifth DIPECHO Action Plan for South America

    Additionally to the

    hydrometric equipment,

    2 limnimetric scales

    were installed in the

    community of Puerto

    Pacay in the Municipality

    of Cuatro Caadas and6 limnimetric rulers were

    painted in the railroad

    bridge of Puerto Pailas,

    in the Municipality of

    Pailon. These devices were also created with the purpose of

    improving the quality and quantity of data that allow optimising

    and improving the necessary information to declare states of alert

    in the area of influence of the project.

    To validate the EWS

    strengthening processand other actions carried

    out during the project, a

    departmental simulation

    was carried out where

    EWS operation was

    observed, as well as the

    c o m m u n i c a t i o n

    protocols and means,

    training given to the

    communities, the response of the organizations in charge and the

    communities themselves facing emergency situations, coordination

    levels, communication among communities, municipalities and

    departmental government.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    34/53

    Fifth DIPECHO Action Plan for South America

    35

    2. Impact, relevance and comprehensiveness

    The departmental EWS strengthening facing floods was vitally

    important since it allowed the risks analysis articulations, alert

    signals and monitoring through technical-scientific means and

    communication systems, at departmental, municipal and communal

    level.

    The communities point out that the use of cell phone

    communication means will not only be for flood situations but

    there is already an awareness and acquiring of the systems to be

    used in any emergency situation that occurs in their community

    related to health, fires, etc.

    The hydrological-hydraulic study made in the Lower Basin of the

    Rio Grande provided relevant information about the dynamics of

    the river, areas of influence of its overflowing, factors that increase

    threats in the area, as well as anthropic activities that increase their

    vulnerability conditions, a situation that has been increasing through

    the years. An important element within the recommendations of

    this study is an action proposal called Comprehensive Management

    Service of the Lower Basin of the Rio Grande.

    From the Communal Contingency Plans, the communities know

    and identify their evacuation routes, meeting places and shelters,

    distances to these points, information that is relevant for the

    municipality, and from it, they can plan response activities more

    appropriately, contributing with support by the necessaryequipment and logistics.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    35/53

    36

    Fifth DIPECHO Action Plan for South America

    The elements previously mentioned allow departmental and

    municipal levels to have larger instruments to plan the response

    to emergencies or disasters and join them technically.

    Component 3.

    Process inter-institutional training on preparation for disasters

    Within the project, there was an important Training component,

    incorporated in: Result 2. Authorities and technicians from

    institutions in the Lower Basin of the Rio Grande have improved

    their skills to face disaster situations, and Result 3.Technicians and

    authorities of municipal and departmental levels know the risks to

    which the population of the Lower Basin of the Rio Grande is

    exposed better and how to respond to disasters efficiently and co-

    ordinately.

    1. Description and conclusive aspects

    In this component the Municipal Emergency Operation Centres

    were organized and equipped in 6 beneficiary municipalities and

    the Departmental Emergency Operation Centre. In the municipalities

    where there was no COEMs, the process started from their creation.

    To strengthen the COEM and the Departmental Emergency

    Operation Centre COED, technicians and municipal and

    departmental authorities were trained on the following topics:

    - Early Alert and response activation

    - Logistic Support Systems Course LSS/SUMA- Need Analysis and Damage Evaluation Course

    - Minimal Norms Sphere

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    36/53

    Fifth DIPECHO Action Plan for South America

    37

    - Shelter Administration

    - GPS basic handling

    - First Aids

    In the training general process a big step was taken to the design

    and implementation of the Course called: Risk Reduction and

    Preparation for Emergencies, in coordination with the AutonomousUniversity Gabriel Rene Moreno (UAGRM). This course has been

    the first academic experience of this kind in the Department of

    Santa Cruz. Its contents are structured the following way:

    Module 1. Conceptual framework of Risk Management

    Module 2. Legal and Regulation framework Risk Management

    Module 3. Risk Analysis

    Module 4. Hydrology: risk management

    Modulo 5. Climatic change

    Modulo 6. Land Use Plan

    Modulo 7. Early Warning System for Forest Fires (SATIF)

