SESSION 2 - QUESTION 12.1 PRACTICES AND REGULATOR REQUIREMENTS TO COLLECT AND COMPUTE RELIABILITY INDICES. Javier Amantegui. Billing discount must be applied to customer in case of non-fulfilment of individual quality. Measuring Systems must be able to be audited. - PowerPoint PPT Presentation

Citation preview

Page 1: Javier Amantegui

Barcelona 12-15 May 2003

SESSION 2 - QUESTION 12.1

PRACTICES AND REGULATOR REQUIREMENTS TO COLLECT

AND COMPUTE RELIABILITY INDICES

Javier Amantegui

Page 2: Javier Amantegui

Barcelona 12-15 May 2003

QUALITY OF SUPPLY REGULATIONS IN SPAIN

• Billing discount must be applied to customer in case of non-fulfilment of individual quality.

• Measuring Systems must be able to be audited.

Zonal

Individual URBAN SEMI-URBANCONCENTRATED

RURALDISPERSED

RURAL

Hours (No.) 4 8 12 16MV

Int. (No.) 8 12 15 20

Hours (No.) 6 10 15 20LV

Int. (No.) 12 15 18 24

URBAN SEMI-URBANCONCENTRATED

RURALDISPERSED

RURAL

TIEPI(Equivalent interruption time)

2 4 8 12

Percentile 80% 3 6 12 18

NIEPI (>3 min)(Equivalent interruption number)

4 6 10 15

Page 3: Javier Amantegui

Barcelona 12-15 May 2003

QUALITY OF SUPPLY PROJECT AT IBERDROLA

• Connectivity: To establish connectivity between each LV customer and distribution transformer for 9.2 million customer

• System: To calculate new indices and individual quality for each LV customer (paper 3.35)

• Procedures: To keep support documentation about– Customer calls– Automatic operations–Manual events– Notification of planned interruptions– Interruptions caused by third parties

• A vey important effort: 4 years, 300 people involved and more than 1000 affected.