    Improving the Transportation Network inWestern Prince William and Eastern

    Loudoun Counties

    June 3, 2013

    Charles Kilpatrick, PE

    Chief Deputy Commissioner

  • 7/28/2019 N-S CIM Presentation

    2/47

    2

    2010

    Household

    Density andPopulation

    121,700

    342,400

    835,100

    233,120

    90,000

  • 7/28/2019 N-S CIM Presentation

    3/47

    3

    2040HouseholdDensity andPopulationGrowth

    1,021,000+ 22%

    327,000+ 41%

    195,000+ 60%

    147,000+ 63%

    488,000+ 43%

  • 7/28/2019 N-S CIM Presentation

    4/47

    4

    2010Employment

    36,260

    104,180

    507,450

    145,090

    38,200

  • 7/28/2019 N-S CIM Presentation

    5/47

    5

    2040Employment

    Growth

    706,390+39%

    269,550+ 86%

    78,620

    +106% 190,600+83%

    76,720+ 112%

  • 7/28/2019 N-S CIM Presentation

    6/47

    6

    Volumes to Capacity (V/C) Ratio

    V/C ratio is a planning-level measure of the extent towhich a roadway accommodates traffic

    V/C ratios greater than 1.0 indicate high levels ofcongestion and stop-and-go travel

    -- (0-0.4) Less than 40% of capacity utilized

    -- (0.4-0.7) 40% to 70% of capacity utilized

    -- (0.7-1) 70% to 100% of capacity utilized

    -- (1-1.4) 140% of capacity utilized

    -- (> 1.4) Demand is more than 140% of capacity

  • 7/28/2019 N-S CIM Presentation

    7/47

    2013 Network Traffic AM Peak Hour

    7

  • 7/28/2019 N-S CIM Presentation

    8/47

    2040 Network Traffic No Build Scenario AM

    8

  • 7/28/2019 N-S CIM Presentation

    9/47

    2013 Network Traffic PM Peak Hour

    9

  • 7/28/2019 N-S CIM Presentation

    10/47

    2040 Network Traffic No Build Scenario PM

    10

  • 7/28/2019 N-S CIM Presentation

    11/47

    2040 Network Traffic Build Scenario AM

    11

  • 7/28/2019 N-S CIM Presentation

    12/47

    2040 Network Traffic Build Scenario PM

    12

  • 7/28/2019 N-S CIM Presentation

    13/47

    EXISTING TRAFFICCONGESTION

    13

  • 7/28/2019 N-S CIM Presentation

    14/47

    14

  • 7/28/2019 N-S CIM Presentation

    15/47

    15

  • 7/28/2019 N-S CIM Presentation

    16/47

    16

  • 7/28/2019 N-S CIM Presentation

    17/47

    17

    4:38 pm, Wed., May 22, 2013

  • 7/28/2019 N-S CIM Presentation

    18/47

    18

  • 7/28/2019 N-S CIM Presentation

    19/47

    19

  • 7/28/2019 N-S CIM Presentation

    20/47

    20

  • 7/28/2019 N-S CIM Presentation

    21/47

    21

  • 7/28/2019 N-S CIM Presentation

    22/47

    22

  • 7/28/2019 N-S CIM Presentation

    23/47

    23

  • 7/28/2019 N-S CIM Presentation

    24/47

    24

  • 7/28/2019 N-S CIM Presentation

    25/47

    25

  • 7/28/2019 N-S CIM Presentation

    26/47

    26

  • 7/28/2019 N-S CIM Presentation

    27/47

    27

    East-West Improvements

    Total Over $ 1.2 Billion Allocated in Six Year Program

    VA 7 Widen to 6 LanesReston Ave. to Jarrett Valley Dr.

    In Design

    I-66 Spot Improvement 2Westmoreland St to Haycock Rd

    In Design

    Metro Silver LineEast Falls Church to Route 772

    Under Construction

    US 50 Widen to 6 LanesPoland Rd (VA 742) to VA 28

    Under Construction

    I-66 / VA 28 InterchangeIn Design

    I-66 Widening (1 HOV + 1 SOV)US 15 to US 29

    Design / Build - Advertised

    I-66 / US 15 InterchangeDesign/Build

    US 29 / Linton Hall Rd InterchangeUnder Construction

    VA 234 Bypass / Balls Ford Rd Relocated InterchangeIn Study

    I-66 EIS (Tier 1)US 15 to I-495

    Study

    I-66 Bus on Shoulder PilotI-495 to Roosevelt Bridge

    In Design

    I-66 ATMUS 29 to T R Bridge

    In Design

    Dulles LoopRt 606/VA 28/US 50

    In Design

  • 7/28/2019 N-S CIM Presentation

    28/47

    Composite Studies Map

    28

  • 7/28/2019 N-S CIM Presentation

    29/47

    North-South Corridor Master Plan Study45-mile multi-modal transportation network between I-95 inPrince William County and Rte. 7 in Loudoun County

