Hoja1

E2 = 2E5 = 10E6 = 12NNOMBREPREDECESORA (ANTES DE )DURACION (DIAS)E1 = 0ACSE SELECCIONA EL MAYOR VALOR 1A--228F2E6 = 82B--5E3 = 5E6 = 1203CA8BDFRUTA CRITICA4DB7576E7 = 185EB3EE6 = 86FE,D63F10E4 = 8E1 0L180SE SELECCIONA EL MENORE2 2L210E35L359E48L412E510L518E612L612E718L718"L" SE INICIARA DE MAYOR A MENOR

RUTA CRITICAL = EANALIZAR CADA ACTIVIDAD Y COMPARAR OCURRENCIAS TEMPRANAS Y TARDIAS, SI COINCIDEN ESNTONCES ES SU RUTA CRITICA

HOLGURA TOTALHT = L ini- (Einic +D)HOLGURA LIBREHL = E ini- (Einic +D)HOLGURA INDEPENDIENTEHI = E ini- (Linic +D)