H O J A R E S U M E N PROYECTO : CONDOMINIO "SOL DE CHOSICA" PROPIETARIO : CONSTRUCTORA ARMI - ESTRATEGIA SOLUCIONES UBICACIÓN : Panamericana Norte KM. 777 , Fundo Chacupe, parcela 10274-I Dist..La Victoria, Prov. Chiclayo, Dpto. Lambayeque FECHA : AGOSTO 2014 P R E S U P U E S T O BLOQUE tipo C - 12 Dptos 01 ESTRUCTURAS ………………………………………………………………. S/. 694,837.34 02 ARQUITECTURA ……………………………………………………………… S/. 502,484.53 03 INSTALACIONES SANITARIAS ………………………………………………… S/. 53,048.33 04 INSTALACIONES ELECTRICAS ………………………………………………… S/. 89,848.42 TOTAL PRESUPUESTO S/. 1,340,218.62 TOTAL COSTO DIRECTO S/. 946,482.07 Gastos Generales 10.00% S/. 94,648.21 Utilidad 10.00% S/. 94,648.21 SUB TOTAL PRESUPUESTO 1,135,778.49 I.G.V. 18.00% 204,440.13 TOTAL PRESUPUESTO S/. 1,340,218.62

Planeamiento BLOQ. C - 12 DPTOS

Embed Size (px)

DESCRIPTION

Formato

Citation preview

Page 1: Planeamiento BLOQ. C - 12 DPTOS

H O J A R E S U M E N

PROYECTO : CONDOMINIO "SOL DE CHOSICA"

PROPIETARIO : CONSTRUCTORA ARMI - ESTRATEGIA SOLUCIONES

UBICACIÓN : Panamericana Norte KM. 777 , Fundo Chacupe, parcela 10274-I

Dist..La Victoria, Prov. Chiclayo, Dpto. Lambayeque

FECHA : AGOSTO 2014

P R E S U P U E S T OBLOQUE tipo C - 12 Dptos

01 ESTRUCTURAS ………………………………………………………………. S/. 694,837.34

02 ARQUITECTURA ……………………………………………………………… S/. 502,484.53

03 INSTALACIONES SANITARIAS ………………………………………………… S/. 53,048.33

04 INSTALACIONES ELECTRICAS ………………………………………………… S/. 89,848.42

TOTAL PRESUPUESTO S/. 1,340,218.62

TOTAL COSTO DIRECTO S/. 946,482.07

Gastos Generales 10.00% S/. 94,648.21

Utilidad 10.00% S/. 94,648.21

SUB TOTAL PRESUPUESTO 1,135,778.49

I.G.V. 18.00% 204,440.13

TOTAL PRESUPUESTO S/. 1,340,218.62

Page 2: Planeamiento BLOQ. C - 12 DPTOS

PRESUPUESTO BLOQUE tipo C PROYECTO : CONDOMINIO "SOL DE CHOSICA"