    29

  • 7/28/2019 N-S CIM Presentation

    30/47

    Manassas National Battlefield Park BypassEIS and Location Study

    Initiated as directed byCongress in 1988legislation to developalternatives that allowfor the closure ofRoutes 29 and 234 to

    preserve theBattlefield

    30

  • 7/28/2019 N-S CIM Presentation

    31/47

    Dulles Air Cargo, Passenger and MetroAccess Highway Environmental Assessmentand Location Study

    Enhance themovement of

    people, passenger

    services and aircargo traffic toDullesInternationalAirport

    31

  • 7/28/2019 N-S CIM Presentation

    32/47

    Bi-County Parkway(Tri-County Parkway)

    EIS & Location Study

    New north-south

    link between PrinceWilliam County andLoudoun County

    32

  • 7/28/2019 N-S CIM Presentation

    33/47

    33

    Today

  • 7/28/2019 N-S CIM Presentation

    34/47

    34

    2040 NoBuild

    2040Build

  • 7/28/2019 N-S CIM Presentation

    35/47

    Will there be tolls on the Bi-CountyParkway?

    The Bi-County Parkway willnot have tolls.

    35

  • 7/28/2019 N-S CIM Presentation

    36/47

    Will the Bi-County Parkway destroy theRural Crescent by inducing development?

    No, the road will not change localland use restrictions

    The road will be limited-accessThe only access points in the Rural

    Crescent will be at I-66, Route 29,

    existing Route 234 west of the

    battlefield

    36

  • 7/28/2019 N-S CIM Presentation

    37/47

    When will the Bi-County Parkwayconstruction begin?

    There is no Construction Schedule VDOT needs to complete the EIS FHWA needs to issue Record of

    Decision

    $12 million is available for design37

  • 7/28/2019 N-S CIM Presentation

    38/47

    Will Route 234 through the Park closewith the construction of the Bi-County

    Parkway?

    Route 234 will be widened andrelocated to the west of Manassas

    National Battlefield Park

    The segment of Route 234 currentlylocated in the Park would close to

    through traffic but still remain open foraccess to private property

    38

  • 7/28/2019 N-S CIM Presentation

    39/47

    Will Route 29 through the ManassasNational Battlefield Park close with

    construction of the Bi-County Parkway?

    No The Manassas National Battlefield

    Bypass will relocate Route 29, when it isbuilt

    No funding for construction of theMNBPB has been identified

    39

  • 7/28/2019 N-S CIM Presentation

    40/47

    Will there be traffic-calming on Route29?

    Yes, VDOT will design and construct at least$300,000 of traffic-calming measures

    Traffic on Route 29 will not be restricted Project is solely intended to maintain safe

    travel and preserve the parks historiccharacter

    Work would be completed prior to openingthe Bi-County Parkway

    Project will be open to public involvement40

  • 7/28/2019 N-S CIM Presentation

    41/47

    Will Pageland Lane remain open tothrough traffic

    Yes

    41

  • 7/28/2019 N-S CIM Presentation

    42/47

    Wont the historic Civil War Battlefieldsbe destroyed?

    The Battlefield will be enhanced by removing a majortraffic bottleneck at the intersection of Routes 29 and234 at the Stone House

    The National Park Service supports the Bi-CountyParkway at the proposed location because traffic willbe relocated from the core of the Battlefield to theParks periphery

    The key to minimizing and mitigating potentialadverse effects of the Bi-County Parkway on historicresources is laid out in the ProgrammaticAgreement, which implements regulations andmeasures agreed upon by the signatory parties

    42

    What about access to Sudley

  • 7/28/2019 N-S CIM Presentation

    43/47

    What about access to SudleyMethodist Church and other propertyowners on existing Route 234?

    All local property owners will haveaccess to their properties during andafter the construction of the Bi-CountyParkway

    Directional signage to Sudley MethodistChurch will be provided on the Bi-CountyParkway

    43

  • 7/28/2019 N-S CIM Presentation

    44/47

    What about Route 234 South of I-66

    VDOT is studying projects to gradeseparate Route 234 at Balls Ford Roadand Prince William Parkway

    While Prince William CountysComprehensive Plan calls Route 234 to

    be six lanes from I-95 to I-66, there areno formal plans or funding to widen theroad

    44

  • 7/28/2019 N-S CIM Presentation

    45/47

    What traffic volumes are anticipated for theBi-County Parkway?

    In 202022,000 to 42,000 vehicles a day

    In 204045,000 to 61,000 vehicles a day

    45

    What happens if the Bi County Parkway and the

  • 7/28/2019 N-S CIM Presentation

    46/47

    What happens if the Bi-County Parkway and theMNBPB are not built?

    46

  • 7/28/2019 N-S CIM Presentation

    47/47

    Questions ?

    Meeting [email protected]

    Include in subject line:

    North-South Corridor Meeting