Presupuesto 0000001
Subpresupuesto 001 ESTRUCTURAS. Elaborado por ING. ENRIQUE SIGUAS CAMPOS.
Cliente CORPORACIN AMERICANA DE DESARROLLO. Direccin AV. NICOLS DE PIEROLA N 615
Contratista NQT CONTRATISTA S.A.C. rea Geogrfica 03
Lugar CUSCO-CUSCO-CUSCO. Fecha 14/12/2013
DESCRIPCIN UND. METRADO
PRECIO
UNITARIO
S/.
PARCIAL
S/.TOTAL
ESTRUCTURAS. 44,148.49
OBRAS DE CONCRETO ARMADO. 44,148.49
COLUMNAS. 12,357.01
PARA EL CONCRETO. 6,518.50
CONCRETO F'C=210 KG/CM2. EN COLUMNAS . M3. 20.00 325.92 6,518.50
PARA EL ENCOFRADO Y DESENCOFRADO. 2,561.24
ENCOFRADO Y DESENCOFRADO EN COLUMNAS. M2. 60.00 42.69 2,561.24
PARA LA ARMADURA DE ACERO. 3,277.28
ACERO FY=4,200KG/CM2. GRADO 60. EN COLUMNAS. KG. 800.00 4.10 3,277.28
VIGAS 8,657.80
PARA EL CONCRETO. 2,931.45
CONCRETO F'C=210 KG/CM2. EN VIGAS. M3. 10.00 293.15 2,931.45
PARA EL ENCOFRADO Y DESENCOFRADO. 3,268.39
ENCOFRADO Y DESENCOFRADO EN VIGAS. M2. 69.00 47.37 3,268.39
PARA LA ARMADURA DE ACERO. 2,457.96
ACERO FY=4,200KG/CM2. EN VIGAS. KG. 600.00 4.10 2,457.96
LOSAS. 23,133.68
LOSAS ALIGERADAS CONVENCIONALES. 23,133.68
CONCRETO F'C=210 KG/CM2. EN LOSA ALIGERADA
CONVENCIONAL.M3. 15.00 274.16 4,112.46
ENCOFRADO Y DESENCOFRADO EN LOSA ALIGERADA
CONVENCIONAL.M2. 300.00 33.68 10,104.19
ACERO FY=4,200KG/CM2. EN LOSA ALIGERADA
CONVENCIONAL.KG. 690.00 4.10 2,826.65
LADRILLO HUECO DE ARCILLA 0.15X0.30X0.30 m. PARA
LOSA ALIGERADA CONVENCIONAL.UND. 2,500.00 2.44 6,090.38
ARQUITECTURA. 8,783.63
MUROS Y TABIQUES DE ALBAILERA. 8,783.63
MUROS DE ALBAILERA CONFINADA. 8,783.63
MUROS DE LADRILLO KING KONG DE ARCILLA. 8,783.63
MURO DE LADRILLO KK 18 HCO. APAREJO SOGA. M2. 55.00 49.00 2,694.93
MURO DE LADRILLO KK 18 HCO. APAREJO CABEZA. M2. 80.00 76.11 6,088.70
52,932.12
5,293.21
6,351.85
64,577.18
11,623.89
76,201.07
OE.2.3.7.3.1.
OE.2.3.8.1.1.
OE.2.3.8.2.
OE.2.3.8.3.
OE.2.3.9.2.
OE.2.3.9.2.3.
OE.2.3.9.2.4.
OE.2.3.7.2.
OE.2.3.7.3.
OE.2.3.8.1.
OE.2.3.
GASTOS GENERALES (10%)
UTILIDAD (12%)
SUBTOTAL
IGV (18%)
TOTAL
OE.3.1.9.1.1.
OE.3.1.9.1.2.
COSTO DIRECTO
OE.3.
OE.3.1.9.
OE.3.1.9.1.
Presupuesto
ITEM
OE.2.
OE.3.1.
OE.2.3.7.
OE.2.3.8.
OE.2.3.9.
OE.2.3.7.1.1.
OE.2.3.7.2.1.
OE.2.3.8.2.1.
OE.2.3.8.3.1.
OE.2.3.9.2.1.
OE.2.3.9.2.2.
AMPLIACIN DE LAS OFICINAS DEL SEGUNDO PISO DE LA CORPORACIN AMERICANA DE DESARROLLO (CAD) SEDE CUSCO,
PROVINCIA Y REGIN DE CUSCO.
OE.2.3.7.1.
Acero de
Construccin
Liso
Acero de
Construccin
Corrugado
Agregado
Fino
Agregado
Grueso
Bloques y
Ladrillos
Cemento
Portland Tipo
I
Herramienta
Manual
ndice
General de
Precios al
Consumidor
Madera
Nacional para
Encofrado y
Carpintera
Mano de
Obra Inc.
