CRONOGRAMA VALORIZADOPROYECTO:
“MEJORAMIENTO DEL PASAJE ANCASH, DE LA LOCALIDAD DE PARIAHUANCA, PROVINCIA DE CARHUAZ, ANCASH
LOCALIDAD PARIAHUANCADISTRITO PARIAHUANCAPROVINCIA CARHUAZREGION ANCASH FECHA JUNIO 2014
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) SEMANA1 SEMANA2 SEMANA3 SEMANA4 SEMANA5 SEMANA6 SEMANA7 SEMANA801 OBRAS PROVISIONALES S/. 4,699.90
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. und 1.00 2,128.15 S/. 2,128.15 S/. 2,128.15
01.02 ALAMCEN Y OFICINA m2 25.00 102.87 S/. 2,571.75 S/. 2,571.75
02 PAVIMENTO S/. 75,499.68
02.01 OBRAS PRELIMINARES S/. 3,488.10
02.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS GLB 1.00 3,000.00 S/. 3,000.00 S/. 3,000.00
02.01.02 TRAZO, NIVELACION Y REPLANTEO KM 0.10 3,096.34 S/. 309.63 S/. 309.63
02.01.03 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA KM 1.00 178.47 S/. 178.47 S/. 178.47
02.02 MOVIMIENTO DE TIERRAS S/. 38,799.22
02.02.01 CORTE HASTA EL NIVEL DE SUBRASANTE CON MAQUINARIA m3 123.20 3.54 S/. 436.13 S/. 436.13
02.02.02 COMPACTADO SUBRASANTE EN ZONA DE CORTE m2 363.00 7.29 S/. 2,646.27 S/. 2,646.27
02.02.03 SUB - BASE AFIRMADO DE 0.15 M. FACTOR DE COMPACTACION 1.2 m2 363.00 80.58 S/. 29,250.54 S/. 14,625.27 S/. 14,625.27
02.02.04 BASE GRANULAR E=0.20 M REND.=2310 M2/DIA FACT. COMPACT.=1.20 m2 122.40 31.41 S/. 3,844.58 S/. 3,844.58
02.02.05 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 135.00 19.42 S/. 2,621.70 S/. 2,621.70
02.03 OBRAS DE CONCRETO S/. 29,382.08
02.03.01 ENCOFRADO DE PAVIMENTO RIGIDO m2 61.20 52.07 S/. 3,186.68 S/. 3,186.68
02.03.02 CONCRETO F'C=210 KG/CM2. EN PAVIMENTO RIGIDO m3 56.70 441.67 S/. 25,042.69 S/. 12,521.35 S/. 12,521.35
02.03.03 CURADO EN PAVIMENTO RIGIDO m3 56.70 20.33 S/. 1,152.71 S/. 1,152.71
02.04 JUNTAS DE DILATACION S/. 3,241.33
02.04.01 JUNTAS DE CONTRACCION, e=2.0 cm m 396.25 8.18 S/. 3,241.33 S/. 3,241.33
02.05 SEÑALIZACION S/. 588.95
02.05.01 SEÑALIZACION CON CINTAS DE SEGURIDAD m2 10.20 57.74 S/. 588.95 S/. 588.95
03 VEREDAS DE CONCRETO S/. 7,557.65
03.01 OBRAS PRELIMINARES S/. 619.27
03.01.01 TRAZO, NIVELACION Y REPLANTEO KM 0.20 3,096.34 S/. 619.27 S/. 619.27
03.02 MOVIMIENTO DE TIERRAS S/. 1,188.05
03.02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 MT m3 15.27 5.28 S/. 80.63 S/. 80.63
03.02.02 NIVELACION Y COMPACTACION DE SUBRASANTE CON EQUIPO LIVIANO m2 50.90 7.29 S/. 371.06 S/. 371.06
03.02.03 RELLENO CON MATERIAL GRANULAR COMPACTADO m3 15.27 25.89 S/. 395.34 S/. 395.34
03.02.04 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 17.56 19.42 S/. 341.02 S/. 341.02
03.03 OBRAS DE CONCRETO S/. 5,142.17
