RENDIMIENTO
DESCRIP./ACTIVIDAD FECHA CUARILLAHORA CANTIDAD MATERIAL UTILIZADO EFICIENCIA
INICIO FIN HTOTAL-NETA UNIDAD VALOR CEMENTO (Kg) ARENA(m3) AGUA(Lts) CUADRILLA
PAÑETE APTO 401 8/31/2015 1OF+1AY 7:00 AM 5:00 PM 9.00 16.92 75 0.293 42.22 0.53 hC/m²
PAÑETE APTO 503 8/31/2015 1OF+1AY 7:00 AM 5:00 PM 9.00 19 62.5 0.244 35 0.47 hC/m²
PAÑETE APTO 9/1/2015 1OF+1AY 7:00 AM 5:00 PM 9.00 20.8 100 0.39 56 0.43 hC/m²
PAÑETE APTO 9/3/2015 1OF+1AY 7:00 AM 5:00 PM 9.00 18.35 175 0.68 98.35 0.49 hC/m²
PAÑETE APTO 103 9/14/2015 1OF+1AY 7:00 AM 5:00 PM 9.00 6.75 25 0.098 14 1.33 hC/m²
CEMENTO (Kg) ARENA(m3) AGUA(Lts) BLOQUES CUADRILLA
MURO EN BLOQUE
8/31/2015
1OF+1AY 7:00 AM 5:00 PM 36.00 m² 36.4 350 1.37 175 1750 0.99 hC/m²9/1/20159/2/20159/3/2015
MURO EN BLOQUE APTO 601 9/16/2015 1OF+1AY 2:00 PM 4:00 PM 2 5.88 62.5 0.25 31.25 312 0.34 hC/m²
CEMENTO (Kg) ARENA(m3) AGUA(Lts) CUADRILLAANTEPISO APART-ESTUDIO 102 9/7/2015 1OF+1AY 8:00 AM 12:00 PM 4 19.72 200 1.25 116 0.20 hC/m²ANTEPISO APART-ESTUDIO 202 9/9/2015 1OF+1AY 1:00 PM 4:00 PM 3 19.72 200 1.25 116 0.15 hC/m²ANTEPISO APART-ESTUDIO 302 9/10/2015 1OF+1AY 7:00 AM 2:00 PM 6 39.44 400 2.5 232 0.15 hC/m²
CEMENTO (Kg) YESO(Kg) CAOLIN(Kg) AGUA(Lts) CUADRILLA
ESTUCOAPARTAMENTO 104 9/15/2015 1OF+1AY 7:00 AM 4:00 PM 11 m² 129.197 38.75 56.85 168 517 0.09 hC/m²9/16/2015 7:00 AM 11:00 AM
ESTUCO LOCAL 04 Y LOCAL 039/16/2015
1OF+1AY2:00 PM 4:00 PM
9.5 m² 87.16 26.15 38.35 26.15 349 0.11 hC/m²9/17/2015 7:00 AM 3:30 PM
CANTIDAD REALIZADA
m2
m2
m2
m2
m2
TABLA 3. VALORES PROMEDIOS RENDIMIENTO CONSUMO DE MATERIAL POR UNIDAD RENDIMIENTO
EFICIENCIA PRODUCTIVIDAD CEMENTO (Kg) ARENA(m3) AGUA(Lts)DESCRIP./ACTIVIDAD
EFICIENCIA PRODUCTIVIDAD HOMBRE CUADRILLA HOMBRE CUADRILLA HOMBRE CUADRILLA HOMBRE
1.06 hH/m² 1.88 m²/hC 0.94 m²/hH 4.43 Kg/m² 0.02 m³/m² 2.50 Lts/m² PAÑETE APTO 0.65 hC/m² 1.30 hH/m² 1.82 m²/hC 0.91 m²/hH0.95 hH/m² 2.11 m²/hC 1.06 m²/hH 3.29 Kg/m² 0.01 m³/m² 1.84 Lts/m² MURO EN BLOQUE 0.66 hC/m² 1.33 hH/m² 1.98 m²/hC 0.99 m²/hH0.87 hH/m² 2.31 m²/hC 1.16 m²/hH 4.81 Kg/m² 0.02 m³/m² 2.69 Lts/m² ANTEPISO 0.17 hC/m² 0.34 hH/m² 6.03 m²/hC 3.01 m²/hH0.98 hH/m² 2.04 m²/hC 1.02 m²/hH 9.54 Kg/m² 0.04 m³/m² 5.36 Lts/m²
2.67 hH/m² 0.75 m²/hC 0.38 m²/hH 3.70 Kg/m² 0.01 m³/m² 2.07 Lts/m² ESTUCO 0.10 hC/m² 0.19 hH/m² 10.46 m²/hC 5.23 m²/hH
HOMBRE CUADRILLA HOMBRE CEMENTO (Kg) ARENA(m3) AGUA(Lts) BLOQUES
1.98 hH/m² 1.01 m²/hC 0.51 m²/hH 9.62 Kg/m² 0.04 m³/m² 4.81 Lts/m² 48 Lad/m²
0.68 hH/m² 2.94 m²/hC 1.47 m²/hH 10.63 Kg/m² 0.04 m³/m² 5.31 Lts/m² 53 Lad/m²
HOMBRE CUADRILLA HOMBRE CEMENTO (Kg) ARENA(m3) AGUA(Lts)0.41 hH/m² 4.93 m²/hC 2.47 m²/hH 10.14 Kg/m² 0.06 m³/m² 5.88 Lts/m² 0 Lad/m²0.30 hH/m² 6.57 m²/hC 3.29 m²/hH 10.14 Kg/m² 0.06 m³/m² 5.88 Lts/m² 0 Lad/m²0.30 hH/m² 6.57 m²/hC 3.29 m²/hH 10.14 Kg/m² 0.06 m³/m² 5.88 Lts/m² 0 Lad/m²
