Id Modo de tarea
Nombre de tarea Duracin Comienzo Fin PredecesorasCosto
1 MEJORAMIENTO DEL SISTEMA DE LA PLANTA DE TRATAMIETNO DE AGUA POTABLE DE LA LOCALIDAD DE SAN MARTIN DE PANGOA
60 das lun 01/06/15 mar 18/08/15
S/. 247,565.49
2 MEJORAMIENTO DE CAPTACION 52 das lun 01/06/15 vie 07/08/15 S/. 45,812.34
3 CONSTRUCCION DE GAVION 41 das lun 01/06/15 mi 22/07/15 S/. 39,325.63
4 TRABAJOS PRELIMINARES 1 da lun 01/06/15 lun 01/06/15 S/. 71.37
5 TRAZO Y REPLANTEO 1 da lun 01/06/15 lun 01/06/15 S/. 71.37
6 MOVIMIENTO DE TIERRAS 4 das mar 02/06/15 vie 05/06/15 S/. 222.57
7 EXCAVACION DE ZANJA MANUAL. 2 das mar 02/06/15 mi 03/06/15 5 S/. 126.66
8 ELIMINACION MATERIAL EXCEDENTE 2 das jue 04/06/15 vie 05/06/15 7 S/. 95.91
9 MURO DE GAVIONES 36 das sb 06/06/15 mi 22/07/15 S/. 39,031.69
10 CUERPO DE GAVION 18 das mar 30/06/15 mi 22/07/15 11 S/. 9,720.40
11 COLOCACION DE MALLA GALVANIZADA 18 das sb 06/06/15 mar 30/06/15 8 S/. 29,311.29
12 MURO DE CONTENCION 11 das mi 22/07/15 vie 07/08/15 3 S/. 1,835.84
13 TRABAJOS PRELIMINARES 1 da mi 22/07/15 jue 23/07/15 S/. 21.53
14 TRAZO Y REPLANTEO 1 da mi 22/07/15 jue 23/07/15 10 S/. 21.53
15 OBRAS DE CONCRETO SIMPLE 4 das jue 23/07/15 jue 30/07/15 S/. 848.45
16 CONCRETO CICLOPEO + 30% P.G. 1 da jue 30/07/15 jue 30/07/15 17 S/. 39.81
17 ENCOFRADO Y DESENCOFRADO NORMAL 3 das jue 23/07/15 lun 27/07/15 14 S/. 808.64
18 OBRAS DE CONCRETO ARMADO 7 das jue 30/07/15 vie 07/08/15 S/. 682.31
19 CONCRETO F'c=175 KG/CM2 2 das mi 05/08/15 vie 07/08/15 20 S/. 253.34
20 ACERO FY= 4200 KG/CM2 2 das lun 03/08/15 mi 05/08/15 21 S/. 31.79
21 ENCOFRADO Y DESENCOFRADO NORMAL 3 das jue 30/07/15 lun 03/08/15 17 S/. 397.18
22 REVESTIMIENTOS 2 das jue 30/07/15 vie 31/07/15 S/. 283.55
23 TARRAJEO EN INTERIORES Y EXTERIORES MEZCLA 1:5 E=2.00CM2 das jue 30/07/15 vie 31/07/15 17 S/. 283.55
24 TUBERIA DE LIMPIEZA 6 das lun 01/06/15 lun 08/06/15 3CC S/. 4,650.87
25 TRABAJOS PRELIMINARES 1 da lun 01/06/15 lun 01/06/15 S/. 11.71
26 TRAZO Y REPLANTEO 1 da lun 01/06/15 lun 01/06/15 5CC S/. 11.71
27 MOVIMIENTO DE TIERRAS 5 das mar 02/06/15 lun 08/06/15 S/. 302.46
28 EXCAVACION DE ZANJA MANUAL 1 da mar 02/06/15 mar 02/06/15 26 S/. 50.69
29 REFINE Y NIVELACION EN TERRENO NORMAL 1 da mi 03/06/15 mi 03/06/15 28 S/. 27.17
30 CAMA DE APOYO C / MATERIAL PROPIO ZARANDEADO E=0.10M1 da jue 04/06/15 jue 04/06/15 29 S/. 43.87
31 RELLENO Y COMPACTACION DE ZANJAS MAT. PROPIO1 da vie 05/06/15 lun 08/06/15 34 S/. 114.14
32 ELIMINACION MATERIAL EXCEDENTE 2 das mi 03/06/15 jue 04/06/15 28 S/. 66.59
