Hoja1PRECIOS DE MATERIALES PARA CUBIERTA DE POZAS DE HUMUS - VIVERO HUAMANCHACATE

ITEMDESCRIPCIONUNDCANTID.PRECIO UNITPRECIO TOTAL

1Parantes de Eucalipto 3m x 6"und14.0025.00350.002Parantes de Eucalipto 4m x 6"und7.0030.00210.003Vigas Eucalipto 8m x 4"und12.0040.00480.004Vigas Eucalipto 5m x 3"und12.0015.00180.005Varillas de 2 1/2 "und17.0010.00170.006Esteras de Carrizillo 3m x 2mund44.0016.00704.007Alambrekg15.006.0090.008Cementobls79.0025.001975.009Arenam34.5545.00204.7510Piedram35.6738.00215.4611Aguam31.7010.0017.004596.21

MANO DE OBRA

ITEMDESCRIPCIONUNDCANTIDN VECESPRECIO UNITPRECIO TOTAL

1OPERARIOhh56.001.0020.151128.402PEONhh56.002.0016.111804.322932.72

Costo Directo7528.93G.G 10%752.893SUB TOTAL8281.82IGV 18%1490.728149772.55CONCRETO CICLOPEO 175 kg/cm2 1 : 2.6 : 3.2Aporte de Materiales para 9.26 m3Cemento : 8.43Arena Gruesa : 0.49Piedra : 0.61Agua : 0.184

Hoja2PRECIOS DE MATERIALES PARA CUBIERTA DE POZAS DE HUMUS - VIVERO HUAMANCHACATE

ITEMDESCRIPCIONUNDCANTID.PRECIO UNITPRECIO TOTAL

1Parantes de Eucalipto 3m x 6"und14.0035.00490.002Parantes de Eucalipto 4m x 6"und7.0040.00280.003Vigas Eucalipto 8m x 4"und12.0045.00540.004Vigas Eucalipto 5m x 3"und12.0020.00240.005Varillas de 2 1/2 "und17.0014.00238.006Esteras de Carrizillo 3m x 2mund44.0019.00836.007Alambrekg15.006.0090.008Cementobls79.0023.001817.009Arenam34.5545.00204.7510Piedram35.6750.00283.5011Aguam31.7012.0020.405039.65

MANO DE OBRA

ITEMDESCRIPCIONUNDCANTIDN DIASPRECIO UNITPRECIO TOTAL

1OPERARIOdh1.007.0090.00630.002PEONdh2.007.0075.001050.001680.00

TOTAL S/.6719.65

CONCRETO CICLOPEO 175 kg/cm2 1 : 2.6 : 3.2Aporte de Materiales para 9.26 m3Cemento : 8.43Arena Gruesa : 0.49Piedra : 0.61Agua : 0.184