PRESUPUESTO : 01 ESTRUCTURAS

FECHA : AGOSTO 2014

ITEM DESCRIPCION UNID CANT. P.U. S/. PARCIAL TOTAL

1.00 OBRAS Y TRABAJOS PRELIMINARES

1.02 CASETA P/OFICINA, GUARDIANIA Y DEPOSITO M2 1.90 197.14 374.57

1.03 BAÑOS Y DUCHAS PROVISIONALES PARA LA OBRA mes 0.56 726.32 406.74

1.05 TRANSPORTE DE MATERIALES Y EQUIPOS GLB 0.50 4,633.20 2,316.60

1.06 TRAZO Y REPLANTEO C/ EQUIPO M2 778.44 1.28 996.40 4,094.31

2.00 MOVIMIENTO DE TIERRAS

2.01 EXCAV. PARA CISTERNA T.N. H=MAS 2.00M. PROF M3 68.44 43.89 3,003.83

EXCAV. MASIVA p/PLATEA CIM. c/CARGAD. FRONT. 100-125 HP M3 375.84 7.90 2,969.14

2.02 RELLENO COMPACTADO MATERIAL DE PRESTAMO M3 469.80 35.29 16,579.24

ACARREO INTERNO, MAT. PROCEDENTE DE EXCAV. M3 88.97 14.35 1,276.72

2.03 ELIMIN. MAT. c/CARGAD. 125 HP y VOLQ. 10 M3 D=05 KM M3 577.56 19.34 11,170.01 34,998.94

3.00 OBRAS DE CONCRETO SIMPLE

3.01 FALSA ZAPATA - CONCRETO F´c 100 KG/CM2 + 30% PG M3 39.20 175.45 6,877.64 6,877.64

4.00 OBRAS DE CONCRETO ARMADO

4.01 PLATEA CIMENTACION - CONCRETO F'c 175 KG/CM2 M3 62.64 290.67 18,207.57

PLATEA CIMENTACION - ENCOF. Y DESENCOF. NORMAL M2 42.00 33.67 1,414.14

PLATEA CIMENTACION - ACERO Fy 4200 KG/CM2 KG 3,145.32 4.66 14,657.19

4.02 VIGA CIMENTACION - CONCRETO F'c 175 KG/CM2 M3 38.22 290.67 11,109.41

VIGA CIMENTACION - ENCOF. Y DESENCOF. NORMAL M2 258.78 33.67 8,713.12

VIGA CIMENTACION - ACERO Fy 4200 KG/CM2 KG 3,779.04 4.66 17,610.33

4.03 TABIQUE Y PLACA - CONCRETO F'c 175 KG/CM2 M3 135.24 404.90 54,758.68

TABIQUE Y PLACA - ENCOF. Y DESENCOF. NORMAL M2 2,704.80 35.13 95,019.62

TABIQUE Y PLACA - ACERO Fy 4200 KG/CM2 KG 10,906.44 4.66 50,824.01

4.04 COLUMNA - CONCRETO F'c 175 KG/CM2 M3 2.76 404.90 1,117.52

COLUMNA - ENCOF. Y DESENCOF. NORMAL M2 52.92 35.13 1,859.08

COLUMNA - ACERO Fy 4200 KG/CM2 KG 430.20 4.66 2,004.73

4.05 VIGA - CONCRETO F'c 175 KG/CM2 M3 21.96 330.81 7,264.59

VIGA - ENCOF. Y DESENCOF. NORMAL M2 373.80 40.45 15,120.21

VIGA - ACERO Fy 4200 KG/CM2 KG 3,634.92 4.66 16,938.73

4.06 LOSA MACIZA - CONCRETO F'c 175 KG/CM2 M3 99.84 330.81 33,028.07

LOSA MACIZA - ENCOF. Y DESENCOF. NORMAL M2 768.00 30.49 23,416.32

LOSA MACIZA - ACERO Fy 4200 KG/CM2 KG 5,398.80 4.66 25,158.41

4.07 ESCALERA - CONCRETO F'c 175 KG/CM2 M3 23.81 404.73 9,636.62

ESCALERA - ENCOF. Y DESENCOF. NORMAL M2 180.72 52.12 9,419.13

ESCALERA - ACERO Fy 4200 KG/CM2 KG 1,052.01 4.66 4,902.37

4.08 CISTERNA - CONCRETO F'c 175 KG/CM2 M3 13.23 404.73 5,354.58

CISTERNA - ENCOF.Y DESENCOF.NORMAL M2 49.23 31.27 1,539.42