Leyes
Sociales
Maquinaria y
Equipo
Nacional
02 03 04 05 17 21 37 39 43 47 48
OE.2.3.7.1.1. CONCRETO F'C=210 KG/CM2. EN COLUMNAS . M3. 20.00 325.92 6,518.50 184.80 527.00 2,888.88 66.24 2,503.17 348.40
OE.2.3.7.2.1. ENCOFRADO Y DESENCOFRADO EN COLUMNAS. M2. 60.00 42.69 2,561.24 73.20 63.44 1,155.84 1,268.76
OE.2.3.7.3.1. ACERO FY=4,200KG/CM2. GRADO 60. EN COLUMNAS. KG. 800.00 4.10 3,277.28 60.00 2,225.60 47.22 944.45
OE.2.3.8.1.1. CONCRETO F'C=210 KG/CM2. EN VIGAS. M3. 10.00 293.15 2,931.45 92.40 263.50 1,444.44 33.12 993.99 104.00
OE.2.3.8.2.1. ENCOFRADO Y DESENCOFRADO EN VIGAS. M2. 69.00 47.37 3,268.39 59.20 87.54 1,370.75 1,750.89
OE.2.3.8.3.1. ACERO FY=4,200KG/CM2. EN VIGAS. KG. 600.00 4.10 2,457.96 45.00 1,669.20 35.42 708.34
OE.2.3.9.2.1.CONCRETO F'C=210 KG/CM2. EN LOSA ALIGERADA
CONVENCIONAL.M3. 15.00 274.16 4,112.46 138.60 395.25 2,166.66 49.68 1,175.07 187.20
OE.2.3.9.2.2.ENCOFRADO Y DESENCOFRADO EN LOSA ALIGERADA
CONVENCIONAL.M2. 300.00 33.68 10,104.19 183.00 253.75 4,592.40 5,075.04
OE.2.3.9.2.3.ACERO FY=4,200KG/CM2. EN LOSA ALIGERADA
CONVENCIONAL.KG. 690.00 4.10 2,826.65 51.75 1,919.58 40.73 814.59
OE.2.3.9.2.4.LADRILLO HUECO DE ARCILLA 0.15X0.30X0.30 m. PARA
LOSA ALIGERADA CONVENCIONAL.UND. 2,500.00 2.44 6,090.38 4,305.50 1,784.88
OE.3.1.9.1.1. MURO DE LADRILLO KK 18 HCO. APAREJO SOGA. M2. 55.00 49.00 2,694.93 1.88 35.09 1,017.50 192.49 65.23 78.05 1,304.69
OE.3.1.9.1.2. MURO DE LADRILLO KK 18 HCO. APAREJO CABEZA. M2. 80.00 76.11 6,088.70 2.73 102.08 2,720.00 474.56 127.42 113.52 2,548.39
52,932.12 476.76 5,814.38 552.97 1,185.75 8,043.00 7,167.04 720.76 149.04 7,310.56 20,872.26 639.60
5,293.21 47.68 581.44 55.30 118.58 804.30 716.70 72.08 14.90 731.06 2,087.23 63.96
6,351.85 57.21 697.73 66.36 142.29 965.16 860.05 86.49 17.88 877.27 2,504.67 76.75
64,577.18 581.64 7,093.54 674.62 1,446.62 9,812.46 8,743.79 879.32 181.83 8,918.88 25,464.16 780.31
11,623.89 104.70 1,276.84 121.43 260.39 1,766.24 1,573.88 158.28 32.73 1,605.40 4,583.55 140.46
76,201.07 686.34 8,370.38 796.06 1,707.01 11,578.70 10,317.67 1,037.60 214.56 10,524.28 30,047.71 920.77
0.00901 0.10985 0.01045 0.02240 0.15195 0.13540 0.01362 0.00282 0.13811 0.39432 0.01208
0.901% 10.985% 1.045% 2.240% 15.195% 13.540% 1.362% 0.282% 13.811% 39.432% 1.208%
-0.901% 0.901% -1.045% 1.045% 0.282% -0.282%
-2.240% 2.240% 1.208% -1.208%
-2.852% 2.852%
0.000% 11.885% 0.000% 0.000% 15.195% 16.825% 0.000% 0.000% 16.663% 39.432% 0.000%
NO OK NO NO OK OK NO NO OK OK NO
NO OK NO NO OK OK NO NO OK OK NO
0.11885 0.15195 0.16825 0.16663 0.39432
Smbolo I.U. CoeficienteIncidencia
Especfica
J 47 0.394 100.00%
AA 02 0.119 92.42%
03 7.58%
B 17 0.152 100.00%
CAfAg 21 0.168 80.48%
04 6.21%
05 13.31%
MH 43 0.167 82.89%
37 17.11%
COEFICIENTES DE INCIDENCIA Y FRMULA POLINMICA.
Madera Nacional para Encofrado y Carpintera
Herramienta Manual
0.167xMHr/MHo
K= 0.394xJr/Jo + 0.119xAAr/AAo + 0.152xBr/Bo + 0.168xCAfAgr/CAfAgo + 0.167xMHr/MHo
Bloques y Ladrillos
0.152xBr/Bo
Cemento Portland Tipo I
Agregado Fino
Agregado Grueso
0.168xCAfAgr/CAfAgo
Concepto
Mano de Obra Inc. Leyes Sociales
0.394xJr/Jo
Acero de Construccin Liso
Acero de Construccin Corrugado
0.119xAAr/AAo
COEFICIENTES DE INCIDENCIA EN LA FRMULA POLINMICA
% INICIAL
% SALDO
AGRUPAMIENTO INICIAL
AGRUPAMIENTO FINAL
SUBTOTAL
IGV (18%)
TOTAL
COEFICIENTES DE INCIDENCIA
Descripcintem
ndice Unificado de Precios
COSTO DIRECTO
GASTOS GENERALES (10%)
UTILIDAD (12%)
Metrado
Parcial
S/.
Precio Unitario
S/.Unidad Cantidad
K= 0.394xJr/Jo + 0.119xAAr/AAo + 0.152xBr/Bo + 0.168xCAfAgr/CAfAgo + 0.167xMHr/MHo