    Use Risk Management to Make SolidCommitments08OCT,2008

    Commentary onThe Art of Agile Development'sRisk

    Managementpractice.

    Makingand meetingcommitments. Over and over, when I ask executives

    what they want from their teams, I've found this to be one of the top

    priorities.

    That's why the Risk Management practice inThe Art of Agile

    Developmentis one of my favorites. It's all about being able to make and

    meet commitments, and we have three great tools in there: risk multipliers,

    risk-adjusted burn-up charts, and project-specific risks. Today, I'll show you

    how to use the first two to make solid commitments to your executives.

    Risk Multipliers

    Risk multipliers account for common risks, such as turnover, changing

    requirements, work disruption, and so forth. These risk multipliers allow you

    to set a date, estimate how many story points of work you'll get done, and

    be right. It's a simpler version of the risk curves you'll see in good books on

    estimating and project management.

    RISKMULTIPLIER

    CHANCE RIGOROUS PROCESS RISKY PROCESS DESCRIPTION

    10% 1 1 Ignore--almost impossible

    http://www.jamesshore.com/http://www.jamesshore.com/http://www.jamesshore.com/http://www.jamesshore.com/Blog/http://www.jamesshore.com/Blog/http://www.jamesshore.com/Blog/http://www.jamesshore.com/Blog/http://www.letscodejavascript.com/http://www.letscodejavascript.com/http://www.letscodejavascript.com/#demohttp://www.letscodejavascript.com/#demohttp://www.letscodejavascript.com/#demohttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/risk_management.htmlhttp://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/risk_management.htmlhttp://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Agile-Book/http://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.letscodejavascript.com/#demohttp://www.letscodejavascript.com/http://www.jamesshore.com/Blog/http://www.jamesshore.com/
  • 8/12/2019 Riesgo Agil

    2/11

    50% 1.4 2 Stretch goal--50/50 chance

    90% 1.8 4 Commitment--virtually certain

    (As we explain in the book, these multipliers are estimates gleaned from DeMarco &

    Lister's RISKOLOGY simulator and Todd Little's detailed analysis of hundreds of

    projects. I'm guessing somewhat at how accurately they apply to XP. The most

    accurate approach is to calculate your own risk multipliers from past project

    history, but most companies don't track that data.)

    The way this works is that you take your iteration velocity and extrapolate

    out to your delivery date. That's the best estimate of how many story points

    you'll finish under ideal circumstances. So if your velocity is 14 and you have

    ten iterations left, you predict that you'll finish 140 more story points beforeyou release.

    Then you apply the risk multipliers according to the type of process you're

    using. If you have a solid velocity and get everything"done done"every

    iteration, you get to use the "rigorous" column. Otherwise, you use the

    "risky" column.

    To continue the example, let's say your team has a rigorous approach. To

    make a commitment, you apply the multipliers, like this:

    CHANCE STORY POINTS FINISHED DESCRIPTION

    10% 140 (140 1) Ignore--almost impossible

    50% 100 (140 1.4) Stretch goal--50/50 chance

    90% 78 (140 1.8) Commitment--virtually certain

    This allows you to make commitments to stakeholders and executives. "Weare virtually certainto finish 78 more points by our release date, so

    we're committingto delivering features A, B, and C. We have a50-50

    chanceof completing 100 points, so we're planning on features X, Y, and Z

    as a stretch goal."

    The Risk-Adjusted Burn-Up Chart

    http://www.jamesshore.com/Agile-Book/done_done.htmlhttp://www.jamesshore.com/Agile-Book/done_done.htmlhttp://www.jamesshore.com/Agile-Book/done_done.htmlhttp://www.jamesshore.com/Agile-Book/done_done.html
  • 8/12/2019 Riesgo Agil

    3/11

    The risk-adjusted burn-up chart allows you to track your commitments

    alongside your progress. It's based on Phil Goodwin's burn-up chart, which is

    a variant of Scrum's burn-down chart. Here's how it works.

    Start by drawing a chart with iterations on the bottom and story points onthe left. Mark the release date with a dashed line, as shown.

    At the start of every iteration (typically, every week), plot two points on the

    chart. At the bottom of the chart, plot the number of story points that are

    "done done". At the top of the chart, plot the total story points--"done done"

    plus the number remaining in the plan. This gives you a standard burn-up

    chart.

    Now add the risk numbers. Calculate your probability of completing variousnumbers of story points using the risk multiplier approach described in the

    previous section, and then plot those numbers on a vertical line. You can

    either draw the vertical line on the release date and change it every week

    (as shown in the figure above), or you can draw it on the current iteration

    (as I'll show in a moment).

  • 8/12/2019 Riesgo Agil

    4/11

    The result is an information-rich chart that shows you three trends:

    1. Completion progress;2. Changes to the plan; and3. What you can commit to.

    Example

    Here's an extended example of these ideas in practice. Imagine a team of

    six programmers. They've been working together for a while now and have a

    solid velocity of 12. They start a new project that's due in six weeks. After

    playingthe planning game, they have a prioritized list ofminimum

    marketable featuresthat looks like this:

    FEATURE COST TOTAL

    A 34 34

    B 7 41

    C 13 54

    D 2 56

    E 6 62

    F 26 88

    Based on their past velocity of 12 and their history of getting iterations

    "done done," the team calculates the following estimates:

    10%: 72 (12 velocity 6 iterations 1 risk) 50%: 51 (12 velocity 6 iterations 1.4 risk) 90%: 40 (12 velocity 6 iterations 1.8 risk)

    They report this to their stakeholders by saying, "We committo delivering

    features A and B, and we'll work on feature C as a stretch goal. Features D

    and E are unlikely to make it, and we almost certainly won't have time to do

    feature F."