03.03.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 30.54 23.71 S/. 724.10 S/. 724.10
03.03.02 CONCRETO F'C=140 KG/CM2 m3 15.27 289.33 S/. 4,418.07 S/. 4,418.07
03.04 JUNTAS DE DILATACION S/. 608.16
03.04.01 JUNTAS ASFALTICAS m 120.81 4.22 S/. 509.82
03.04.02 PINTURA CON ESMALTE EN EXTERIOR m2 30.54 3.22 S/. 98.34
04 MURO DE CONTENCION S/. 218,917.44
04.01 TRAZO, NIVELACION Y REPLANTEO KM 0.06 3,096.34 S/. 185.78 S/. 185.78
04.02 EXCAVACION PARA ESTRUCTURAS m3 471.41 9.02 S/. 4,252.12 S/. 4,252.12
04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 512.40 23.71 S/. 12,149.00 S/. 4,049.67 S/. 4,049.67 S/. 4,049.67
04.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 15,526.69 4.35 S/. 67,541.10 S/. 33,770.55 S/. 33,770.55
04.05 JUNTAS ASFALTICAS m 132.17 4.22 S/. 557.76 S/. 557.76
04.06 CONCRETO F'C=210 KG/CM2, m3 204.96 453.04 S/. 92,855.08 S/. 23,213.77 S/. 23,213.77 S/. 23,213.77 S/. 23,213.77
04.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS S/. 16,199.32
04.07.01 TRAZO, NIVELACION Y REPLANTEO KM 0.11 3,096.34 S/. 340.60 S/. 340.60
04.07.02 EXCAVACION MANUAL DE ZANJAS 0.40 X 1.20 m3 52.80 3.86 S/. 203.81 S/. 203.81
04.07.03 REFINE Y NIVELACION EN TERRENO NORMAL m2 44.00 1.79 S/. 78.76 S/. 78.76
04.07.04 CAMA DE APOYO DE ARENA e=0.15 M m3 6.60 159.14 S/. 1,050.32 S/. 1,050.32
04.07.05 DOBLE PRUEBA HIDRAULICA m3 52.80 0.69 S/. 36.43 S/. 36.43
04.07.06 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO m3 52.80 24.05 S/. 1,269.84 S/. 1,269.84
04.07.07 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C10 D= 2" m 110.00 88.59 S/. 9,744.90 S/. 3,248.30 S/. 3,248.30 S/. 3,248.30
04.07.08 TUBERIA DE PVC A-10 SP D=1/2" INC.ELEM.UNION+2% DESPER m 50.00 3.12 S/. 156.00 S/. 156.00
04.07.09 CONEXIONES DOMICILIARIAS DE AGUA pza 18.00 184.37 S/. 3,318.66 S/. 1,659.33 S/. 1,659.33
04.08 CANAL DE CONCRETO S/. 25,177.28
04.08.01 EXCAVACION MANUAL DE ZANJAS m3 50.22 3.86 S/. 193.85 S/. 193.85
04.08.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 54.00 1.79 S/. 96.66 S/. 96.66
04.08.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 216.00 23.71 S/. 5,121.36 S/. 2,560.68 S/. 2,560.68
04.08.04 CONCRETO f'c=175 kg/cm2 m3 17.10 359.98 S/. 6,155.66 S/. 3,077.83 S/. 3,077.83
04.08.05 CONCRETO F'C=210 KG/CM2, m3 10.80 453.04 S/. 4,892.83 S/. 2,446.42 S/. 2,446.42
04.08.06 JUNTAS DE CONTRACCION, e=2.0 cm m 17.00 8.18 S/. 139.06 S/. 139.06
04.08.07 JUNTAS DE DILATACION, e=2.0 cm m 27.20 15.78 S/. 429.22 S/. 429.22
04.08.08 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,873.25 4.35 S/. 8,148.64 S/. 4,074.32 S/. 4,074.32
05 CONTROL DE CALIDAD DEL CONCRETO S/. 1,050.04