33 SUMINISTRO E INSTALACION DE TUBERIAS 1 da vie 05/06/15 vie 05/06/15 S/. 1,208.74
34 INSTALACION DE TUBERIA PVC P/AGUA POTABLE, 14"1 da vie 05/06/15 vie 05/06/15 30 S/. 1,208.74
35 PRUEBA HIDRAULICA 1 da vie 05/06/15 lun 08/06/15 S/. 25.44
36 PRUEBA HIDRAULICA PARA AGUA POTABLE 1 da vie 05/06/15 lun 08/06/15 34 S/. 25.44
37 SUMINISTRO E INSTALACION DE ACCESORIOS 1 da sb 06/06/15 lun 08/06/15 S/. 3,102.52
38 REJA GALVANIZADA REMOVIBLE de 0.70x0.80m. 1 da sb 06/06/15 lun 08/06/15 34 S/. 123.21
39 REJA GALVANIZADA REMOVIBLE de 1.20x0.80m. 1 da sb 06/06/15 lun 08/06/15 38CC S/. 123.21
40 CODO PVC 45 x 14" 1 da sb 06/06/15 lun 08/06/15 38CC S/. 271.05
41 VALVULA COMPUERTA DE BRONCE DE 14" 1 da sb 06/06/15 lun 08/06/15 38CC S/. 1,817.89
42 CAJA DE VALVULA DE COMPUERTA 1 da sb 06/06/15 lun 08/06/15 38CC S/. 767.16
43 FLOCULADORES 29 das lun 01/06/15 mar 07/07/15 2CC S/. 89,240.77
44 MOVIMIENTO DE TIERRAS 6 das lun 01/06/15 lun 08/06/15 S/. 881.93
45 NIVELACION 2 das mi 03/06/15 jue 04/06/15 47 S/. 250.94
46 NIVELACION Y COMPACTACION MANUAL 2 das vie 05/06/15 lun 08/06/15 45 S/. 137.96
47 EXCAVACION DE ZANJA MANUAL 2 das lun 01/06/15 mar 02/06/15 5CC S/. 92.31
48 ELIMINACION MATERIAL EXCEDENTE 2 das mi 03/06/15 jue 04/06/15 47 S/. 400.72
49 OBRAS DE CONCRETO SIMPLE 2 das jue 04/06/15 lun 08/06/15 S/. 3,255.01
50 CONCRETO SOLADO 1:8 + 25 % P.M. 2 das jue 04/06/15 lun 08/06/15 48 S/. 3,255.01
51 OBRAS DE CONCRETO ARMADO 13 das lun 08/06/15 mi 24/06/15 S/. 69,567.41
52 CONCRETO FC=210 KG/CM2 4 das jue 18/06/15 mi 24/06/15 53 S/. 20,052.08
53 ENCOFRADO Y DESENCOFRADO 5 das vie 12/06/15 jue 18/06/15 54 S/. 34,689.44
TOPOGRAFO[29%],PEON[88%],ESTACION TOTAL,MADERA TORNILLO[1],WINCHA[1]
OPERARIO[2%],PEON[48%]
CAPATAZ[2%],PEON[18%]
PEON[33%],PIEDRA DE CANTO RODADO[18,330%]
OFICIAL[20%],PEON[40%],MALLA GALVANIZADA 3/4"[1]
TOPOGRAFO[9%],PEON[26%],ESTACION TOTAL,MADERA TORNILLO[1],WINCHA[1]
CEMENTO PORTLAND TIPO I (42.5KG)[1],OPERARIO[2%],OFICIAL[2%],PEON[16%],PIEDRA MEDIANA DE 6"[1],HORMIGON[1],AGUA[1]
OPERARIO[72%],OFICIAL[145%],ALAMBRE NEGRO RECOCIDO # 8[1],CLAVOS PARA MADERA C/C 2 1/2"[1],CLAVOS PARA MADERA C/C 3"[1],MADERA TORNILLO INC.CORTE P/ENCOFRADO[1]
CEMENTO PORTLAND TIPO I (42.5KG)[1],OPERARIO[13%],OFICIAL[7%],PEON[80%],GRAVA CANTO RODADO[1],ARENA GRUESA[1],AGUA[1]
OPERARIO[3%],OFICIAL[3%],ALAMBRE NEGRO RECOCIDO # 16[1],FIERRO CO. FY=4200 KG/CM2 G-60 3/8"[1]