    Modulo 8. Early Warning System for Floods in the CBRG

    The courses develop every module in theory and in practice through

    conceptual presentations, exercises and case studies in which GR

    topics are incorporated, Municipal Development Plans and Territorial

    Arrangement.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    37/53

    38

    Fifth DIPECHO Action Plan for South America

    The Search and Rescue Team FAB SAR was also trained on: First

    Aids, Cartography, Damage Evaluation and Need Analysis EDAN,

    Aquatic Rescue, Use and Handling of communication equipment,

    Engine Handling and Diving; equipment was also given to carry

    out the activities they were trained on.

    Health personnel were trained on Disaster Preparedness in the

    Lower Basin of the Rio Grande, with the support of the Departmental

    Health Service (SEDES) and the Panamerican Health Organization

    (OPS).

    In the results this component covers, there is the preparation of the

    Departmental Contingency Plan and Municipal Contingency Plans,and for these, inter-institutional workshops were organized where

    action protocols were defined in case of floods.

    Photo 5. Training to Municipal COEs

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    38/53

    Fifth DIPECHO Action Plan for South America

    39

    From a need identified during the formulation of the project, COEDs

    technicians were designed and trained on the implementation of

    the Information System for Departmental Emergencies (SIGED),

    that allows:

    - The creation of a database, a structured archive and

    information analysis of Damage Evaluation EDAN

    - The automatic generation of reports in which type and

    amount of humanitarian help required in a community or

    municipality is specified

    - The generation of GIS (Geographic Information System)

    maps of victim areas, degree of affectation, etc.

    - Representation of damage maps on Google Earth.

    All the generated information was shown to the departmental and

    municipal institutions and to the general public so that they could

    apply the generated knowledge.

    Finally, together with the Departmental Government of Santa Cruz,

    a commemorative fair of the International Day for Disaster Reduction

    was co-organized and implemented, where the civil society was

    shown the activities carried out by the Project, the need to be aware

    of the risks they coexist with, as well as of the importance of including

    risk management in the organizational social culture. In this fair,

    institutions such as the City hall, Mayoralty, Voluntary Fire-fighters,SAR FAB, Departmental Civil Defence, International Plan, Bolivian

    Red Cross, Help in Action among others.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    39/53

    40

    Fifth DIPECHO Action Plan for South America

    2. Impact, relevance and comprehensiveness

    Although COEDs members had an empirical knowledge and a wide

    experience on emergency assistance, the training reinforced the

    acquired practical skills, offering new operative technical knowledge,

    which allowed to strengthen their institution quality not only

    through their practice but also by having a more comprehensivefocus on the preparation and response to disasters.

    The strengthening not only physical but also conceptual of the COEMs

    generated a leadership and awareness from local authorities at the time

    of focusing on emergencies to a Comprehensive Risk Management

    in all its processes through the creation of Risk Management Unit

    (UGR) that allows the municipality to work not only at the time of a

    disaster but also during its previous and ulterior phases.

    A relevant aspect in the attitude change that lately has been

    perceived in municipalities is the purposed manifested by

    technicians and authorities to prioritise the response to a disaster

    that affects the municipality before turning to departmental help,

    which is a resource to turn to in case that local capabilities have

    been overwhelmed. The training course organized with the

    University allowed focusing on risk management not as an activity

    separate from the development processes but as an incorporated

    to municipal development planning.

    The training received by SAR Group besides being in accordance

    with the objectives the institution pursuits, allowed them to generatea vision of self management in strengthening and training processes

    through knowledge, capabilities and skills that have been developed.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    40/53

    Fifth DIPECHO Action Plan for South America

    41

    Finally, the software development of the Departmental Emergency

    Information System (SIGED) allows the Departmental Government

    to have a tool that articulates the generation of maps (SIG), with

    the Damage Evaluation Form (EDAN) and SPHERE Minimal Norms

    in a comprehensive way.