05.01 DISEÑO DE MEZCLAS und 2.00 305.00 S/. 610.00 S/. 610.00
05.02 ENSAYOS DE DENSIDAD DE CAMPO und 2.00 36.67 S/. 73.34 S/. 73.34
05.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 10.00 36.67 S/. 366.70 S/. 183.35 S/. 183.35
06 VARIOS S/. 34,392.88
06.01 REPOSICION Y CAMBIO DE TUBERIAS AVERIADAS m 110.00 70.44 S/. 7,748.40 S/. 7,748.40
06.02 MODIFICACION DE NIVELES DE TAPA DE BUZONES und 4.00 2,611.12 S/. 10,444.48 S/. 5,222.24 S/. 5,222.24
06.03 FLETE TERRESTRE GLB 1.00 2,600.00 S/. 2,600.00 S/. 650.00 S/. 650.00 S/. 650.00 S/. 650.00
06.04 REPOSICION DE MUROS DE ABOBE GLB 1.00 2,500.00 S/. 2,500.00 S/. 2,500.00
06.05 DESBROSE Y DESQUINCHE POR ENSANCHE DE VIA (PROPIEDAD DE TERCERGLB 1.00 11,100.00 S/. 11,100.00 S/. 5,550.00 S/. 5,550.00
S/. 31,965.76 S/. 33,750.47 S/. 79,207.41 S/. 66,584.06 S/. 46,610.50 S/. 28,355.94 S/. 23,771.53 S/. 31,263.77
CRONOGRAMA GANTTPROYECTO:
“MEJORAMIENTO DEL PASAJE ANCASH, DE LA LOCALIDAD DE PARIAHUANCA, PROVINCIA DE CARHUAZ, ANCASH
LOCALIDAD PARIAHUANCADISTRITO PARIAHUANCAPROVINCIA CARHUAZREGION ANCASH
FECHA JUNIO 2014
MES1 MES2
Item Descripción Und. Metrado SEMANA1 SEMANA2 SEMANA3 SEMANA4 SEMANA5 SEMANA6 SEMANA7 SEMANA801 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. und 1.00 7 DIAS
01.02 ALAMCEN Y OFICINA m2 25.00 7 DIAS
02 PAVIMENTO
02.01 OBRAS PRELIMINARES
02.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS GLB 1.00 7 DIAS
02.01.02 TRAZO, NIVELACION Y REPLANTEO KM 0.10 7 DIAS
02.01.03 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA KM 1.00 7 DIAS
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE HASTA EL NIVEL DE SUBRASANTE CON MAQUINARIA m3 123.20 7 DIAS
02.02.02 COMPACTADO SUBRASANTE EN ZONA DE CORTE m2 363.00 7 DIAS
02.02.03 SUB - BASE AFIRMADO DE 0.15 M. FACTOR DE COMPACTACION 1.2 m2 363.00 7 DIAS 7 DIAS
02.02.04 BASE GRANULAR E=0.20 M REND.=2310 M2/DIA FACT. COMPACT.=1.20 m2 122.40 7 DIAS
02.02.05 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 135.00 7 DIAS
02.03 OBRAS DE CONCRETO
02.03.01 ENCOFRADO DE PAVIMENTO RIGIDO m2 61.20 7 DIAS
02.03.02 CONCRETO F'C=210 KG/CM2. EN PAVIMENTO RIGIDO m3 56.70 7 DIAS 7 DIAS
02.03.03 CURADO EN PAVIMENTO RIGIDO m3 56.70 7 DIAS
02.04 JUNTAS DE DILATACION
02.04.01 JUNTAS DE CONTRACCION, e=2.0 cm m 396.25 7 DIAS
02.05 SEÑALIZACION
02.05.01 SEÑALIZACION CON CINTAS DE SEGURIDAD m2 10.20 7 DIAS
03 VEREDAS DE CONCRETO
03.01 OBRAS PRELIMINARES
03.01.01 TRAZO, NIVELACION Y REPLANTEO KM 0.20 7 DIAS
03.02 MOVIMIENTO DE TIERRAS
03.02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 MT m3 15.27 7 DIAS
03.02.02 NIVELACION Y COMPACTACION DE SUBRASANTE CON EQUIPO LIVIANO m2 50.90 7 DIAS
