3
FECHA : DICIEMBRE DE 2008 COD. DESCRIPCION Nº DE DIMENSIONES PARCIAL TOTAL UNID. VECES LARGO ANCHO ALTO 01 TRABAJOS PRELIMINARES 01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 1.20 X 2.40 m 1.00 1.00 1.00 u 01.02 LIMPIEZA DE TERRENO MANUAL 1.00 30.00 17.00 510.00 510.00 m2 01.03 TRAZO, NIVELES Y REPLANTEO 1.00 30.00 17.00 510.00 510.00 m2 02 MOVIMIENTO DE TIERRAS 02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS 54.60 m3 2.00 5.88 0.60 1.40 9.87 2.00 3.75 0.60 1.40 6.30 1.00 3.25 0.60 1.40 2.73 12.00 3.05 0.60 1.40 30.74 2.00 2.95 0.60 1.40 4.96 02.02 EXCAVACIONES DE ZANJAS PARA ZAPATAS 25.00 1.00 1.00 0.65 16.25 16.25 m3 02.03 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) 1.00 71.66 1.00 1.00 71.66 71.66 m3 03 CONCRETO SIMPLE 03.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS 38.04 m3 2.00 6.63 0.60 0.80 6.36 2.00 4.50 0.60 0.80 4.32 1.00 4.00 0.60 0.80 1.92 12.00 3.80 0.60 0.80 21.89 2.00 3.70 0.60 0.80 3.55 03.02 CONCRETO 1:10 PARA SOLADOS ZAPATA 25.00 1.00 1.00 25.00 25.00 m3 03.03 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS 5.35 m3 2.00 6.63 0.15 0.45 0.89 2.00 4.50 0.15 0.45 0.61 1.00 4.00 0.15 0.45 0.27 12.00 3.80 0.15 0.45 3.08 2.00 3.70 0.15 0.45 0.50 03.04 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30 m 71.33 m2 DE 0.30 A 0.60 M. 4.00 6.63 0.45 11.93 4.00 4.50 0.45 8.10 2.00 4.00 0.45 3.60 24.00 3.80 0.45 41.04 4.00 3.70 0.45 6.66 03.05 FALSO PISO DE 4" DE CONCRETO 1:10 1.00 28.20 13.70 386.34 386.34 m2 04 CONCRETO ARMADO 04.01 ZAPATAS 04.01.01 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS 25.00 1.00 1.00 0.55 13.75 13.75 m3 04.01.02 ACERO fy=4200 kg/cm2 GRADO 60 250.00 kg 25.00 10.00 1.00 0.99 247.50 Alambre N° 16 25.00 25.00 0.30 0.02 3.00 04.02 COLUMNAS 04.02.01 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS 25.00 0.25 0.25 3.50 5.47 5.47 m3 04.02.02 ACERO fy=4200 kg/cm2 GRADO 60 1,132.11 kg 1/2" C-1 25.00 6.00 6.00 0.99 891.00 1/4" 25.00 0.90 38.00 0.25 213.75 ALAMBRE 16 25.00 0.30 228.00 0.02 27.36 04.02.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 25.00 1.00 3.50 87.50 87.50 m2 04.03 VIGAS DE CIMENTACION 04.03.01 CONCRETO f'c=175 kg/cm2 PARA VIGAS DE CIMENTACION 20.40 m3 2.00 14.00 0.40 0.60 6.72 2.00 28.50 0.40 0.60 13.68 04.03.02 ACERO fy=4200 kg/cm2 GRADO 60 837.25 kg 1/2" 2.00 14.20 6.00 0.99 168.70 2.00 28.70 6.00 0.99 340.96 1/4" 2.00 2.20 93.00 0.25 102.30 2.00 2.20 190.00 0.25 209.00 ALAMBRE 16 2.00 0.30 558.00 0.02 5.36 2.00 0.30 1,140.00 0.02 10.94 04.03.03 ENCOFRADO Y DESENCOFRADO PARA VIGAS DE CIMENTACION RECTA 51.00 m2 2.00 14.00 0.60 16.80 2.00 28.50 0.60 34.20 HOJA DE METRADO ALTERNATIVA Nº 01 PROYECTO : CONSTRUCCION DE ALMACEN PARA LA COMUNIDAD DE SEVITE BAJA, DISTRITO DE SIVIA - HUANTA - AYACUCHO.