CISTERNA - ACERO Fy 4200 KG/CM2 KG 905.95 4.66 4,221.73

4.09 TECHO 3°P Y SOPORTE TANQUES - CONCRETO F'c 175 KG/CM2 M3 9.13 330.81 3,020.30

TECHO 3° P Y SOPORTE TANQUES - ENCOF. Y DESENCOF. NORMAL M2 142.60 37.79 5,388.85

TECHO 3° P Y SOPORTE TANQUES - ACERO Fy 4200 KG/CM2 KG 649.94 4.66 3,028.72 444,733.45

Total Costo Directo 490,704.34

Gastos Generales 10% 49,070.43Utilidades 10% 49,070.43

Subtotal del Presupuesto 588,845.20Imp. Gral. a las Ventas 18% 105,992.14

TOTAL PRESUPUESTO S/. 694,837.34

Page 3: Planeamiento BLOQ. C - 12 DPTOS

CALCULO DE TIEMPOS EN DIAS POR PARTIDAS

METRADO N° Cuadrilla Cptz. Op. Of. Pe. Rend. Tu Tp

1.90

0.56

0.50

778.44 1.00 0.10 1.00 1.00 320.00 2.43

68.44 2.00 0.10 1.00 2.90 11.80 1.31

375.84 1.00 0.10 1.00 80.75 4.65 6.29

469.80 1.00 0.10 1.00 2.00 51.00 9.21 7.54

88.97 1.00 0.10 1.00 8.68 10.25 4.24

577.56 1.00 1.00 433.60 1.33 3.84

39.20 1.00 0.20 2.00 1.00 8.00 20.00 1.96 2.49

62.64 1.00 0.20 2.00 2.00 8.00 17.00 3.68

42.00 4.00 0.10 1.00 1.00 13.88 0.76 Cuadrilla A3145.32 4.00 0.10 1.00 1.00 255.00 3.08 Cuadrilla A

38.22 1.00 0.20 2.00 2.00 8.00 17.00 2.25

258.78 3.00 0.10 1.00 1.00 13.55 6.37 Cuadrilla B3779.04 4.00 0.10 1.00 1.00 255.00 3.70 Cuadrilla A135.24 1.00 0.20 2.00 2.00 8.00 8.25 16.39

2704.80 4.00 0.10 1.00 1.00 15.00 45.08 Cuadrilla B + (1)10906.44 3.00 0.10 1.00 1.00 255.00 14.26 Cuadrilla B

2.76 1.00 0.20 2.00 2.00 8.00 8.25 0.33

52.92 4.00 0.10 1.00 1.00 15.00 0.88 Cuadrilla A430.20 4.00 0.10 1.00 1.00 255.00 0.42 Cuadrilla A21.96 1.00 0.20 2.00 2.00 12.00 16.00 1.37

373.80 8.00 0.10 1.00 1.00 14.00 3.34 Cuadrilla A + Cuadrilla B + (1)3634.92 4.00 0.10 1.00 1.00 255.00 3.56 Cuadrilla B + (1)

99.84 1.00 0.20 2.00 2.00 12.00 16.00 6.24

768.00 6.00 0.10 1.00 1.00 17.00 7.53 Cuadrillla C5398.80 4.00 0.10 1.00 1.00 255.00 5.29 Cuadrilla A

23.81 1.00 0.20 2.00 2.00 8.00 7.70 3.09

180.72 4.00 0.10 1.00 1.00 8.70 5.19 Cudarilla A1052.01 4.00 0.10 1.00 1.00 255.00 1.03 Cudarilla A

13.23 1.00 0.20 2.00 2.00 8.00 7.70 1.72

49.23 4.00 0.10 1.00 1.00 16.00 0.77 Cuadrilla A905.95 4.00 0.10 1.00 1.00 255.00 0.89 Cuadrilla A

9.13 1.00 0.20 2.00 2.00 12.00 16.00 0.57

142.60 1.00 0.10 1.00 1.00 13.20 10.80 Cuadrilla A649.94 4.00 0.10 1.00 1.00 255.00 0.64 Cuadrilla A

FierrosEncofrados

Page 4: Planeamiento BLOQ. C - 12 DPTOS

14541.3614711.32

654.373150.48

768.00

Page 5: Planeamiento BLOQ. C - 12 DPTOS

PRESUPUESTO BLOQUE tipo C PROYECTO : CONDOMINIO "SOL DE CHOSICA"