OPERARIO[53%],OFICIAL[107%],ALAMBRE NEGRO RECOCIDO # 8[1],CLAVOS PARA MADERA C/C 2 1/2"[1],CLAVOS PARA MADERA C/C 3"[1],MADERA TORNILLO INC.CORTE P/ENCOFRADO[1]
OPERARIO[104%],PEON[52%],ARENA FINA[1],MADERA TORNILLO CEPILLADA[1]
TOPOGRAFO[4%],PEON[12%],ESTACION TOTAL,MADERA TORNILLO[1],WINCHA[1]
OPERARIO[2%],PEON[58%]
OPERARIO[12%],PEON[24%]
OPERARIO[10%],PEON[38%]
OPERARIO[2%],PEON[24%],COMPACTADOR VIBR. TIPO PLANCHA 4 HP,ARENA GRUESA[1],AGUA[1]
CAPATAZ[2%],PEON[17%]
CAPATAZ[1%],OPERARIO[10%],OFICIAL[10%],TUBERIA PVC 14" C-7.5[1]
OFICIAL[0%],PEON[5%],BALDE DE PRUEBA-TAPON-ABRAZ. Y ACCESORIOS ,AGUA[1]
PEON[8%],REJA GALVANIZADA REMOVIBLE de 0.70x0.80m.[1]
PEON[8%],REJA GALVANIZADA REMOVIBLE de 1.20x0.80m.[1]
OPERARIO[5%],PEON[5%],CODO PVC 45 x 14"[1]
OPERARIO[8%],PEON[8%],VALVULA DE COMPUERTA DE BRONCE 14"[1]
CAJA DE VALVULA DE COMPUERTA[1]
OPERARIO[16%],PEON[159%]
OPERARIO[20%],PEON
OPERARIO[1%],PEON[30%]
PEON[309%]
CEMENTO PORTLAND TIPO V (EN FCA.)S-PUB[1],OPERADOR DE EQUIPO PESADO,OPERARIO[48%],OFICIAL[48%],PEON[190%],MEZCLADORA CONCRETO TAMBOR 18HP 11P3,FLETE TRANSPORTE LOCAL[1],PIEDRA CHANCADA DE 3/4"[1],ARENA GRUESA[1],AGUA[1]
CEMENTO PORTLAND TIPO I (42.5KG)[1],OPERARIO[99%],OFICIAL[99%],PEON[593%],MEZCLADORA CONCRETO TAMBOR 18HP 11P3,ARENA FINA[1],HORMIGON[1]
OPERARIO[99%],OFICIAL[197%],PEON[197%],ALAMBRE NEGRO RECOCIDO # 8[1],CLAVOS PARA MADERA C/C 2 1/2"[1],CLAVOS PARA MADERA C/C 3"[1],MADERA TORNILLO INC.CORTE P/ENCOFRADO[1]
22 26 30 03 07 11 15 19 23 27 01 05 09 13 17 21 25 29 02 06 10 14 18 22 26 30 03 07 11 15 19 23 27 01 05 09 13 17 21 25 2924 may '15 07 jun '15 21 jun '15 05 jul '15 19 jul '15 02 ago '15 16 ago '15 30 ago '15 13 sep '15 27 sep '15 11 oct '15 25 oct '15
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tareas externas
Hito externo
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
Slo duracin
Informe de resumen manual
Resumen manual
Slo el comienzo
Slo fin
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Pgina 1
Proyecto: CRONOGRAMA DE OBRFecha: mar 17/03/15
Id Modo de tarea
Nombre de tarea Duracin Comienzo Fin PredecesorasCosto
54 ACERO FY= 4200 KG/CM2 4 das lun 08/06/15 vie 12/06/15 50 S/. 14,825.89
55 REVOQUES Y ENLUCIDOS 8 das mi 24/06/15 sb 04/07/15 S/. 14,735.35
56 TARRAJEO EN MUROS INTERIORES FROTACHADO 1:5, E=1.5CM.4 das mi 24/06/15 mar 30/06/15 52 S/. 13,895.84
57 TARRAJEO EN MUROS EXTERIORES FROTACHADO 1:5, E= 1.5CM.4 das mar 30/06/15 sb 04/07/15 56 S/. 839.51
58 PINTURA 2 das sb 04/07/15 mar 07/07/15 S/. 801.07