METRADOS SEVITE

Embed Size (px)

DESCRIPTION

ZCZC

Citation preview

Page 1: METRADOS SEVITE

FECHA : DICIEMBRE DE 2008

COD. DESCRIPCIONNº DE DIMENSIONES

PARCIAL TOTAL UNID.VECES LARGO ANCHO ALTO

01 TRABAJOS PRELIMINARES01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 1.20 X 2.40 m 1.00 1.00 1.00 u01.02 LIMPIEZA DE TERRENO MANUAL 1.00 30.00 17.00 510.00 510.00 m201.03 TRAZO, NIVELES Y REPLANTEO 1.00 30.00 17.00 510.00 510.00 m2

02 MOVIMIENTO DE TIERRAS02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS 54.60 m3

2.00 5.88 0.60 1.40 9.87

2.00 3.75 0.60 1.40 6.30

1.00 3.25 0.60 1.40 2.73

12.00 3.05 0.60 1.40 30.74

2.00 2.95 0.60 1.40 4.96

02.02 EXCAVACIONES DE ZANJAS PARA ZAPATAS 25.00 1.00 1.00 0.65 16.25 16.25 m3

02.03 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) 1.00 71.66 1.00 1.00 71.66 71.66 m3

03 CONCRETO SIMPLE03.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS 38.04 m3

2.00 6.63 0.60 0.80 6.36

2.00 4.50 0.60 0.80 4.32

1.00 4.00 0.60 0.80 1.92

12.00 3.80 0.60 0.80 21.89

2.00 3.70 0.60 0.80 3.55

03.02 CONCRETO 1:10 PARA SOLADOS ZAPATA 25.00 1.00 1.00 25.00 25.00 m3

03.03 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS 5.35 m3

2.00 6.63 0.15 0.45 0.89

2.00 4.50 0.15 0.45 0.61

1.00 4.00 0.15 0.45 0.27

12.00 3.80 0.15 0.45 3.08

2.00 3.70 0.15 0.45 0.50

03.04 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30 m 71.33 m2 DE 0.30 A 0.60 M. 4.00 6.63 0.45 11.93

4.00 4.50 0.45 8.10

2.00 4.00 0.45 3.60

24.00 3.80 0.45 41.04

4.00 3.70 0.45 6.66

03.05 FALSO PISO DE 4" DE CONCRETO 1:10 1.00 28.20 13.70 386.34 386.34 m2

04 CONCRETO ARMADO04.01 ZAPATAS

04.01.01 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS 25.00 1.00 1.00 0.55 13.75 13.75 m3

04.01.02 ACERO fy=4200 kg/cm2 GRADO 60 250.00 kg

25.00 10.00 1.00 0.99 247.50

Alambre N° 16 25.00 25.00 0.30 0.02 3.00

04.02 COLUMNAS04.02.01 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS 25.00 0.25 0.25 3.50 5.47 5.47 m3

04.02.02 ACERO fy=4200 kg/cm2 GRADO 60 1,132.11 kg 1/2" C-1 25.00 6.00 6.00 0.99 891.00

1/4" 25.00 0.90 38.00 0.25 213.75

ALAMBRE 16 25.00 0.30 228.00 0.02 27.36

04.02.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 25.00 1.00 3.50 87.50 87.50 m2

04.03 VIGAS DE CIMENTACION04.03.01 CONCRETO f'c=175 kg/cm2 PARA VIGAS DE CIMENTACION 20.40 m3

2.00 14.00 0.40 0.60 6.72

2.00 28.50 0.40 0.60 13.68

04.03.02 ACERO fy=4200 kg/cm2 GRADO 60 837.25 kg 1/2" 2.00 14.20 6.00 0.99 168.70

2.00 28.70 6.00 0.99 340.96

1/4" 2.00 2.20 93.00 0.25 102.30

2.00 2.20 190.00 0.25 209.00

ALAMBRE 16 2.00 0.30 558.00 0.02 5.36

2.00 0.30 1,140.00 0.02 10.94

04.03.03 ENCOFRADO Y DESENCOFRADO PARA VIGAS DE CIMENTACION RECTA 51.00 m2

2.00 14.00 0.60 16.80

2.00 28.50 0.60 34.20

HOJA DE METRADOALTERNATIVA Nº 01

PROYECTO : CONSTRUCCION DE ALMACEN PARA LA COMUNIDAD DE SEVITE BAJA, DISTRITO DE SIVIA - HUANTA - AYACUCHO.

Page 2: METRADOS SEVITE

FECHA : DICIEMBRE DE 2008

COD. DESCRIPCIONNº DE DIMENSIONES

PARCIAL TOTAL UNID.VECES LARGO ANCHO ALTO

HOJA DE METRADOALTERNATIVA Nº 01

PROYECTO : CONSTRUCCION DE ALMACEN PARA LA COMUNIDAD DE SEVITE BAJA, DISTRITO DE SIVIA - HUANTA - AYACUCHO.

04.04 VIGAS COLLARIN04.04.01 CONCRETO EN VIGAS f'c=210 kg/cm2 5.31 m3

2.00 14.00 0.25 0.25 1.75

2.00 28.50 0.25 0.25 3.56

04.04.02 ACERO fy=4200 kg/cm2 GRADO 60 483.42 kg 1/2" 2.00 14.20 4.00 0.99 112.46

2.00 28.70 4.00 0.99 227.30

1/4" 2.00 0.90 93.00 0.25 41.85

2.00 0.90 190.00 0.25 85.50

ALAMBRE 16 2.00 0.30 558.00 0.02 5.36

2.00 0.30 1,140.00 0.02 10.94

04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 42.50 m2

4.00 14.00 0.25 14.00

4.00 28.50 0.25 28.50

05 ALBAÑILERIA05.01 MURO DE SOGA DE LADRILLO KK 190.80 m2

2.00 6.63 3.00 39.75

1.00 6.63 2.00 13.25

2.00 4.50 3.00 27.00

1.00 4.50 2.00 9.00

1.00 4.00 3.00 12.00

1.00 4.00 1.00 4.00

12.00 3.80 3.00 136.80

2.00 3.70 3.00 22.20

DESCUENTO VENTANAS -1.00 73.20 1.00 -73.20

06 REVOQUES ENLUCIDOS Y MOLDURAS06.01 TARRAJEO EN INTERIORES Y EXTERIORES ACABADO CON CEME 2.00 190.80 1.00 381.60 381.60 m2

