MEMORIA 0+189

Embed Size (px)

Citation preview

  • 7/25/2019 MEMORIA 0+189

    1/3

    LATINOAMERICANA DE INGENIERIA CIVIL, S.A. DE C.V.

    CARRETERA : XPUJIL - DZIBALCHEN ALTERNATIVA : CORONA 7.50 M

    TRAMO : XPUJIL - DZIBALCHEN KM - KM : KM. 0+000.00 AL KM. 5+000.00

    SUB-TRAMO : KM. 0+000.00 AL KM. 20+000.00 ORIGEN : XPUJIL, CAMP.

    ALCANTARILLA LOSA DE 4.00 X 1.50 M ESTACION

    C R U C E 0 00' NORMAL EN TANGENTE SENT. ESC. IZQ. A DER.

    SUB-RASANTE 246.13 M ESP. PAV. 0.20 M ESP CARP 0.05 M

    RASANTE CALCULO 246.33 M RASANTE O.V. 246.33 M PEND. O.V. -0.15 %

    Y1 = 3.75 M W1 = -2.00 %

    Y2 = 7.80 M W2 = -2.00 %

    X1 = 0.00 TAN E= 0.000 X2 = 0.00

    C1 = 3.75 COS E= 1.000 C2 = 7.80

    R1 = 246.33 SEN E= 0.000 R2 = 246.33

    H1 = 246.25 TN = 2.50 0.001 H2 = 246.17

    COS E + K = 1.00 K1 = 0.000 COS E + K= 1.00

    T1 = 2.50 K2 = 0.000 T2 = 0.00

    PLANTILLA DEL PENDIENTE S = -2.10 % E LOSA = 0.32 M

    CAUCE ELEV. CL D = 243.91 M ALT.DIR.= 0.10 M

    1/T1 = 0.400 M= 1.92 Q = 0.20 1/T2= 1000.000

    (1/T1) - S = 0.421 M1 = 1.92 M2 = 1.92 (1/T2) + S= 999.979 F 1 = 245.91 F'1 = 245.83 F'2 = 245.83 F 2 = 245.66

    h 1 = 0.34 Q' = 0.20 Q'S = -0.004 h 2 = 0.51

    d 1 = 0.80 d 2 = 0.00

    L 1 = 4.75 L = 12.75 L 2 = 8.00

    L1 EXISTENTE = 0.00 L2 EXISTENTE = 0.00

    L1 PROLONGAR = 4.75 L PROL.= 12.75 L2 PROLONGAR = 8.00

    4.75 M ELEV = 244.01 M 8.00 M ELEV 243.74 M

    CL ELEV 243.91 M

    COLCHON EN EL CL 0.60 M CLASIFICACION DEL T.N.: 20 80 00

    N O T A S :

    CALCULO NORMA HORTENSIA ROMERO S. REVISO ING. M. PATRICIA SALAZAR HDZ. APROBO

    ECHA SEP 2012 FECHA SEP 2012 FECHA

    DATOS COMPLEMENTARIOS

    C A L C U L O D E L O N G I T U D D E E S T R U C T U R A M E N O R

    DATOS DE LAS TERRACERIAS EN EL CRUCE

    SECCION DE LA S TERRACERIAS SEGUN EL EJE DE LA ESTRUCTURA

    SEMI-CORONAS SOBRE-ELEVACIONES

    0+189.08

    L SIGNO ALGEBRAICO DE LA EXPRESION COS E + K, KCONSERVA EL SIGNO DE LA PENDIENTE DE LA OBRA VIAL, DEL LADO QUE TIENE NOMBRE EL ESVIAJE

    LONGITUD DE LA ESTRUCTURA

    ELEVACIONES DE LA PLANTILLA

  • 7/25/2019 MEMORIA 0+189

    2/3

    LATINOAMERICANA DE INGENIERIA CIVIL, S.A. DE C.V.

    CARRETERA : XPUJIL - DZIBALCHEN ALTERNATIVA : CORONA 7.50 M

    TRAMO : XPUJIL - DZIBALCHEN KM - KM : KM. 0+000.00 AL KM. 5+000.00SUB-TRAMO : KM. 0+000.00 AL KM. 20+000.00 ORIGEN : XPUJIL, CAMP.

    ALCANTARILLA LOSA DE 4.00 X 1.50 M ESTACION

    C R U C E 0 00' NORMAL SENT. ESC. IZQ. A DER.

