CONCEPTO UNIDAD CANTIDA D P.U. TOTAL 1.-PREELIMINARES 1.1.-LIMPIEZA Y DESENRAICE DE TERRENO A MANO DE MALEZA A UN METRO DE PROFUNDIDAD m2 180 $3.39 $610.20 -GRUPO 1 DE CUADRILLA jr 0.0125 $271.50 $3.39 -1/10 DE CABO jr 0.1 $300.00 $30.00 -1 PEON jr 1 $200.00 $200.00 -% HERRAMIENTA MENOR %mo 0.03 $350.00 $10.50 -% MANDO INTERMEDIO %mo 0.08 $350.00 $28.00 -% FACTOR DE SEGURIDAD %mo 0.01 $300.00 $3.00 1.1.-TRAZO Y NIVELACION DE TERRENO, URBANO DE 250 A 750 M2, POR MEDION MANUALES, CON HILO Y NIVEL DE MANGUERA m2 180 $2.84 $511.66 -CAL tn 0.0004 $1,100. 00 $0.44 -HILO DE CAÑAMO O DE PLASTICO pza 0.00167 $25.00 $0.04 -BARROTES DE MADERA pt 0.0145 $13.76 $0.20 -MANGUERA pza 0.00067 $75.00 $0.05 -CUADRILLA 2 TAREAS PESADAS jr 0.00667 $316.50 $2.11 -1/4 DE CABO jr 0.25 $300.00 $75.00 -1 PEON jr 1 $200.00 $200.00 -% HERRAMIENTA MENOR %mo 0.003 $350.00 $1.05 -% MANDO INTERMEDIO %mo 0.08 $350.00 $28.00 -% FACTOR DE SEGURIDAD %mo 0.01 $300.00 $3.00 2.-EXCAVACION 2.1.- EXCAVACIONES m3 60 $68.34 $4,100. 18 -PICO DE 5lb pza 0.0013 $150.00 $0.20 -PALA CUADRADA pza 0.00222 $120.00 $0.27

Final

Embed Size (px)

DESCRIPTION

mata

Citation preview

Page 1: Final
Page 2: Final

CONCEPTO UNIDAD CANTIDAD P.U. TOTAL

1.-PREELIMINARES        

   1.1.-LIMPIEZA Y DESENRAICE DE TERRENO A MANO DE MALEZA A UN METRO DE PROFUNDIDAD

m2 180 $3.39 $610.20

    -GRUPO 1 DE CUADRILLA jr 0.0125 $271.50 $3.39

    -1/10 DE CABO jr 0.1 $300.00 $30.00

    -1 PEON jr 1 $200.00 $200.00

    -% HERRAMIENTA MENOR %mo 0.03 $350.00 $10.50

    -% MANDO INTERMEDIO %mo 0.08 $350.00 $28.00

    -% FACTOR DE SEGURIDAD %mo 0.01 $300.00 $3.00

    1.1.-TRAZO Y NIVELACION DE TERRENO, URBANO DE 250 A 750 M2, POR MEDION MANUALES, CON HILO Y NIVEL DE MANGUERA

m2 180 $2.84 $511.66

    -CAL tn 0.0004 $1,100.00 $0.44

    -HILO DE CAÑAMO O DE PLASTICO pza 0.00167 $25.00 $0.04

    -BARROTES DE MADERA pt 0.0145 $13.76 $0.20

    -MANGUERA pza 0.00067 $75.00 $0.05

    -CUADRILLA 2 TAREAS PESADAS jr 0.00667 $316.50 $2.11

    -1/4 DE CABO jr 0.25 $300.00 $75.00

    -1 PEON jr 1 $200.00 $200.00

    -% HERRAMIENTA MENOR %mo 0.003 $350.00 $1.05

    -% MANDO INTERMEDIO %mo 0.08 $350.00 $28.00

    -% FACTOR DE SEGURIDAD %mo 0.01 $300.00 $3.00

2.-EXCAVACION        

   2.1.- EXCAVACIONES m3 60 $68.34 $4,100.18

    -PICO DE 5lb pza 0.0013 $150.00 $0.20

    -PALA CUADRADA pza 0.00222 $120.00 $0.27

    -CUADRILLA 2 TAREAS PESADAS jr 0.25 $271.50 $67.88

    -1/4 DE CABO jr 0.1 $300.00 $30.00

    -1 PEON jr 1 $200.00 $200.00

    -% HERRAMIENTA MENOR %mo 0.01 $300.00 $3.00