    http://www.jamesshore.com/Agile-Book/the_planning_game.htmlhttp://www.jamesshore.com/Agile-Book/the_planning_game.htmlhttp://www.jamesshore.com/Agile-Book/release_planning.htmlhttp://www.jamesshore.com/Agile-Book/release_planning.htmlhttp://www.jamesshore.com/Agile-Book/release_planning.htmlhttp://www.jamesshore.com/Agile-Book/release_planning.htmlhttp://www.jamesshore.com/Agile-Book/release_planning.htmlhttp://www.jamesshore.com/Agile-Book/release_planning.htmlhttp://www.jamesshore.com/Agile-Book/the_planning_game.html
  • 8/12/2019 Riesgo Agil

    5/11

    (Sorry about the image quality. Also, the 10% and 90% should be reversed.)

    Iteration 1

    The team signs up for 12 points and the iteration goes smoothly. They

    deliver 12 points. The customers leave the plan unchanged in hopes that the

    team's predictions are wrong. The team recalculates their risk-based

    projections:

    10%: 72 (12 finished + 12 velocity 5 iterations 1 risk)

    50%: 55 (12 finished + 12 velocity 5 iterations 1.4 risk) 90%: 45 (12 finished + 12 velocity 5 iterations 1.8 risk)

  • 8/12/2019 Riesgo Agil

    6/11

    (The 10% and 90% should be reversed in this picture.)

    Iteration 2

    It's a national holiday and most of the team is out for a few days this week.

    The team uses all of theirslackbut is unable to get everything done. They

    deliver 7 points, but they keep their projected velocity at 12, knowing that

    the holiday was an unusual event.

    10%: 67 (19 finished + 12 velocity 4 iterations 1 risk)

    50%: 53 (19 finished + 12 velocity 4 iterations 1.4 risk) 90%: 46 (19 finished + 12 velocity 4 iterations 1.8 risk)

    They report the news: "We are still committed to delivering features A and

    B, and feature C remains a reasonable stretch goal. Features E and F will

    definitely not be done and we're removing them from the plan."

    http://www.jamesshore.com/Agile-Book/slack.htmlhttp://www.jamesshore.com/Agile-Book/slack.htmlhttp://www.jamesshore.com/Agile-Book/slack.html
  • 8/12/2019 Riesgo Agil

    7/11

    (The 10% and 90% are correct in this picture and all the remaining ones.)

    Iteration 3 & 4

    Iterations three and four proceed without incident and the team delivers all

    12 points each time.

    10%: 67 (43 finished + 12 velocity 2 iterations 1 risk) 50%: 60 (43 finished + 12 velocity 2 iterations 1.4 risk) 90%: 56 (43 finished + 12 velocity 2 iterations 1.8 risk)

    The team reports, "Great news! The work's been proceeding smoothly and

    we've finished features A and B. We're now working on features C and D,

    and we're adding feature E back in as a further stretch goal."

  • 8/12/2019 Riesgo Agil

    8/11

    Iteration 5Disaster strikes! A critical database crashes and everyone is pulled to work

    on it. The team only delivers 6 points this iteration.

    10%: 61 (49 finished + 12 velocity 1 iteration 1 risk) 50%: 56 (49 finished + 12 velocity 1 iteration 1.4 risk) 90%: 55 (49 finished + 12 velocity 1 iteration 1.8 risk)

    The team's report: "Due to the unexpected problems this week, we're not

    going to get to feature E after all, and any problems on the scale of thisweek's will mean canceling feature D, too. However, we're committed to

    delivering feature C and we're going to do our best to get feature D done for

    you."

  • 8/12/2019 Riesgo Agil

    9/11

    Iteration 6No problems arise and the team gets all 12 points done, for a grand total of

    61 points completed. They finish features C and D and spend the extra

    points adding polish to existing features and documenting their work. Rather

    than being upset that the team didn't get the whole plan done, stakeholders

    are happy that their expectations were exceeded. Everyone gets a big raise

    and they all live happily ever after.

  • 8/12/2019 Riesgo Agil

    10/11

    The end.

    PS: One of the cool things about this technique is that it automatically

    accounts for Steve McConnell's famouscone of uncertainty. Look at the

    risk bars over time and you'll see how they become smaller and more certain

    as time progresses, just as McConnell predicts.

    Further Reading

    Estimate Inflation: A Cautionary Tale.A follow-up example that shows

    what not to do.

    HOMEBLOG|PERMANENT LINK

    I work with people who want to be great. People who are willing to take

    risks, rock the boat, and change their environment to maximize theirproductivity, throughput, and value. If that's youparticularly if you're in a

    http://www.construx.com/Page.aspx?hid=1648http://www.construx.com/Page.aspx?hid=1648http://www.construx.com/Page.aspx?hid=1648http://www.jamesshore.com/Blog/Estimate-Inflation-A-Cautionary-Tale.htmlhttp://www.jamesshore.com/Blog/Estimate-Inflation-A-Cautionary-Tale.htmlhttp://www.jamesshore.com/http://www.jamesshore.com/http://www.jamesshore.com/http://www.jamesshore.com/Blog/http://www.jamesshore.com/Blog/http://www.jamesshore.com/Blog/http://www.jamesshore.com/Blog/http://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/Use-Risk-Management-to-Make-Solid-Commitments.htmlhttp://www.jamesshore.com/Blog/http://www.jamesshore.com/http://www.jamesshore.com/Blog/Estimate-Inflation-A-Cautionary-Tale.htmlhttp://www.construx.com/Page.aspx?hid=1648
  • 8/12/2019 Riesgo Agil

    11/11