59 PINTADO DE MURO INTERIOR Y EXTERIOR CON TEKNO MATE O SUPERMATE (SIMILAR)2 das sb 04/07/15 mar 07/07/15 57 S/. 801.07
60 TUBERIA DE INTERCONEXION 14 das mar 07/07/15 vie 24/07/15 43 S/. 39,243.13
61 OBRAS PROVISIONALES 2 das mar 07/07/15 jue 09/07/15 S/. 322.03
62 CINTAS PLASTICAS SEALIZADORAS (LIMITE DE
SEGURIDAD)
2 das mar 07/07/15 jue 09/07/15 43 S/. 322.03
63 TRABAJOS PRELIMINARES 1 da mar 07/07/15 mi 08/07/15 S/. 315.32
64 TRAZO Y REPLANTEO 1 da mar 07/07/15 mi 08/07/15 62CC S/. 315.32
65 MOVIMIENTO DE TIERRAS 13 das mi 08/07/15 vie 24/07/15 S/. 5,079.31
66 EXCAVACION DE ZANJA MANUAL 3 das mi 08/07/15 lun 13/07/15 64 S/. 1,416.94
67 REFINE Y NIVELACION EN TERRENO NORMAL 2 das lun 13/07/15 mi 15/07/15 66 S/. 628.40
68 CAMA DE APOYO C / MATERIAL PROPIO
ZARANDEADO E=0.10M
2 das mi 15/07/15 vie 17/07/15 67 S/. 355.57
69 RELLENO Y COMPACTACION DE ZANJAS MAT.
PROPIO
4 das lun 20/07/15 vie 24/07/15 73 S/. 2,658.96
70 ELIMINACION MATERIAL EXCEDENTE 1 da lun 13/07/15 mar 14/07/15 66 S/. 19.44
71 SUMINISTRO E INSTALACION DE TUBERIAS 3 das vie 17/07/15 mar 21/07/15 S/. 21,374.66
72 SUMINISTRO E INSTALACION DE TUBERIA PVC C-7.5
8"
2 das vie 17/07/15 lun 20/07/15 68 S/. 3,189.38
73 SUMINISTRO E INSTALACION DE TUBERIA PVC C-7.5
10"
2 das vie 17/07/15 lun 20/07/15 68 S/. 4,486.98
74 SUMINISTRO E INSTALACION DE TUBERIA PVC C-7.5
12"
1 da lun 20/07/15 mar 21/07/15 73 S/. 2,364.79
75 SUMINISTRO E INSTALACION DE TUBERIA PVC C-7.5
14"
1 da lun 20/07/15 mar 21/07/15 73 S/. 11,333.51
76 PRUEBA HIDRAULICA 1 da mar 21/07/15 mi 22/07/15 S/. 592.62
77 PRUEBA HIDRAULICA PARA AGUA POTABLE 1 da mar 21/07/15 mi 22/07/15 75 S/. 592.62
78 ACCESORIOS 1 da lun 20/07/15 mar 21/07/15 S/. 11,559.19
79 TEE PVC 12"x10" 1 da lun 20/07/15 mar 21/07/15 72 S/. 1,111.96
80 TEE PVC 12"x8" 1 da lun 20/07/15 mar 21/07/15 79CC S/. 960.44
81 TEE PVC 14"x10" 1 da lun 20/07/15 mar 21/07/15 79CC S/. 624.22
82 TEE PVC 14"x14" 1 da lun 20/07/15 mar 21/07/15 79CC S/. 959.22
83 SUMINISTRO E INSTALACION DE CODO PVC 8"X45 1 da lun 20/07/15 mar 21/07/15 79CC S/. 116.19
84 SUMINISTRO E INSTALACION DE CODO PVC 90x8" 1 da lun 20/07/15 mar 21/07/15 79CC S/. 627.42
85 SUMINISTRO E INSTALACION DE CODO PVC
90x10"
1 da lun 20/07/15 mar 21/07/15 79CC S/. 308.62
86 SUMINISTRO E INSTALACION DE CODO PVC
90x14"
1 da lun 20/07/15 mar 21/07/15 79CC S/. 2,371.88
87 REDUCCION PVC DE 12"x8" 1 da lun 20/07/15 mar 21/07/15 79CC S/. 471.80
88 VALVULA COMPUERTA DE BRONCE DE 8" 1 da lun 20/07/15 mar 21/07/15 86CC S/. 2,810.58