    F'C = 200 KG/CM2

    ARMADO: SENCILLO

    H1 = 1.84 HR1= 0.00 H2 1.84 HR2 = 0

    H1 - HR1 = 1.84 E= 0.00 TAN = 0.000 H2 - HR2 = 1.84

    1/T1 + S = 0.421 COS E= 1.000 1/T2 - S = 999.979

    L1 = 4.36 B+E= 30.00 COS E+B = 0.866 L2 = 0.00

    N1 = 4.36 B= 30.00 COS B = 0.866 N2 = 0.00

    J1 = 5.04 SEN B = 0.500 J2 = 0.00

    J'1 = 4.36 J'2 = 0.00

    J"1 = 2.52 |& - E| = 30.00 COS (&-E) = 0.866 J"2 = 0.00

    G1 = 5.04 &= 30.00 COS &= 0.866 G2 = 0.00

    G'1 = 4.36 SEN & = 0.500 G'2 = 0.00

    G"1 = 2.52 G"2 = 0.00

    a = 0.30 a = 0.00 a' = 0.00 Hp = 1.84

    az = 1.37 azr = 0.00 a'zr = 0.00 LUZ/2 = 2.00

    b = 0.48 air = 0.00 a'ir = 0.00 Y = 0.00

    v = 0.44 Vzr = 0.00 V'zr = 0.00 h = 1.50

    Pz = 0.00 Pzr = 0.00 Pzr = 0.00 ae = 0.33

    P'z = 0.45 P'zr= 0.00 P'zr = 0.00 K = 0.00

    P"z = 0.45 P"zr= 0.00 P"zr = 0.00 an = 0.26

    PROF.DESPLANTE = 0.45 M F'T = 1.00 KG/CM2 CLASIF.: 20 80 00

    N O T A S :

    C A L C U L O: NORMA HORTENSIA ROMERO S. REVISO: ING. M. PATRICIA SALAZAR HDZ. APROBO :

    E C H A : SEP 2012 FECHA : SEP 2012 FECHA :

    DIMENSIONES DE LA SECCION

    NORMALES

    AUXILIARES

    0+189.08

    NORMALES ESVIAJADAS

    DATOS DE CIMENTACION

    EN EL ARRANQUE

    C A L C U L O D E L O N G I T U D D E A L E R O S

    L A D O I Z Q U I E R D O L A D O D E R E C H O

    EN EL CORTE

  • 7/25/2019 MEMORIA 0+189

    3/3

    LATINOAMERICANA DE INGENIERIA CIVIL, S.A. DE C.V.

    CARRETERA : XPUJIL - DZIBALCHEN KM - KM : KM. 0+000.00 AL KM. 5+000.00

    T R A M O : XPUJIL - DZIBALCHEN ESTACION :

    ORIGEN : XPUJIL, CAMP.

    A) D A T O S

    .- ESTRIBO 3.- ACERO

    b = 0.48 CUADRO DE VARILLAS

    d = 0.45 L W / m sep L a n n' m n

    P"z = 0.45

    P'z = 0.45 VAR A 1.566 10 501 458 6

    P z = 0.00 VAR B 1.566 30 494 249 25 35 87 4

    h = 1.50 VAR C 1.566 23 1265 1265 2

    Lz = 4.00 VAR D 0 0 0

    b + d = 0.93 VAR E 0 0 0

    v = 0.44 VAR D1 0.566 10 460

    b2 = 0.33

    b3 = 0.30

    L = 12.75 4.- CLASIFICACION 5.- CONCRETO

    he = 0.85 % MAT A= 20 V/M LOSA= 1.536

    Bm = 1.87 % MAT B= 80 V/M GUAR= 0.049

    B = 30.00 % MAT C= 0 L GUAR = 4.70

    E = 0.00 3) ACERO

    & = 30.00 A = 502.00 KG

    dentellon = 0.50 B) CALCULO B = 340.00 KG

    e = 0.32 C = 495.00 KG

    Sep ( d ) = 2.82 1) CONCRETO EN ESTRIBOS Y ALEROS D = 0.00 KG

    tan B + E = 0.58 E = 0.00 KG

    tan & - E = 0.58 A1 = 1.75 M2 D1= 10.00 KG

    .- ALEROS A2 = 0.14 M2 W losa = 1,347.00 KG

    J 1 = 5.04 A = 1.56 M2 W estribos = 774.00 KG

    J'1 = 4.36 VE = 39.82 M3 W aleros = 188.00 KG

    J''1 = 2.52 VA = 8.21 M3 WT = 2,309.00 KG

    G 1 = 5.04 VD = 1.71 M3 4) ZAMPEADO

    G'1 = 4.36 VT = 50.00 M3 A1= 23.38 M2

    G''1 = 2.52 VCAJA = 0.00 M3 A2= 0.00 M2

    J 2 = 0.00 A3= 35.96 M2

    J'2 = 0.00 VZ= 5.93 M3

    J''2 = 0.00 2) CONCRETO EN LOSA

    G 2 = 0.00 6) CAJA

    G'2 = 0.00 Vlosa 19.58 M3 h1 = 0.00 M

    G''2 = 0.00 Vguar 0.46 M3 H1 = 0.00 M

    VT = 20.00 M3 b1 = 0.00 M

    H2 = 0.00 M

    b2 = 0.00 M

    CONCRETO EST. Y ALER. 50.00 M3 l = 0.00 MCONCRETO EN LOSA 20.00 M3 L1 = 0.00 M

    DEMOLICION 52.22 M3 L2 = 0.00 M

    ACERO 2,309.00 KG 5) EXCAVACION

    AMPEADO 5.93 M3 Bm + (Tc)(he) 2.30

    EXCAVACION 69.00 M3 LE1 17.61

    RELLENO MAT.BCO. 1.47 M3 LE2 17.61

    CONCRETO CAJA 0.00 M3 VE1 34.36

    VE2 34.36

    VE= 69.00 M3

    + .

    R E S U M E N