PRESUPUESTO : 02 ARQUITECTURA

FECHA : AGOSTO 2014

ITEM DESCRIPCION UNID CANT. P.U. S/. PARCIAL TOTAL

1.00 REVOQUES, ENLUCIDOS Y MOLDURAS

TARRAJEO COLUMNAS C:A 1:5 E=1.5CM M2 47.64 14.15 674.11

TARRAJEO VIGAS C:A 1:5 E=1.5CM M2 336.48 18.73 6,302.27

TARRAJEO MUROS D CONCRETO C:A 1:5 E=1.5CM M2 2,434.32 10.64 25,901.16

TARRAJEO CON IMPERMEABILIZANTE MEZC. C:A 1:5 E=2.0 CM M2 59.12 17.94 1,060.61

TARRAJEO FROTCH. GRADAS ESCALERA C:A 1:4 E=3CM ML 200.40 14.19 2,843.68

TARRAJEO FROTCH. DESCANSO ESCALERA C:A 1:4 E=3CM M2 23.25 14.19 329.92

VESTIDURA DERRAMES A=0.10M C:A 1:5 E=2.0CM ML 746.64 6.41 4,785.96 41,897.71

2.00 CIELORASOS

TARRAJEO CIELORASO C:A 1:5 C/CINTAS E=1.5CM M2 768.00 16.23 12,464.64

VESTIDURA FONDO ESCALERA C:A 1:5 E=1.5CM M2 111.60 13.83 1,543.43 14,008.07

3.00 PISOS Y PAVIMENTOS

CONTRAPISO E=40 MM MEZC. 1:5 M2 657.96 13.33 8,770.61

PISO DE MADERA LAMINADA DE 11MM (dormitorios) M2 286.08 42.28 12,095.46

PISO DE CERAMICA 40x40CM (sala-com, cocin, baños y pasad 3°P) M2 371.88 37.63 13,993.84 34,859.91

4.00 CONTRAZOCALOS Y ZOCALOS

CONTRAZOCALO DE MADERA CEDRO 1/2"x 4" c/RODON 3/4" (dormit) ML 370.80 7.06 2,617.85

CONTRAZOCALO DE CERAMICA H=10CM (sala-com,cocina y pasad 3°P) ML 313.08 10.20 3,193.42

ZOCALO DE CERAMICA 40x40CM (cocina y baños) M2 278.40 37.62 10,473.41 16,284.68

5.00 REVESTIMIENTOS GRADAS Y ESCALERAS

REVEST GRADAS ESCALERA C/CERAMICA ML 200.40 37.62 7,539.05

REVEST DESCANSO ESCALERA C/CERAMICA M2 23.25 37.62 874.67

CONTRAZOC. COST. ESCALERA C/CERAMICA H=10CM ML 288.00 10.20 2,937.60

CANTONERA DE ALUMINIO DE 11/2" x 11/4" ML 200.40 8.75 1,753.50 13,104.82

6.00 CUBIERTAS

CUBIERTA LADR. PASTEL 25x25 ASENT. MEZC. 1:5, 1.5 CM M2 4,856.25 21.06 102,272.63 102,272.63

7.00 CARPINTERIA DE MADERA

PUERTA INTERIOR CONTRAPLACADA inc./MARCOS M2 158.76 132.68 21,064.28

PUERTA CORREDIZA PARA CLOSETS M2 48.00 119.04 5,713.92

PUERTA EXTERIOR MACIZA C/TABLEROS CEDRO inc. MARCOS M2 25.20 292.14 7,361.93

MUEBLE ALTO COCINA c/TABLERO POSTFORM. PTA. MELAM ML 18.00 234.19 4,215.42

MUEBLE BAJO DE COCINA c/TABLERO REVEST. GRANITO ML 30.00 548.13 16,443.90 54,799.45

8.00 CARPINTERIA METALICA

PASAMANO / BARANDA C/TUB F.N. 2"+3 LIN Ø11/4" ML 64.80 63.88 4,139.42

ESCALERA DE GATO CON TUBOS FO. NO. (cisternas y tanq. Elev.) ML 15.00 38.05 570.75 4,710.17