06.02 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA 1.00 87.50 87.50 87.50 m2

07 PISOS Y PAVIMENTOS07.01 PISO DE CONCRETO E=2" f'c 140 kg/cm2 X 4 cm PULIDO 1:2 X 1 cm 1.00 28.20 13.70 386.34 386.34 m2

07.02 VEREDA DE CONCRETO DE 4" 95.00 m2

2.00 30.00 1.00 60.00

1.00 14.00 1.00 14.00

1.00 14.00 1.50 21.00

07.03 ENCOFRADO Y DESENCOFRADO PARA VEREDAS 17.60 m22.00 30.00 0.20 12.00

2.00 14.00 0.20 5.60

08 CARPINTERIA DE MADERA08.01 PUERTA DE MADERA APANELADA 1.00 4.00 3.25 13.00 13.00 m2

09 CARPINTERIA METALICA09.01 VENTANA METALICA INCLUYE COLOCACION 60.20 m2

2.00 6.63 0.80 10.60

2.00 4.50 0.80 7.20

12.00 3.80 0.80 36.48

2.00 3.70 0.80 5.92

09.02 MALLA METALICA PROTECTORA DE VENTANAS 1.00 60.20 60.20 60.20 m2

10 TECHO CON ESTRUCTURA DE MADERA Y CUBIERTA10.01 TIJERALES T-1 9.00 1.00 9.00 9.00 u10.02 CORREAS DE MADERA TORNILLO DE 2"X3" 22.00 1.00 22.00 22.00 u10.03 ARRIOSTRE DE MADERA TORNILLO DE 1"X3" 2.00 1.00 2.00 2.00 u10.04 FRISO DE MADERA TORNILLO DE 1"X8" 2.00 1.00 2.00 2.00 u10.05 COBERTURA CON CALAMINA GALVANIZADA DE O.80 X 1.80 M 2.00 31.00 8.26 512.00 512.00 m210.06 CUMBRERA DE CALAMINA GALVANIZADA 1.00 31.00 1.00 31.00 31.00 m10.07 CANALETA DE CALAMINA GALVANIZADA 2.00 31.00 1.00 62.00 62.00 m

11 PINTURA11.01 PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES 2 MANOS 1.00 381.60 1.20 457.92 457.92 m2

11.02 PINTURA LATEX EN COLUMNAS 2 MANOS 1.00 66.50 66.50 66.50 m2

12 DRENAJE DE AGUAS PLUVIALES12.01 DRENAJE DE AGUAS PLUVIALES CON TUBERIA PVC 3" 4.00 1.00 4.00 4.00 u

Page 3: METRADOS SEVITE

FECHA : DICIEMBRE DE 2008

COD. DESCRIPCIONNº DE DIMENSIONES

PARCIAL TOTAL UNID.VECES LARGO ANCHO ALTO

HOJA DE METRADOALTERNATIVA Nº 01

PROYECTO : CONSTRUCCION DE ALMACEN PARA LA COMUNIDAD DE SEVITE BAJA, DISTRITO DE SIVIA - HUANTA - AYACUCHO.

13 INSTALACIONES ELECTRICAS13.01 SALIDA DE TECHO C/CABLE AWG TW 2.5 mm (14) + D PVC SAP 19 mm 1.00 12.00 12.00 12.00 pto13.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC 1.00 6.00 6.00 6.00 pto13.03 TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLOS 1.00 2.00 2.00 2.00 pza

14 CONEXION A LA RED EXTERNA, MEDIDORES Y POZA A TIERRA14.01 CONEXION PUESTA A TIERRA 1.00 1.00 1.00 1.00 u

15 ARTEFACTOS ELECTRICOS15.01 ARTEFACTO FLUORESCENTE DE 32 W 1.00 12.00 12.00 12.00 u

16 FLETE16.01 FLETE TERRESTRE 1.00 52,989.44 52,989.44 52,989.44 glb

17 MITIGACION DE IMPACTO AMBIENTAL17.01 REFORESTACION LATERAL 1.00 1.00 1.00 glb

18 CAPACITACION18.01 FORTALECIMIENTO DE PRODUCTORES AGRICOLAS 1.00 1.00 1.00 glb18.02 RIESGOS DE SALUD 1.00 1.00 1.00 glb18.03 EVENTOS DE CAPACITACION SOBRE ALMACENAJE DE PRODUCTO 1.00 1.00 1.00 glb