89 VALVULA COMPUERTA DE BRONCE DE 12" 1 da lun 20/07/15 mar 21/07/15 72 S/. 1,196.86
90 RESERVORIO DE V=500M3 27 das lun 13/07/15 mar 18/08/15 43CC+33 dasS/. 73,269.25
91 OBRAS PRELIMINARES 3 das lun 13/07/15 jue 16/07/15 S/. 1,034.20
92 LIMPIEZA DE TERRENO MANUAL 1 da lun 13/07/15 mar 14/07/15 43CC+15 dasS/. 717.98
93 TRAZO Y REPLANTEO 2 das mar 14/07/15 jue 16/07/15 92 S/. 316.22
94 MOVIMIENTO DE TIERRAS 5 das jue 16/07/15 mi 22/07/15 S/. 2,920.58
95 EXCAVACION DE ZANJA MANUAL. 3 das jue 16/07/15 lun 20/07/15 93 S/. 1,269.82
96 ELIMINACION MATERIAL EXCEDENTE 2 das lun 20/07/15 mi 22/07/15 95 S/. 1,650.76
97 OBRAS DE CONCRETO ARMADO 14 das mi 22/07/15 mar 11/08/15 S/. 58,170.62
98 CONCRETO FC=210 KG/CM2 EN MUROS 4 das jue 06/08/15 mar 11/08/15 99 S/. 31,854.81
99 ACERO FY= 4200 KG/CM2 5 das vie 31/07/15 jue 06/08/15 100 S/. 21,374.16
CAPATAZ[10%],OPERARIO,OFICIAL,ALAMBRE NEGRO RECOCIDO # 16[1],FIERRO CO. FY=4200 KG/CM2 G-60 1/2"[1]
CEMENTO PORTLAND TIPO I (42.5KG)[1],OPERARIO[97%],PEON[194%],CLAVOS DE ALAMBRE PARA MADERA C/C DE 3"[1],ARENA FINA[1],REGLA DE MADERA[1],ANDAMIO DE MADERA[1]
CEMENTO PORTLAND TIPO I (42.5KG)[1],OPERARIO[84%],OFICIAL[84%],ARENA FINA[1],AGUA[1],REGLA DE MADERA[1],ANDAMIO DE MADERA[1]
ANDAMIO METAL TABLAS-ALQUILER,IMPRIMANTE[1],PINTURA LATEX[1],OPERARIO[77%],PEON[19%]
OPERARIO[6%],PEON[56%],CINTA PLASTICAS SEALIZADORAS[1]
TOPOGRAFO[56%],PEON[168%],ESTACION TOTAL,MADERA TORNILLO[1],WINCHA[1]
OPERARIO[4%],PEON[134%]
OPERARIO[15%],PEON[75%],ARENA GRUESA[1]
OPERARIO[47%],PEON[93%]
OPERARIO[10%],PEON,COMPACTADOR VIBR. TIPO PLANCHA 4 HP,ARENA GRUESA[1],AGUA[1]
CAPATAZ[2%],PEON[23%]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[19%],PEON[19%],TUBERIA PVC C-7.5 8"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[27%],PEON[27%],TUBERIA PVC C-7.5 10"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[13%],PEON[13%],TUBERIA PVC C-7.5 12"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[27%],PEON[27%],TUBERIA PVC C-7.5 14"[1]
OFICIAL[3%],PEON[28%],BALDE DE PRUEBA-TAPON-ABRAZ. Y ACCESORIOS ,AGUA[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[10%],TEE PVC 12"X10"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[5%],PEON[50%],TEE PVC 12" x 8"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[3%],PEON[25%],TEE PVC 14" X 10"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[3%],PEON[25%],TEE PVC 14"x14"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],CAPATAZ[2%],OPERARIO[17%],CODO PVC 45 x 8"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[10%],CODO PVC 90x8"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[10%],CODO PVC 90 x 10"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[10%],CODO PVC 90x14"[1]