9.00 CERRAJERIA

BISAGRA CAPUCHINA ALUNINIZADA DE 3" PZA 216.00 5.75 1,242.00

BISAGRA ALUMINIZADA PESADA DE 4" PZA 36.00 6.84 246.24

CERRADURA PTA PRINCIPAL INGRESO DPTO PZA 12.00 57.30 687.60

CERRADURA PARA PUERTA INTERIOR PZA 60.00 33.16 1,989.60

CERRADURA PARA PUERTA DE BAÑO PZA 24.00 23.40 561.60

TIRADOR PARA PUERTA DE CLOSETS PZA 12.00 23.40 280.80 5,007.84

10.00 VIDRIOS, CRISTALES Y SIMILARES

VENTANA VIDRIO 4mm c/SISTEMA CORREDIZO M2 221.64 54.07 11,984.07 11,984.07

11.00 PINTURA

PINTURA c/EMPAST. CIELORAS,VIGAS, FOND ESCAL. LATEX 2M c/IMPRIM. M2 1,216.08 5.93 7,211.35

PINTURA c/EMPASTE MUROS INTERIORES LATEX 2M c/IMPRIM. M2 2,233.76 5.93 13,246.20

PINTURA MUROS EXTERIORES LATEX 2M c/IMPRIM. M2 243.43 6.40 1,557.95

PINTURA EN CONTRAZOCALOS CON BARNIZ 2M ML 370.80 2.22 823.18

PINTURA EN PUERTAS DE MADERA c/BARNIZ 2M M2 463.92 9.05 4,198.48

PINTURA EN PASAM. METAL c/ZINCROMATO y ESMALTE 2M ML 64.80 6.67 432.22 27,469.38

12.00 APARATOS Y ACCESORIOS SANITARIOS

INODORO TOP PIECE BLANCO STDR inc ACCES y VALV PZA 24.00 155.38 3,729.12

ASIENTO y TAPA W.C.PLAST.BLANCO inc/BISAG JGO 24.00 26.66 639.84

LAVATORIO + PEDESTAL MANANTIAL BLANCO STDR inc ACCES PZA 24.00 79.45 1,906.80

LAVADERO COCINA AC.SAT.1POZ c/ESCURR 19"x37" inc ACCES PZA 12.00 172.28 2,067.36

LAVADERO ROPA GRANITO GRIS 0.60x1.00 c/MANDIL inc ACCES PZA 6.00 79.64 477.84

SARDINEL DUCHA ALBAÑILERIA REVEST c/CERAMICA ML 30.00 56.35 1,690.50

JABONERA SIMPLE 15x15 LOSA BLANCA STDR PZA 24.00 9.81 235.44

PAPELERA LOSA BLANCA c/TUBO RESORTE STDR PZA 24.00 9.81 235.44

PAR TOALLERO LOSA BLANCA c/BARRA PLASTICA STDR PZA 24.00 11.70 280.80

GRIFERIA CROMADA 1 LLAVE p/LAVADERO DE COCINA PZA 12.00 26.39 316.68

GRIFERIA DE BRONCE 1 LLAVE p/LAVADERO DE ROPA PZA 6.00 15.49 92.94

MEZCLADORA CROMADA 2 LLAVES p/LAVATORIO PZA 24.00 166.09 3,986.16

MEZCLADORA CROMADA 2 LLAVES p/DUCHA PZA 24.00 229.28 5,502.72

COLOCACION DE APARATOS SANITARIOS PZA 90.00 58.65 5,278.50

COLOCACION DE ACCES Y GRIFERIA SANITARIA PZA 138.00 14.66 2,023.08 28,463.22

Total Costo Directo 354,861.95

Gastos Generales 10% 35,486.20Utilidades 10% 35,486.20

Subtotal del Presupuesto 425,834.35Imp. Gral. a las Ventas 18% 76,650.18

TOTAL PRESUPUESTO S/. 502,484.53

Page 6: Planeamiento BLOQ. C - 12 DPTOS

PRESUPUESTO BLOQUE tipo C PROYECTO : CONDOMINIO "SOL DE CHOSICA"