03.02.03 RELLENO CON MATERIAL GRANULAR COMPACTADO m3 15.27 7 DIAS
03.02.04 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 17.56 7 DIAS
03.03 OBRAS DE CONCRETO
03.03.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 30.54 7 DIAS
03.03.02 CONCRETO F'C=140 KG/CM2 m3 15.27 7 DIAS
03.04 JUNTAS DE DILATACION
03.04.01 JUNTAS ASFALTICAS m 120.81
03.04.02 PINTURA CON ESMALTE EN EXTERIOR m2 30.54 PARTIDAS CRITICAS
04 MURO DE CONTENCION
04.01 TRAZO, NIVELACION Y REPLANTEO KM 0.06 7 DIAS
04.02 EXCAVACION PARA ESTRUCTURAS m3 471.41 7 DIAS
04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 512.40 7 DIAS 7 DIAS 7 DIAS
04.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 15,526.69 7 DIAS 7 DIAS
04.05 JUNTAS ASFALTICAS m 132.17 7 DIAS
04.06 CONCRETO F'C=210 KG/CM2, m3 204.96 7 DIAS 7 DIAS 7 DIAS 7 DIAS
04.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.07.01 TRAZO, NIVELACION Y REPLANTEO KM 0.11 7 DIAS
04.07.02 EXCAVACION MANUAL DE ZANJAS 0.40 X 1.20 m3 52.80 7 DIAS
04.07.03 REFINE Y NIVELACION EN TERRENO NORMAL m2 44.00 7 DIAS
04.07.04 CAMA DE APOYO DE ARENA e=0.15 M m3 6.60 7 DIAS
04.07.05 DOBLE PRUEBA HIDRAULICA m3 52.80 7 DIAS
04.07.06 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO m3 52.80 7 DIAS
04.07.07 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C10 D= 2" m 110.00 7 DIAS 7 DIAS 7 DIAS
04.07.08 TUBERIA DE PVC A-10 SP D=1/2" INC.ELEM.UNION+2% DESPER m 50.00 7 DIAS
04.07.09 CONEXIONES DOMICILIARIAS DE AGUA pza 18.00 7 DIAS 7 DIAS
04.08 CANAL DE CONCRETO 7 DIAS
04.08.01 EXCAVACION MANUAL DE ZANJAS m3 50.22 7 DIAS
04.08.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 54.00 7 DIAS
04.08.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 216.00 7 DIAS 7 DIAS
04.08.04 CONCRETO f'c=175 kg/cm2 m3 17.10 7 DIAS 7 DIAS
04.08.05 CONCRETO F'C=210 KG/CM2, m3 10.80 7 DIAS 7 DIAS
04.08.06 JUNTAS DE CONTRACCION, e=2.0 cm m 17.00 7 DIAS
04.08.07 JUNTAS DE DILATACION, e=2.0 cm m 27.20 7 DIAS
04.08.08 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,873.25 7 DIAS 7 DIAS
05 CONTROL DE CALIDAD DEL CONCRETO
05.01 DISEÑO DE MEZCLAS und 2.00 7 DIAS
05.02 ENSAYOS DE DENSIDAD DE CAMPO und 2.00 7 DIAS
05.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 10.00 7 DIAS 7 DIAS
06 VARIOS
06.01 REPOSICION Y CAMBIO DE TUBERIAS AVERIADAS m 110.00 7 DIAS
06.02 MODIFICACION DE NIVELES DE TAPA DE BUZONES und 4.00 7 DIAS 7 DIAS
06.03 FLETE TERRESTRE GLB 1.00 7 DIAS 7 DIAS 7 DIAS 7 DIAS
06.04 REPOSICION DE MUROS DE ABOBE GLB 1.00 7 DIAS
06.05 DESBROSE Y DESQUINCHE POR ENSANCHE DE VIA (PROPIEDAD DE TERCERGLB 1.00 7 DIAS 7 DIAS