    This tool gives complete information that allows planning actionsbefore, during and after the emergency.

    This computer system may be empowered by the national

    organization such as Civil Defence and by other departments by

    incorporating them to their emergency management. The SIGED

    becomes a useful tool to make a strategic planning of Response to

    Disasters.

    3.3 Lessons learned

    This part of the projects capitalization process was also made with

    the managerial and technical team of Action against Hunger.

    - The creation of Civil Defence Communal Brigades in the

    area of intervention has limited sustainability given the

    social cultural conditions. Therefore, the need to incorporate

    preparation and communal response to disasters to already

    existing local organizational structures is proposed.

    - Increasing the levels of planning, coordination, follow-up,

    experience sharing and articulation of different componentsof the technical team to increase impact of each activity

    was identified as of vital importance.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    41/53

    42

    Fifth DIPECHO Action Plan for South America

    - In the processes of work with promoters, methodological

    weaknesses of teaching were identified, so it is necessary

    to design a training methodology for promoters and a

    training methodology from promoters to villagers

    implemented homogenously in all the Projects activities.

    - Due to the situations specific to the context where theactivities are carried out, the projects technical team showed

    a great capability of adjustment to the difficult environment

    dynamics, and remained in its neutral and independent

    position.

    - In the training processes in communities, a great number

    of participants were women accompanied by children. This

    circumstance may be used to carry out simultaneous

    activities of awareness directed to school children that allow

    a more comprehensive use by the participants and the

    inclusion of a new participant in the training.

    - Due to the social cultural characteristics, the difficulty of

    communication and the extension of the territory covered

    by the project, the community workshop or training calls

    were not as good as they should have, and as a consequence,

    the level of participation in the training was lower than

    expected. A strategy to insure a greater participation of the

    rural population must be designed.

    - At the beginning of the Project and during its execution,it is necessary that the Projects team correctly understand

    and interpret the objectives and commitments of the

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    42/53

    Fifth DIPECHO Action Plan for South America

    43

    document to improve the articulation of components and

    results.

    - Although carrying out departmental simulations

    strengthened the learning processes of DIPECHO Project,

    the need to carry out these exercises was identified focusing

    on different sectors, level and stages so that during apreliminary exercise there may be a real diagnostic that

    allows defining strategies during the implementation of

    the project and at the end of the process carry out an

    evaluation of the generated capabilities.

    - To achieve attitude and behaviour changes in communities,

    it is important and necessary to use a methodology of

    information based on the community developing a medium

    and long term publicity campaign.

    - Although ACH achieved incidence on the social

    responsibility of the cell phone telephony private companies,

    the results were not those expected. However, it became a

    new working line that allows the articulation of new

    participants of the preparation for disasters.

    3.4 Testimonies of participants in the DIPECHO Rio Grande

    Project

    - The project was developed very appropriately within

    the municipality because it is a municipality that itscontinuously threatened by floods, so that it can assists its

    different communities that needed this training, so that

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    43/53

    44

    Fifth DIPECHO Action Plan for South America

    they become more aware of the danger, of the threat they

    have there permanently. By becoming aware, they already

    know they are threatened and then they have a response

    at the moment of the flood, unlike past years, the

    communities are trained and make the decision of self

    evacuate, if the term is valid, and not to wait for the help to

    come, because it always comes late. They have the capabilityto evacuate, they take preventive measures before it

    happens, considering the place where they will go to,

    adjusting the possible shelters, the possible routes. We have

    noticed a change thanks to the training received Severino

    Barba Bazn, Honourable Municipal Government of

    Okinawa.

    - Civil Defence has always had to made expenditures to

    train people sending them abroad, but since Action against

    Hunger has started to train

    people, we have had the

    opportunity to attend the training

    and to increase our possibility to

    help people Colonel Juan

    Carlos Velsquez Rivera, Head of

    E v a l u a t o r s C i v i l D e f e n c e

    Departmental Direction Santa

    Cruz.