PRESUPUESTO : 03 INSTALACIONES SANITARIAS

FECHA : AGOSTO 2014

ITEM DESCRIPCION UNID CANT. P.U. S/. PARCIAL TOTAL

1.00 SISTEMA DE DESAGUE1.01 SALIDAS, TUBERIAS Y ACCESORIOS DE DESAGUE

SALIDA DE DESAGUE PVC SAL LIV. DE 2" PTO 72.00 48.52 3,493.44

SALIDA DE DESAGUE PVC SAL LIV. DE 4" PTO 24.00 64.31 1,543.44

SALIDA DE VENTILACION PVC SAL LIV. DE 2" PTO 72.00 48.52 3,493.44

SALIDA DE VENTILACION PVC SAL LIV. DE 4" PTO 12.00 64.31 771.72

TUBERIA PVC SAL LIV. p/DESAGUE DE 2" ML 27.00 12.33 332.91

TUBERIA PVC SAL LIV. p/DESAGUE DE 3" ML 73.80 13.38 987.44

TUBERIA PVC SAL LIV. p/DESAGUE DE 4" ML 88.80 14.90 1,323.12

TUBERIA PVC SAL LIV. p/DESAGUE DE 6" ML 42.00 21.74 913.08

CODO DE PVC - SAL 2" x 90° UND 12.00 0.96 11.52

CODO DE PVC - SAL 3" x 90° UND 6.00 1.82 10.92

CODO DE PVC - SAL 4" x 90° UND 12.00 2.68 32.16

TEE SANITARIA PVC-SAL 2"x 2" UND 6.00 1.37 8.22

TEE SANITARIA PVC-SAL 3"x 3" UND 12.00 2.39 28.68

TEE SANITARIA PVC-SAL 4"x 4" UND 24.00 4.07 97.68

TRAMPA "P" DE PVC - SAL x 2" UND 12.00 2.92 35.04

SUMIDERO DE BRONCE 2" (c/TRAMPA) UND 42.00 26.70 1,121.40

SUMIDERO DE BRONCE 3" (c/TRAMPA) UND 6.00 32.28 193.68

REGISTRO BRONCE ROSCADO DE PISO 2" UND 6.00 22.39 134.34

REGISTRO BRONCE ROSCADO DE PISO 4" UND 24.00 47.22 1,133.28

SOMBRERO DE VENTILACION PVC 2" UND 24.00 8.76 210.24

SOMBRERO DE VENTILACION PVC 4" UND 12.00 10.73 128.76

CAJA CIEGA 12"x 12" CON REGISTRO DE 4" UND 6.00 57.02 342.12

CAJA CIEGA 12"x 24" CON REGISTRO DE 6" UND 6.00 94.21 565.26

ROMPE AGUA EN CISTER.y TQ. ELEV. HAST. TUB. 1" UND 2.00 12.44 24.88

ROMPE AGUA EN CISTER.y TQ. ELEV. HAST. TUB. 2" UND 4.00 15.87 63.48

MARC-TAPA FoNo 0.60x0.60m PARA CISTERNA UND 2.00 76.68 153.36 17,153.61

2.00 SISTEMA DE AGUA FRIA Y CALIENTE

SALIDA AGUA FRIA PVC c/TUB./ACCS. SP 1/2" PTO 96.00 48.02 4,609.92

SALIDA AGUA CALIENTE CPVC c/TUB.y ACCS. SP 1/2" PTO 48.00 60.57 2,907.36

TUBERIA PVC CL-10 SP p/AGUA FRIA D=1/2" ML 15.00 7.23 108.45

TUBERIA PVC CL-10 SP p/AGUA FRIA D=3/4" ML 53.10 7.53 399.84

TUBERIA PVC CL-10 SP p/AGUA FRIA D=11/4" ML 13.32 8.18 108.96

TUBERIA PVC CL-10 SP p/AGUA FRIA D=11/2" ML 1.92 9.36 17.97

TUBERIA PVC CL-10 SP p/AGUA FRIA D=2" ML 7.62 11.56 88.09

CODO DE PVC SIM.PRES 1/2" x 90° UND 36.00 0.88 31.68

CODO DE PVC SIM.PRES 3/4" x 90° UND 15.78 1.16 18.30

CODO DE PVC SIM.PRES 11/4" x 90° UND 3.78 2.06 7.79