HOMBRE CUADRILLA HOMBRE CEMENTO (Kg) YESO CAOLIN AGUA
0.17 hH/m² 11.75 m²/hC 5.87 m²/hH 0.30 Kg/m² 0.44 m³/m² 1.30 Lts/m² 4.00 Lts/m²
0.22 hH/m² 9.17 m²/hC 4.59 m²/hH 0.30 Kg/m² 0.44 m³/m² 0.30 Lts/m² 4.00 Lts/m²
TABLA 3. VALORES PROMEDIOS CONSUMO DE MATERIAL POR UNIDAD
CEMENTO (Kg) ARENA(m3) AGUA(Lts) BLOQUES
5.15 Kg/m² 0.02 m³/m² 2.89 Lts/m²
10.12 Kg/m² 0.04 m³/m² 5.06 Lts/m² 51 Lad/m²
10.14 Kg/m² 0.06 m³/m² 5.88 Lts/m²CEMENTO (Kg) YESO CAOLIN AGUA
0.30 Kg/m² 0.44 Kg/m² 0.80 Kg/m² 4.00 Lts/m²
ACTIVIDAD: PAÑETE DE 1,5 cm UNIDAD CANTIDAD
MATERIALES UND CANTIDAD VALOR DESPERDICIOCEMENTO Kg 5.15 440 5%
ARENA M3 0.020 42857 5%AGUA Lts 2.9 0.018 5%
MAQUINA Y/EQUIPO UND CANTIDAD VALOR RENDIMIENTO
HERRAMIENTA MENOR
MANO DE OBRA UND SALARIO VR/GLOBAL RENDIMIENTO1 OFICIAL + 1 AYUDANTE 1 76000 5.87
ANALISIS PRECIOS UNITARIOS EDIFICIO CHIKALA
M2 ACTIVIDAD: MURO EN BLOQUE
VR/UNIT. MATERIALES UND CANTIDAD2381.2 CEMENTO Kg 10.12904.4 ARENA M3 0.0400.055 AGUA Lts 5.1
0 LADRILLO UND 510
SUB-TOTAL $ 3,285.59 VR/UNIT. MAQUINA Y/EQUIPO UND CANTIDAD
$ 1,294.33 HERRAMIENTA MENOR
SUB-TOTAL $ 1,294.33 VR/UNIT. MANO DE OBRA UND SALARIO
12943 1 OFICIAL + 1 AYUDANTE 1 76000
SUB-TOTAL $ 12,943.31 COSTO DIRECTO $ 17,523.23
EDIFICIO CHIKALA ANALISIS PRECIOS UNITARIOS EDIFICIO CHIKALA
MURO EN BLOQUE UNIDAD CANTIDAD M2
VALOR DESPERDICIO VR/UNIT.440 5% 4676.5
42857 5% 1803.50.018 5% 0.10800 5% 42478
0SUB-TOTAL $ 48,958.10
VALOR RENDIMIENTO VR/UNIT.
$ 1,270.66
SUB-TOTAL $ 1,270.66 VR/GLOBAL RENDIMIENTO VR/UNIT.
5.98 12707
SUB-TOTAL $ 12,706.56 COSTO DIRECTO $ 62,935.32
ANALISIS PRECIOS UNITARIOS EDIFICIO CHIKALA
ACTIVIDAD: ANTEPISO CON ESPESPR e=4cm UNIDAD CANTIDAD M2
MATERIALES UND CANTIDAD VALOR DESPERDICIO VR/UNIT.CEMENTO Kg 10.14 440 5% 4685.6
ARENA M3 0.063 42857 5% 2852.4AGUA Lts 5.9 0.018 5% 0.11
00
SUB-TOTALMAQUINA Y/EQUIPO UND CANTIDAD VALOR RENDIMIENTO VR/UNIT.
HERRAMIENTA MENOR $ 4,995.73
SUB-TOTALMANO DE OBRA UND SALARIO VR/GLOBAL RENDIMIENTO VR/UNIT.
1 OFICIAL + 1 AYUDANTE 1 76000 1.52 49957
SUB-TOTALCOSTO DIRECTO
ANALISIS PRECIOS UNITARIOS EDIFICIO CHIKALA
ACTIVIDAD: ESTUCO
MATERIALES UND CANTIDAD VALOR CEMENTO Kg 0.30 440
YESO M3 0.440 17700CAOLIN Lts 0.8 7500AGUA 4 0.018
$ 7,538.14 MAQUINA Y/EQUIPO UND CANTIDAD VALOR
HERRAMIENTA MENOR
$ 4,995.73 MANO DE OBRA UND SALARIO VR/GLOBAL2 ESTUCADORES 1 4000
$49,957.33 $62,491.21
ANALISIS PRECIOS UNITARIOS EDIFICIO CHIKALA
UNIDAD CANTIDAD M2
DESPERDICIO VR/UNIT.5% 138.65% 8177.65% 6301.435% 0.0757
0SUB-TOTAL $ 14,617.69
RENDIMIENTO VR/UNIT.
$ 457.87
SUB-TOTAL $ 457.87 RENDIMIENTO VR/UNIT.
0.87 4579
SUB-TOTAL $ 4,578.69 COSTO DIRECTO $ 19,654.24
ANALISIS PRECIOS UNITARIOS EDIFICIO CHIKALA