    - Actually, for us, it has been

    flattering as a municipality,because our capability especially

    of response and to have a good

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    44/53

    result regarding the

    affectations we had,

    the work done by

    Action against Hunger

    has been of great help,

    that besides training us

    as a municipality, theyhave trained all the

    c o m m u n i t i e s

    M a n f r e d o S u a r e z

    Parada, Honourable

    Municipal Government

    of Saavedra.

    - The project has intervened in the logical area, which is

    the Lower Basin of the Rio Grande. It was one of the most

    affected areas, and it has been thus coordinated and we

    are aware of that and we thank having recognized the

    departmental organization that COE is by law and the

    mayoralty which are the top departmental organizations

    by law Alcides Vargas, Departmental Secretary of Human

    Development Director Departmental Emergency

    Operation Centre Departmental Government of Santa Cruz.

    - Action against Hunger comes in the main door at the

    moment of signing an agreement with the municipality of

    San Julian and the conclusions that stand out, I would say,

    for example, are the creation of a Early Alert System wherethe communities are equipped with cell phones and its

    respective antennas and towers. I think this is a very

    Fifth DIPECHO Action Plan for South America

    45

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    45/53

    46

    Fifth DIPECHO Action Plan for South America

    important tool to alert or to have communication that may

    be about emergencies or others. In the Rio Grande for

    example, many eucalyptus seedlings have been produced.

    also with the support of the project, forest areas have been

    reforested and the mayoralty keeps reforesting at the

    moment and we ask ACH to propose a new project with

    other communities in San Julin Avilio Moreira Cruz,Director of Economic Development Honourable Municipal

    Government of San Julin.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    46/53

    47

    Fifth DIPECHO Action Plan for South America

    Chapter IV

    Recommendations8

    1. The information, tools, instruments and results generated must

    be socialized the widest way possible tot he participant of

    Preparation and Response to Disasters to generate a larger use,

    empower their capabilities, their acquisition and relevance for

    their use in decision making.

    2. Even though the project has finished, there is a possibility that

    the public participants continue and search financing for theprojects processes, or other similar proposals be designed and

    financed.

    3. Motivate municipal and departmental Governments to continue

    and include a process of reinforcement of the projects results

    and prepare similar projects.

    4. The promotion of knowledge in technicians and facilitators of

    evaluation methodologies about teaching and learning

    systematically, emphasizing on qualitative aspects. This would

    improve the results and impact on the educational processes

    (training).

    - 8 Recommendations from the Report of External Evaluation EX-Post of the project is incorporated, prepared by consultant Alfredo Paz.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    47/53

    48

    Fifth DIPECHO Action Plan for South America

    5. The selection of qualified personnel of project coordination with

    competencies that prioritise development project management.

    Skills, abilities and experience on the project management seem

    more important than technical competence in the topic dealt

    with. Technical competences at risk management levels and

    others, may be carried out by technical specialists, but good

    personnel management, team work, management tools, control,monitoring and follow-up, inter-institutional relations, etc. are

    key at the time of executing a project.

    6. Applying a reviewing method to consistency of logical

    framework (Any of the methods commonly used), to detect

    difficulties in the measurement of indicators and facilitating the

    generation of verification sources and base lines.

    7. Establishing ample time ranges in places where the occurrence

    of assumptions or external factors interferes with temporary

    efficiency such as social or political conflicts.

    8. Capitalizing the experience at institutional and financial

    organizations levels. The systematisation of experiences and

    practices normally end up in a collection of data, reflections

    about the project and its participants, executors, but it is

    recommended to continue until they are implemented and

    applied to the interior of linked institutions and their projects.

    For this, it is useful to prepare a specific work plan.