CODO DE PVC SIM.PRES 11/2" x 90° UND 1.92 2.45 4.70

CODO DE PVC SIM.PRES 2" x 90° UND 3.78 3.95 14.93

TEE DE PVC SIM.PRES 1/2" x 1/2" UND 24.00 0.85 20.40

TEE DE PVC SIM.PRES 3/4" x 1/2" UND 24.00 1.07 25.68

TEE DE PVC SIM.PRES 3/4" x 3/4" UND 1.92 1.32 2.53

TEE DE PVC SIM.PRES 11/4" x 11/4" UND 1.92 2.82 5.41

TEE DE PVC SIM.PRES 11/2" x 11/2" UND 1.92 3.96 7.60

TEE DE PVC SIM.PRES 2" x 2" UND 0.96 5.43 5.21

VALVULA COMPUERTA TIPO BOLA DE 1/2" UND 48.00 42.42 2,036.16

VALVULA FLOTADOR c/BOLLA COBRE x 3/4" UND 2.00 57.08 114.16

CISTERNAS - TUB/ACCS PVC : IMPUL 11/4", SUCC 11/2", REBOS 2" CJTO 2.00 485.62 971.24

TANQUE+TAPA FIBRA D VIDRIO (POLIETILENO) 2.50M3 s/ACCS. UND 2.00 1,108.15 2,216.30

TANQUES - TUB / ACCS PVC : ALIMENT 11/4", REBOS 2" CJTO 2.00 446.13 892.26

EQUIPO BOMBEO AGUA 1.0HP Qmax=1.66 l.p.s. Hmax=26m CJTO 4.00 957.60 3,830.40

CAJA CONCRET c/MARC/TAPA FoGo p/MED.INT.DPTO x 1/2"-3/4" UND 12.00 44.88 538.56

MEDIDOR DE AGUA T.SEDAPAL x 3/4" p/INTERIOR DPTO. UND 12.00 110.50 1,326.00 20,309.90

Total Costo Directo 37,463.51

Gastos Generales 10% 3,746.35Utilidades 10% 3,746.35

Subtotal del Presupuesto 44,956.21Imp. Gral. a las Ventas 18% 8,092.12

TOTAL PRESUPUESTO S/. 53,048.33

Page 7: Planeamiento BLOQ. C - 12 DPTOS

PRESUPUESTO BLOQUE tipo C

PROYECTO : CONDOMINIO "SOL DE CHOSICA"

PRESUPUESTO : 04 INSTALACIONES ELECTRICAS

FECHA : AGOSTO 2014

ITEM DESCRIPCION UNID CANT. P.U. S/. PARCIAL TOTAL

1.00 INSTALACION ELECTRICA

1.01 SALIDA DE CENTRO DE LUZ Y BRAQUETS PTO 177.00 45.69 8,087.13

SALIDA PARA LUZ DE EMERGENCIA PTO 3.00 60.83 182.49

SALIDA p/TOMACORRIENTE DOBLE c/PTA.TIERRA PTO 269.00 61.88 16,645.72

SALIDA DE FUERZA PARA THERMA PTO 12.00 47.96 575.52

SALIDA DE FUERZA DESDE 1/2 HASTA 5HP PTO 4.00 69.67 278.68

1.02 INTERRUPTOR SIMPLE 6A 250 V UND 108.00 18.31 1,977.48

INTERRUPTOR TRIPLE 6A 250 V UND 12.00 23.49 281.88

CONMUTADOR BIPOLAR SIMPLE UND 1.00 23.06 23.06

CONMUTADOR BIPOLAR DOBLE UND 6.00 25.93 155.58

TOMACORRIENTE BIPOLAR SIMPLE p/LUZ EMERG. UND 3.00 17.74 53.22

TOMACORRIENTE BIPOLAR DOBLE c/PTA.TIERRA UND 269.00 20.76 5,584.44

PLACA DE SALIDA PARA THERMA UND 12.00 25.59 307.08

PLACA DE SALIDA PARA FUERZA 1/2HP - 5HP UND 4.00 31.34 125.36

POZO PUESTA A TIERRA (medidores 1° piso) UND 6.00 388.06 2,328.36

POZO PUESTA A TIERRA (del murete portamedidor) UND 2.00 582.09 1,164.18 37,770.18