PEGAMENTO PARA PVC AGUA FORDUIT[1],OPERARIO[20%],PEON[20%],REDUCCION PVC 12" x 8"[1]
OPERARIO[50%],PEON[50%],VALVULA COMPUERTA DE BRONCE DE 8"[1]
OPERARIO[17%],PEON[17%],VALVULA COMPUERTA DE BRONCE DE 12"[1]
22 26 30 03 07 11 15 19 23 27 01 05 09 13 17 21 25 29 02 06 10 14 18 22 26 30 03 07 11 15 19 23 27 01 05 09 13 17 21 25 2924 may '15 07 jun '15 21 jun '15 05 jul '15 19 jul '15 02 ago '15 16 ago '15 30 ago '15 13 sep '15 27 sep '15 11 oct '15 25 oct '15
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tareas externas
Hito externo
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
Slo duracin
Informe de resumen manual
Resumen manual
Slo el comienzo
Slo fin
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Pgina 2
Proyecto: CRONOGRAMA DE OBRFecha: mar 17/03/15
Id Modo de tarea
Nombre de tarea Duracin Comienzo Fin PredecesorasCosto
100 ENCOFRADO Y DESENCOFRADO NORMAL 5 das mi 22/07/15 jue 30/07/15 96 S/. 4,941.65
101 REBOQUES Y ENLUCIDOS 4 das mar 11/08/15 lun 17/08/15 S/. 4,548.28
102 TARRAJEO EN EXTERIORES MEZCLA 1:5 E=1.50CM 4 das mar 11/08/15 lun 17/08/15 98 S/. 4,548.28
103 SUMINISTRO E INSTALACION DE ACCESORIOS 1 da lun 17/08/15 mar 18/08/15 S/. 6,595.57
104 WATER STOP DE NEOPRENE DE 6". PROVISION Y COLOCADO DE JUNTA1 da lun 17/08/15 mar 18/08/15 102 S/. 2,347.90
105 CODO PVC 10 "X45 1 da lun 17/08/15 mar 18/08/15 104CC S/. 188.88
106 TEE DE FIERRO FUNDIDO BRIDADO DE 10" X 10" 1 da lun 17/08/15 mar 18/08/15 105CC S/. 805.43
107 VALVULA DE F GALVANIZADO 10" 1 da lun 17/08/15 mar 18/08/15 106CC S/. 1,929.58
108 UNION UNIVERSAL 10" 1 da lun 17/08/15 mar 18/08/15 106CC S/. 755.26
109 TAPA METALICA DE 1.9M.X2.5 m. 1 da lun 17/08/15 mar 18/08/15 106CC S/. 568.52
22 26 30 03 07 11 15 19 23 27 01 05 09 13 17 21 25 29 02 06 10 14 18 22 26 30 03 07 11 15 19 23 27 01 05 09 13 17 21 25 2924 may '15 07 jun '15 21 jun '15 05 jul '15 19 jul '15 02 ago '15 16 ago '15 30 ago '15 13 sep '15 27 sep '15 11 oct '15 25 oct '15
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tareas externas
Hito externo
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
Slo duracin
Informe de resumen manual
Resumen manual
Slo el comienzo
Slo fin
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Pgina 3
Proyecto: CRONOGRAMA DE OBRFecha: mar 17/03/15