    9. Mass socialization of the study made for the project and theachieved systematisation because they will promote the topic

    at different levels.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    48/53

    Fifth DIPECHO Action Plan for South America

    49

    10.The assignation of specific budgets to carry out several

    simulations in similar projects because besides being referents

    of the situation valuation, it is an appropriate space to put the

    knowledge, attitudes and practices achieved by the participants

    into practice.

    11.The in-depth study and selection of variable and pertinent andintelligent indicators in the evaluation system of simulations,

    because the application of simulations but especially drills,

    provide ideal opportunities to value several aspects, sectors and

    performances in projects of this kind, and consequently of

    adjustments in the execution and in the strategies and

    methodologies used.

    12.A strategy of work must be designed with information means

    of communication that generate synergy effects that strengthen

    the seizure of knowledge about Preparation and Disaster

    Preparedness.

    13.In the processes of training and follow-up of the activities in

    communities, authorities of the COEM should be included with

    a more protagonist role to increase the capability of autonomous

    response to disasters.

    14.The design and application of methodologies must be

    restructured and strengthened in the training processes of the

    entire technical team in a way that it responds to a strategy of

    the project in all its activities.

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    49/53

    50

    Fifth DIPECHO Action Plan for South America

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    50/53

    Fifth DIPECHO Action Plan for South America

    51

    ANNEX 1

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    51/53

    52

    Fifth DIPECHO Action Plan for South America

    Products systemised by the project, made available to anyone

    interested

    1. Digitalized maps obtained from community self diagnosis of

    flood risks

    2. Didactic materials used in training courses given tocommunities; first aids, forest fire-fighters and controlled burn)

    3. Community Contingency Plans

    4. Report of community simulations workshops systematisation

    5. Report of Survey at the beginning and end of the project, about

    communal Knowledge, Attitudes and Practices (CAP) about

    risk management.

    6. Card of temporary shelter repair systematisation (blue prints

    of work, budgets, photographs)

    7. Card of well protection systematisation (blue prints of work,

    budgets, photographs)

    8. Card of reforestation activity systematisation

    9. Training of technicians and departmental and municipal

    authorities on Preparation for Disasters and Response to

    Emergencies: module contents, support documents, certificatemodel

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    52/53

    Fifth DIPECHO Action Plan for South America

    53

    10. Training and equipping of Municipal Emergency Operation

    Centres (COEM): module contents, support documentation,

    certificate model

    11. Training on preparation for disasters to municipal health service

    personnel in coordination with OPS

    12. Training and equipping of FAB-SAR Groups: module contents,

    support documents, certificate model

    13. Municipal and departmental contingency plans: six documents

    of municipal plans and one document of departmental plan

    14. Report of Systematisation of inter-institutional workshops to

    prepare the Departmental Contingency Plan

    15. Indicators of preparation for disasters: analysis report with

    municipal technicians and authorities of the Red Cross reference

    document

    16. CD with free software Departmental Emergencies Management

    System (SIGED); installation software, users manual, coordinates

    of communities in the Department of Santa Cruz

    17. DVD with hydrological study of the Lower Basin of the Rio

    Grande and risk maps in Arcgis and Autocad formats

    18. Report of systematisation of the commemoration events ofthe International Day of Disaster Reduction (DIRD)

  • 8/14/2019 Informe de Capitalizacin del Proyecto DIPECHO Ro Grande (Ingls)

    53/53

    Fifth DIPECHO Action Plan for South America

    19. Report of capitalization of the project

    20. Card of systematisation about hydrometric equipment given

    to SEARPI, in the framework of improvement activities of the

    Early Alert System (SAT)

    21. Card of systematisation of the SAT communication networkimprovement process

    22. Card of systematisation of the Awareness Campaign about SAT

    and preparation for floods: school drawings, illustrations bank,

    printed materials, radio spots, radio soap opera, Game Riskland

    23. Card of systematisation of communal evacuation routes

    signalling

    24. Report of systematisation of departmental simulation

    25. Report of final External Evaluation

    26. Bank of photographs generated for the project