2.00 INSTALACION COMUNICACIONES Y SEÑALES

2.01 SALIDA PARA TELEFONO EXTERNO PTO 24.00 31.05 745.20

SALIDA PARA INTERCOMUNICADOR (AUDIO) PTO 24.00 63.23 1,517.52

SALIDA PARA SEÑAL CABLE PTO 60.00 31.05 1,863.00

2.02 PLACA DE SALIDA PARA TELEFONO Y CABLE UND 84.00 19.93 1,674.12

PLACA DE SALIDA PARA INTERCOMUNIC (AUDIO) UND 24.00 67.67 1,624.08

2.03 EQUIPO LUZ de EMERGENCIA A BATERIAS (tipo seco recargable) UND 3.00 273.94 821.82 8,245.74

3.00 CANALIZACIONES Y/O TUBERIAS

TUBERIA PVC SEL ELECTRICA DE 3/4" ML 260.00 4.60 1,196.00 1,196.00

4.00 CAJAS DE PASE Y SALIDA

CAJA DE PASE FoGo OCTOG. LIV. 100x100x40mm UND 52.00 7.46 387.92

CAJA DE PASE FoGo CUADR. LIV. 150x150x100mm UND 96.00 16.48 1,582.08

CAJA DE PASE FoGo CUADR. LIV. 200x200x100mm UND 12.00 18.78 225.36

CAJA DE PASE FoGo CUADR. LIV. 250x250x100mm UND 6.00 25.84 155.04

CAJA DE PASE FoGo CUADR. LIV. 300x300x100mm UND 1.00 35.27 35.27

MURETE PARA BANCO DE MEDIDORES 1.50x1.80M UND 1.00 146.34 146.34 2,532.01

5.00 TABLEROS E INTERRUPTORES

TABLERO DISTRIB CAJA METALICA (ST-1, DPTOS) UND 12.00 67.50 810.00

TABLERO DISTRIB CAJA METALICA (TG-DPTOS) UND 12.00 169.23 2,030.76

TABLERO DISTRIB CAJA METALICA ( TSG ) UND 1.00 241.45 241.45

INTERRUPTOR TERMOMAG. MONOF. 2x15A UND 33.00 29.19 963.27

INTERRUPTOR TERMOMAG. MONOF. 2x20A UND 35.00 29.19 1,021.65

INTERRUPTOR TERMOMAG. MONOF. 2x30A UND 37.00 30.34 1,122.58

INTERRUP. TERMOMAG. DIFERENCIAL 2x20A UND 27.00 90.24 2,436.48 8,626.19

6.00 CONEX. RED EXTERNA (ALIMENTADORES )

ALIMENTADOR N2XH 2-1x4mm2+NH80 1x4mm2, PVC Ø1" ML 132.00 8.22 1,085.04

ALIMENTADOR N2XH 2-1x6mm2+ NH80 1x6mm2,Ø1" ML 312.00 9.67 3,017.04 4,102.08

7.00 ARTEFACTOS

ARTEF. FLUOR. CIRC. STDR. BE 1x22W BF (escalera comun) UND 5.00 43.59 217.95

ARTEF.SPOT LIGHT c/REJ. SEG. y LAMP.100W (voladiz techo 1° y 3°P) UND 12.00 41.28 495.36

ARTEF. BRAQ. GLOBO D.VIDRIO c/LAMP.100W (pared 3° P) UND 6.00 44.46 266.76 980.07

Total Costo Directo 63,452.27

Gastos Generales 10% 6,345.23Utilidades 10% 6,345.23

Subtotal del Presupuesto 76,142.73Imp. Gral. a las Ventas 18% 13,705.69

TOTAL PRESUPUESTO S/. 89,848.42